Question

In: Accounting

#6 Please Show step by step, so I can solve similar problems, thanks! Give your answer...

#6 Please Show step by step, so I can solve similar problems, thanks!

Give your answer as a whole number but do not round your calculations until you get to the final answer.

Jole uses the high-low method of estimating costs. Jole had total costs of $12,373 at its lowest level of activity, when 2,597 units were sold. When, at its highest level of activity, sales equaled 6,091 units, total costs were $28,081. Jole would estimate fixed costs as: _______

Solutions

Expert Solution

Highest activity level = 6,091 units.

Cost at highest activity level = $ 28,081

Lowest activity level = 2,597 units.

Cost at lowest level = $ 12,373

At first, need to compute the variable cost per unit.

Variable cost per unit = ( Cost at highest level - cost at lowest level) /(units at highest level - units at lowest level)

Variable cost per unit = (28,081 - 12,373) /(6,091-2,597)

Variable cost per unit = 15,708/3,494

Variable cost per unit = $ 4.4957067 per unit.

Inorder to find out fixed cost, it is required to apply variable cost per unit in either highest activity level or lowest activity level.

Total cost = total fixed cost + total variable cost.

At highest activity level,

Total cost = $ 28,081

Total variable cost = 6,091 units x $ 4.4957067per unit.

Total variable cost = $ 27,383.34

28,081 = Fixed cost + 27,383.34

Fixed cost 28,081 - 27,383.34

Fixed cost = $ 697.66

Fixed cost = $ 698.

Hence, $ 698 is the correct answer.

SUMMARY:

Here variable cost per unit is not rounded because when it is rounded it is not possible to get accurate figure of fixed cost. Here, variable cost is applies at highest level. Let us apply it is in lowest level and check whether same figure is getting or not.

At lowest level,

Total cost = total fixed cost + total variable cost.

Total cost = $ 12,373

Total variable cost = 2,597 units x $ 4.4957067

Total variable cost = $ 11,675.35

12,373 = Fixed cost + 11,675.35

Fixed cost = 12,373 - 11,675.35

Fixed cost = $ 697.65

Fixed cost = $ 698.

First of all, need to compute variable cost per unit by applying values in formula and then apply the resulting per unit value at either on highest or lowest activity level.

Hence, $ 698 is the correct answer.


Related Solutions

How can I solve this problem? Can you please show step by step how to solve...
How can I solve this problem? Can you please show step by step how to solve this? Qd = 2,000 − 10P MC = 0.1Q
I need this computer typed so I can read it, and please show work. thanks! Your...
I need this computer typed so I can read it, and please show work. thanks! Your current salary is $100,000 per year. Every year you save 10 percent of your salary and invest it in a 401K plan which provides you a guaranteed return of 6 percent per year. Assume the deposits will be made at the end of each year for the next 40 years. How much will you have at the end of 40 years if your salary...
How can I solve this in Excel? Please show how to solve it in excel step...
How can I solve this in Excel? Please show how to solve it in excel step by step. 1) Speedy Wheels is a wholesale distributor of bicycles for the western United States. Its Inventory Manager, Ricky Sapolo, is currently reviewing the inventory policy for one popular model — a small, one-speed girl's bicycle that is selling at the rate of 250 per month. The administrative cost for placing an order for this model from the manufacturer is $200 and the...
Please show step by step work in a spreadsheet or excel so I can follow along:...
Please show step by step work in a spreadsheet or excel so I can follow along: A federal agency responsible for enforcing laws governing weights and measures routinely inspects packages to determine whether the weight of the contents is at least as great as that advertised on the package. A random sample of 30 containers whose packaging states that the contents weigh 8 ounces was drawn. The weight of each package in ounces can be found in the sheet entitled...
Please, explain your answer clearly (step-by-step), so I can trace the output without using the Visual...
Please, explain your answer clearly (step-by-step), so I can trace the output without using the Visual Studio Program. Please, clearly describe how the mechanism of the loop works. The answers in bold. What is printed by the following code snippet? for (int i = 0; i < 5; i++) {    for (int j = 0; j <= i; j++)    {       cout << i << " ";    } } 0 1 2 3 4 5 0 0...
I need this computer typed so I can read it, and please show work. thanks! You...
I need this computer typed so I can read it, and please show work. thanks! You purchase an ABC 10%, 30 Year bond with a $100 face value for 109.72 What is the yield to maturity of the bond? What is the current yield on the bond? What is the duration of the bond? If you bought the bond today and sold it after 1 year at a YTM of 10% what is your cash flow yield? What is your...
Can someone please advise how to solve this problem step-by-step on a calculator? Thanks! Option to...
Can someone please advise how to solve this problem step-by-step on a calculator? Thanks! Option to wait. Your company is deciding whether to invest in a new machine. The new machine will increase cash flow by $435,000 per year. You believe the new technology used in the machine has a 10 year life. Obsolete 10 years from today. Machine is currently priced at 2.8 Million. Cost of machine will decline $215,000 per year until it reaches $2.155 million, where it...
Please show all work step by step so i can understand Find and classify each critical...
Please show all work step by step so i can understand Find and classify each critical point (as relative maximum, relative minimum, or saddle point) of f(x,y)=2x^3+3x^2+y^2-36x+8y+1
I need a step by step way to solve this, not just an answer please. THX...
I need a step by step way to solve this, not just an answer please. THX On Jan 1, 2017 Sharpsburg, Inc. issued $400,000, ten-year, 10% bonds for $354,200. The bonds pay interest on June 30 and December 31. The market rate is 12%. What is the carrying value of the bonds at the end of the ten years. According to the book the answer should be $400k, NOT $355,452 like another Clegg member answered.
QUESTION (please show your work so that I may understand how to do the problem) thanks...
QUESTION (please show your work so that I may understand how to do the problem) thanks Before you can calculate your test statistic, you’ll have to calculate the SEM. Use the formula in the book/lecture to calculate the SEM. Put your value below. Remember that you will need to calculate the population standard deviation first (remember to use n rather than n-1 for the population standard deviation calculation). Round your response out to two decimal places, if you give more...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT