Question

In: Mechanical Engineering

A local firm manufactures children's toys. The project demand over the next four months for one...

A local firm manufactures children's toys. The project demand over the next four months for one particular model of toy robot is

Month Workdays Forecasted Demand
July 23 3825
August 16 7245
September 20 2770
October 22 4440

Assume that a normal workday is 8 hours. Hiring cost are $350 per worker and firing cost (including severance) are 850 per worker. Holding cost are $4 per aggergate unit held per month. Assume that it requires an average of 1 hour and 40 minutes for one worker to assemble one toy. Shortages are not permitted. Assime that the ending inventory for June was 600 of these toys and the mangager wishes to have at least 800 units on hand at the end of October. Assume that the current workforce level is 35 workers. Find the optimal plan by formulating as a linear program.  

Solutions

Expert Solution

Since there is 600 units ending inventory in June, the demand for July will be reduced to be 3825– 600 = 3225 units. By the same way, the demand for October will be increased to be 4440 + 800 = 5240 units. This is based on a First In First Out policy.

Month

Demand

Days

Units/workr/mo.

Cumulative Units/workr

Cumulative Demand

Worker Req.

July

3225

23

110.4

110.4

3225

30

August

7245

16

76.8

187.2

10470

56

Sept

2770

20

96

283.2

13240

47

Oct

5240

22

105.6

388.8

18480

48

Note:-

1. To calculate the number of units produced per worker for a particular month (column 4), we first calculate the number of units produced per day, which is equal to (8 hr)/(1 hr 40 min/ unit) = 4.8 units/day. Thus, the number of units produced per month is Days available * 4.8. For example, in July, unit/worker/mo. = 23 days * 4.8 units/day – 110.4 units/worker/mo.

2. To calculate the number of workers required for meeting the demand without any stockouts (column 7), for every month, we divide the cumulative demand up to that month (column 6) by the cumulative number of units produced by a worker (column 5) over the corresponding time interval. Then, we know that for any given month, the cumulative demand up to that month will be met if we employ the number of workers indicated in the corresponding cell, and have them work full-time until that month, possibly building anticipatory inventories in certain months, to be consumed in the subsequent months. Obviously, if we want to experience no stockouts over the entire planning horizon, we must employ the maximum number of workers appearing in the aforementioned column (i.e., 56). These workers will need to work full-time for the months of July and August, but they will be under-utilized in the subsequent months of September and October.

  • Table below calculates the production based on 56 workers:

Month

Cumulative Demand

Production

Cumulative Production

Ending Inv.

July

3225

6182

6182

2957

August

10470

4288

10470

0

Sept

13240

2770

13240

0

Oct

18480

5240

18480

800

The total inventory held is 2,957 + 0 + 0 + 800 = 3757 units, which results in an inventory holding cost of (3757)(4) = $15,028.

The cost of hiring is (56-35)(350) = $7,350, giving a total cost of $15,028 + $7,350 = $22,378.

>> Now the plan that corresponds to demand to chase, i.e., the plan that changes the workforce level each month to most closely match the demand, and compute the cost(s) of this plan.

Month

Demand

Days

Unit/worker/mo.

Worker Req./mo.

July

3225

23

110.4

30

August

7245

16

76.8

95

Sept

2770

20

96

29

Oct

5240

22

105.6

50

Month

Cumulative Demand

Production

Cumulative Production

Ending Inv.

July

3225

3225

3312

0

August

10470

7245

10608

0

Sept

13240

2770

13392

0

Oct

18480

5240

18672

800

The total number of workers fired is 5+66 = 71 at a cost of (5+66)(850) = $60,350

The total hired is 65+21 = 86 at a cost of (86)(350) = $30,100.

inventory holding cost is (800)(4) = $3,200.

The total cost of this plan is $60,350 + $30,100 + $3,200 = $93,650.


Related Solutions

The demand for a perishable item over the next four months is 400, 300, 420, and...
The demand for a perishable item over the next four months is 400, 300, 420, and 380 tons, respectively. The supply capacities for the same months are 500,600, 200, and 300 tons The purchase price per ton varies from month to month and is estimated at $100, $140, $120, and $150, respectively. Because the item is perishable, a current month's supply must be consumed within 3 months (starting with current month). The storage cost per ton per month is $3....
A company currently has 100 items in inventory. The demand for the next four months is...
A company currently has 100 items in inventory. The demand for the next four months is 500, 800, 900, and 300 units. Determine the monthly production rate if a level strategy is selected with the goal of ending the fourth month with 400 units in inventory. a. 500 units/month b. 700 units/month c. 900 units/month d. 1100 units/month
A manufacturer of integrated circuits is planning production for the next four months. The forecast demand...
A manufacturer of integrated circuits is planning production for the next four months. The forecast demand for the circuits is shown in the following table. Circuit September October November December IC341 650 875 790 1100 IC256 900 350 1200 1300 At the beginning of September, the warehouse is expected to be completely empty. There is room for no more than 1,800 integrated circuits to be stored. Holding costs for both types is $0.05 per unit per month. Because workers are...
GG Pearl Corp. is a large multinational firm. Over the next two months, the Company is...
GG Pearl Corp. is a large multinational firm. Over the next two months, the Company is expecting to have sales in Europe totaling 500,000,000 Euros, and is also expected to make purchases from vendors in Europe totaling 350,000,000 Euros. The Company is concerned about the volatility in the exchange rates of currencies in which it has transactions, so it has instituted a policy to mitigate exchange rate risk. GG Pearl's hedging policy is as follows: 50% of the net notional...
The Fraley Company, a merchandising firm, has planned the following sales for the next four months:...
The Fraley Company, a merchandising firm, has planned the following sales for the next four months: March April May June Total budgeted sales...... $50,500 $71,450 $93,600 $67,000 All sales at Fraley are on credit. From experience, the company has learned that a month’s sales on account are collected according to the following pattern: Month of sale....................................................... 68% First month following month of sale................. 29% Uncollectible........................................................ 3%       The company requires a minimum cash balance of $5,000 to start a month....
During the next four months Capps Shoes Company must meet the following demand for pair of...
During the next four months Capps Shoes Company must meet the following demand for pair of shoes: 2000 shoes in month 1, 3000 shoes in month 2, 4000 shoes in month 3, and 5000 shoes in month 4. At the beginning of month 1, 500 shoes are on hand. This company has 100 workers. A worker is paid $11.5 per hour in month 1, $11 per hour in month 2, $10.5 per hour in month 3, and $10 per hour...
Budgeted sales in Acer Corporation over the next four months are given below: September October November...
Budgeted sales in Acer Corporation over the next four months are given below: September October November December Budgeted Sales $140,000 $150,000 $170,000 $130,000 25% of the company's sales are for cash and 75% are on account. Collections for sales on account follow a stable pattern as follows: 50% of a month's credit sales are collected in the month of sale, 30% are collected in the month following sale, and 15% are collected in the second month following sale. The remainder...
1. Budgeted sales at O’Brien Vineyards over the next four months are given below: July August...
1. Budgeted sales at O’Brien Vineyards over the next four months are given below: July August September October Budgeted sales $100,000 $160,000 $180,000 $120,000 All of the company's sales are on account. Collections for sales on account follow a pattern as follows: 70% of a month's credit sales are collected in the month of sale, 25% are collected in the month following sale, and the remainder is uncollectible. There is a $20,000 accounts receivable balance that will be collected in...
A firm uses graphical techniques in its aggregate planning efforts. Over the next twelve months (its...
A firm uses graphical techniques in its aggregate planning efforts. Over the next twelve months (its intermediate period), it estimates the sum of demands to be 80,000 units. The firm has 250 production days per year. In January, which has 20 production days, demand is estimated to be 8,000 units. Which of the following is correct? A. the firm must hire workers between December and January B. level production of 320 units per day is below the January requirement C....
Creative Corporation manufactures children's toys. Creative has significant debt outstanding that has been used to buy...
Creative Corporation manufactures children's toys. Creative has significant debt outstanding that has been used to buy equipment and inventory used in its manufacturing process. Creative has positive cash from operating activities during the holiday season (November and December), but negative cash from operating activities during the months preceding the holiday season. Meanwhile, Technology Inc. is a mature, successful software development company with no debt outstanding and very few non-current assets. Which company requires a higher amount of cash on hand?...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT