Question

In: Operations Management

A firm uses graphical techniques in its aggregate planning efforts. Over the next twelve months (its...

A firm uses graphical techniques in its aggregate planning efforts. Over the next twelve months (its intermediate period), it estimates the sum of demands to be 80,000 units. The firm has 250 production days per year. In January, which has 20 production days, demand is estimated to be 8,000 units. Which of the following is correct?

  • A. the firm must hire workers between December and January
  • B. level production of 320 units per day is below the January requirement
  • C. the January requirement is below level production of 400 units
  • D. level production is approximately 400 units per day
  • E. level production is approximately 500 units per day

Solutions

Expert Solution

Answer:

The correct option is “B. level production of 320 units per day is below the January requirement”.

Annual demand = 80000 units

Production days per year = 250 days

January demand = 8000 units

Number of production days in January = 20 days

As per the above days,

January per day requirement = January demand / Number of production days in January = 8000/ 20 = 400 units

However, the level production for the year = Annual demand / Production days per year = 80000 / 250 = 320 units

So, level production of 320 units per day is below the January requirement.

Other options are incorrect as:

A. the firm must hire workers between December and January – No productivity of workers is mentioned, so incorrect.

C. the January requirement is below level production of 400 units – As calculated above Jan requirement is 400 per day, so this statement is incorrect.

D. level production is approximately 400 units per day – As 400 units times 250 days = 100000 units which is more than annual requirement, so incorrect.

E. level production is approximately 500 units per day – As 500 units times 250 days = 125000 units which is more than annual requirement, so incorrect.


Related Solutions

A company is planning its production schedule over the next six months (it is currently the...
A company is planning its production schedule over the next six months (it is currently the end of month 2). The demand (in units) for its product over that timescale is as shown below: Month 3 4 5 6 7 8 Demand 5000 6000 6500 7000 8000 9500 The company currently has in stock: 1000 units which were produced in month 2; 2000 units which were produced in month 1; 500 units which were produced in month 0. The company...
Aggregate Planning Given the projected demands for the next six months, prepare an aggregate plan that...
Aggregate Planning Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time, overtime, subcontract and backorders. Regular time is limited to 150 units per month (Cost per Unit = $20 ). Overtime is limited to a maximum of 30 units per month (Cost per Unit =$30). Units purchased from the subcontractor (Cost per Unit = $26 ) cannot exceed 40 per month and the total purchases from the subcontractor over the 6...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory,...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time, overtime, subcontract and backorders. Regular time is limited to 170 units per month (Cost per Unit = $40 ). Overtime is limited to a maximum of 20 units per month (Cost per Unit =$60). Units purchased from the subcontractor (Cost per Unit = $72 ) cannot exceed 30 per month and the total purchases from the subcontractor over the 6 month period...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory,...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time and overtime, and backorders. The plan must wind up with no units in ending inventory in Period 6. Regular time capacity is 150 units per month. Overtime capacity is 20 units per month. Overtime cost is $30 per unit, backorder cost is $20 per unit, inventory holding cost is $5 per unit, regular time cost of $20 per unit, and beginning inventory...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory,...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time and overtime, and backorders. A level production cost rate of 150 units per month will be used. Backorder cost is $20 per unit, inventory holding cost is $5 per unit, regular time cost of $20 per unit, and beginning inventory is zero. Month Forecast 1 190 2 150 3 150 4 150 5 120 6 140 What is the cost of this...
What is aggregate planning? In the sample aggregate planning problem, change "for fudge for the next...
What is aggregate planning? In the sample aggregate planning problem, change "for fudge for the next four months is 120, 150, 100, and 70 pounds," to "130, 150, 110, and 60 pounds." Carry out the rest of the solution, with changed numbers, making sure, you follow the procedure used for "Level Strategy." The forecasted demand for fudge for the next four months is 120, 150, 100, and 70 pounds. a. What is the recommended production rate if a level strategy...
A firm uses the pure chase strategy of aggregate planning. It produced 1000 units in the...
A firm uses the pure chase strategy of aggregate planning. It produced 1000 units in the last period. Demand in the next period is estimated at 800, and demand over the next six periods (its aggregate planning horizon) is estimated to average 900 units. Which of the following tactics would be most representative of following a chase strategy? add 100 units to inventory in the next period add 200 units to inventory in the next period  hire workers to match...
GG Pearl Corp. is a large multinational firm. Over the next two months, the Company is...
GG Pearl Corp. is a large multinational firm. Over the next two months, the Company is expecting to have sales in Europe totaling 500,000,000 Euros, and is also expected to make purchases from vendors in Europe totaling 350,000,000 Euros. The Company is concerned about the volatility in the exchange rates of currencies in which it has transactions, so it has instituted a policy to mitigate exchange rate risk. GG Pearl's hedging policy is as follows: 50% of the net notional...
A local firm manufactures children's toys. The project demand over the next four months for one...
A local firm manufactures children's toys. The project demand over the next four months for one particular model of toy robot is Month Workdays Forecasted Demand July 23 3825 August 16 7245 September 20 2770 October 22 4440 Assume that a normal workday is 8 hours. Hiring cost are $350 per worker and firing cost (including severance) are 850 per worker. Holding cost are $4 per aggergate unit held per month. Assume that it requires an average of 1 hour...
The PROCOM Corporation is planning its financing for the next six months. PROCOM makes one item,...
The PROCOM Corporation is planning its financing for the next six months. PROCOM makes one item, which it sells through the retail shop in the front of the factory. The planning process was started with profit-and loss computations. Profit is revenue less expenses and revenue is quantity times the unit price. Expenses are made up fixed costs and variable costs. Fixed costs include: rent, salaries, and utilities. Variable costs depend directly on the quantity. These costs are materials and labor....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT