In: Accounting
Eire Products is a specialty lubricants company. The Lake Plant produces a single product in three departments: Filtering, Blending, and Packaging. Additional materials are added in the Blending Process when units are 50 to 55 percent complete with respect to conversion. Information for operations in June in the Blending process appear as follows.
Work in process on June 1 consisted of 9,000 barrels with the following costs.
|
Amount |
Degree of completion |
|
|
Filtering costs transferred in |
$ 11,700 |
100% |
|
|
Cost added in Blending |
|
|
|
|
Direct materials |
$ - |
0% |
|
|
Conversion costs |
$ 18,335 |
30% |
|
|
Work in process June 1 |
$ 30,035 |
|
|
|
|
|
|
|
|
During June, 116,000 barrels were transferred in from Filtering at a cost of $150,800. The following costs were added in Blending in June.
Direct materials |
$ 387,500 |
Conversion costs |
$ 538,265 |
Total costs added |
$ 925,765 |
Blending finished 115,000 barrels in June and transferred them to Packaging. At the end of June, there were 10,000 barrels in work-in-process inventory. The units were 60 percent complete with respect to conversion costs. The Blending Department uses FIFO method of process costing.
Required: 1. Prepare a cost of production report for Blending department for June.
2. Journal entries for (1) T/I cost; (2) DM used; (3) CC allocated; (4) units completed
T-accounts of WIP- Blending
For Transferred in 100% unit completed in the previous period. It means the remaining 0% completed in this month. |
For Direct material 0% unit completed in the previous period. It means the remaining 100% completed in this month. |
For Conversion cost 30% unit completed in the previous period. It means the remaining 70% completed in this month. |
Part 1
Part 2
Journal entries | |||
Date | Account title | Debit | Credit |
1 | Work in progress - Blending | 150,800 | |
Work in progress - Filtering | 150,800 | ||
(To record cost of transferred in from Filtering.) | |||
2 | Work in progress - Blending | 387,500 | |
Raw material inventory | 387,500 | ||
(To record direct material used.) | |||
3 | Work in progress - Blending | 538,265 | |
Conversion costs (Labor + Manufacturing overhead) | 538,265 | ||
(To record CC allocated.) | |||
4 | Work in progress - Packaging | 1,035,300 | |
Work in progress - Blending | 1,035,300 | ||
(To record cost of unit transferred to next process.) |
Work in progress - Blending | |||
Beg. Balance | 30,035 | 4 (cost of completed) | 1,035,300 |
1 | 150,800 | ||
2 | 387,500 | ||
3 | 538,265 | ||
End. Balance | 71,300 |