In: Accounting
Nailed It! Construction (Nailed It! or the “Company”), an SEC
registrant, is a construction company that...
Nailed It! Construction (Nailed It! or the “Company”), an SEC
registrant, is a construction company that manufactures commercial
and residential buildings. On March 1, 20X1, the Company entered
into an agreement with a customer, Village Apartments, to construct
a residential apartment building for a fixed price of $1.5 million.
The Company estimates that it will incur costs of $1 million to
complete construction of the apartment building. The apartment
building will only transfer to Village Apartments once the
construction of the entire building is complete. In addition,
Village Apartments has various design requirements that would
require Nailed It! to incur significant costs to rework the
building prior to selling it to a customer other than Village
Apartments.
To construct the apartment building, Nailed It! acquires
standard materials that it regularly uses in construction contracts
for both residential and commercial buildings. These materials are
used to manufacture generic component parts for inclusion in
Village Apartments’ residential buildings. These standard materials
remain interchangeable with other items until they are deployed in
a Village Apartments building. The Company has made the following
purchases and incurred the following costs throughout the
construction progress:
- As of June 30, 20X1, in total, Nailed It! has purchased $75,000
of component parts. As of June 30, 20X1, $25,000 of component parts
remain in inventory and $50,000 have been integrated into the
project. Further, Nailed It! has incurred $12,500 of direct costs
to integrate the component parts into the Village Apartments
construction project during the three months ended June 30,
20X1.
- During the three months ended September 30, 20X1, Nailed It!
purchased an additional $500,000 of component parts ($575,000 in
total). Of the $575,000 of component parts, $325,000 remain in
inventory and $200,000 have been integrated into the project during
the three months ended September 30, 20X1. During the three months
ended September 30, 20X1, Nailed It! incurred an additional $50,000
of direct costs to integrate the component parts into the Village
Apartments construction project.
- As of September 30, 20X1, Nailed It! determined that the
project was over budget and revised its cost estimate from $1
million to $1.25 million.
- As of December 31 20X1, the construction project was completed.
During the three months ended December 31, 20X1, Nailed It!
purchased an additional $425,000 of generic component parts ($1
million in total). Of the $1 million component parts, $0 remain in
inventory and $750,000 were integrated into the project during the
three months ended December 31, 20X1. Nailed It! has incurred
$187,500 of direct costs to integrate the component parts into the
Village Apartments construction project during the three months
ended December 31, 20X1.
If Village Apartments cancels the contract, Nailed It! will be
entitled to reimbursement for costs incurred for work completed to
date plus a margin of 20 percent, which is Case 7: Nailed It!
Construction Page 2 Copyright 2018 Deloitte Development LLC All
Rights Reserved. considered to be a reasonable margin. Nailed It!
will not be reimbursed for any materials that have been purchased
for use in the contract but have not yet been used and are still
controlled by Nailed It!.
Required:
- Does the performance obligation meet any of the criteria for
recognition of revenue over time?
- How should the entity recognize revenue for the satisfaction of
its performance obligation? What amount of revenue should be
recognized for the following periods:
- The three months ended June 30, 20X1?
- The three months ended September 30, 20X1?
- The three months ended December 31, 20X1?