In: Math
A and B together can complete a work in 10 days. A alone can complete the work in 15 days. If B does the work only half a day daily, then in how many days A and B together will complete the work?
A and B together can complete a work in 10 days. A alone can complete the work in 15 days. If B does the work only half a day daily,
B’s 1 day’s work = 1/10− 1/15 = 1/30
B’s 1/2 day’s work = 1/60
(A+B) together will complete work in = 1/15 + 1/60 = 1/12 = 12 days
12 days