Question

In: Mechanical Engineering

The total cycle time of an automatied fiber placement (AFP) operation (sheet lamination), used to manufacture...

The total cycle time of an automatied fiber placement (AFP) operation (sheet lamination), used to manufacture a section of the airplane fuselage, is 8 hours and 40 minutes. The setup time before the start of the operation is 10 minutes. After each layer is put down, an inspection stage is performed for 5 minutes. The AFP head requires cleaning cycle of 3 minutes every 7 layers.

a. If the part is made of 20 layers, what is the time required (in minutes) to lay down 1 layer?

b. What is the percentage of down time for this operation?

c. What is the total cycle time (in minutes) for making this part, if the lay down speed was doubled?

Solutions

Expert Solution

Assumption: It is assumed that cleaning is not performed at end (i.e. end of 20th cycle ) this is because only 6 layers are deposited after last cleaning and cleaning is required after every 7 layers.

Total Cycle time for AFP operation = 8 Hours40 minutes = 520 minutes.

Setup time before start = 10 minutes

Inspection time after each layer = 5 minnutes

Every 7 layer, cleaning time = 3 minutes.

No. of times cleaning required for 20 layers = 2.

a)

Total Extra time = Setup time + inspection time + Cleaning time

= 10 + 5*20 + 2*3

= 116 minutes

Time for laying down 20 layers = 520-116 = 404 minutes.

Time for laying down single layer = 404/20 = 20.2 minutes = 20 minutes 12 seconds.

b) Percentage of downtime = downtime/ total time * 100

= 116/520 *100

= 22.3 %.

c) Cycle time if lay down speed was doubled = down time + (lay down time / 2)

= 116 + (404/2)

= 318 minutes.


Related Solutions

The total cycle time of an automated fiber placement (AFP) operation (sheet lamination), used to manufacture...
The total cycle time of an automated fiber placement (AFP) operation (sheet lamination), used to manufacture a section of the airplane fuselage, is 8 hours and 40 minutes. The setup time before the start of the operation is 10 minutes. After each layer is put down, an inspection stage is performed for 5 minutes. The AFP head requires cleaning cycle of 3 minutes every 7 layers. 1. If the part is made of 20 layers, what is the time required...
Manufacture of a certain component requires three different machining operations. Machining time for each operation is...
Manufacture of a certain component requires three different machining operations. Machining time for each operation is normally distributed and the three times are independent of one another. The mean values are 15, 30, and 20 minutes respectively. Their standard deviations are 1, 2, and 1.5 minutes respectively. What is the probability that it takes at least 1.5 hour of machining time to produce a randomly selected item
A worker-machine operation was found to involve 4.6 minutes of machine time per cycle in the...
A worker-machine operation was found to involve 4.6 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The worker’s time averaged 3.1 minutes per cycle, and the worker was given a rating of 121 percent (machine rating is 100 percent). Midway through the study, the worker took a 10-minute rest break. Assuming an allowance percentage of 13 percent of work time which is applied only to the worker element (not the machine element), determine...
Manufacture of a certain component requires three different machining operations. Machining time for each operation has...
Manufacture of a certain component requires three different machining operations. Machining time for each operation has a normal distribution, and the three times are independent of one another. The mean values are 15, 20, and 30 min, respectively, and the standard deviations are 2, 1, and 1.7 min, respectively. What is the probability that it takes at most 1 hour of machining time to produce a randomly selected component? (Round your answer to four decimal places.)
Dubai Corporation’s maximum capacity   in   operation cycle is around 14,900 units per year, against total costs...
Dubai Corporation’s maximum capacity   in   operation cycle is around 14,900 units per year, against total costs of $875,000 and the lowest one is 6,000 units with a corresponding total cost of 60% of the high point. The fixed costs constitute of a significant portion. Required: 1.     Find out the variable cost per unit as spelled out by the HLM. Provide proof evidence as reflected by fixed cost under high point and low point of operation. 2.     What would be the case if...
The cycle involved in the operation of an internal combustion engine is called the Otto cycle....
The cycle involved in the operation of an internal combustion engine is called the Otto cycle. Air can be considered to be the working gas and assumed perfect. The cycle consists of the following steps. reversible adiabatic compression from A to B reversible constant volume pressure increase from B to C (from the fuel combustion) reversible adiabatic expansion from C to D reversible constant volume pressure decrease from D to A Determine an expression for the efficiency of this engine...
The company operates a punch press to manufacture machine parts. It is a noisy operation. As...
The company operates a punch press to manufacture machine parts. It is a noisy operation. As a matter of fact, it is common knowledge in the plant that employees working in this location have to shout to be heard, even if you are right next to them. The employer decides to transfer a new employee to the department to monitor the punch press operation. The employee is deaf and the companies thinking was that since the employee had hearing loss...
what is total internal reflection and what is optical fiber communication
what is total internal reflection and what is optical fiber communication
What are the principal polymers used in fiber-reinforced polymers?
What are the principal polymers used in fiber-reinforced polymers?
A national job placement company is interested in developing a model that might be used to...
A national job placement company is interested in developing a model that might be used to explain the variation in starting salaries for college graduates based on the college GPA score. The following data were collected through a random sample of the clients with which this company has been associated. GPA Score Starting Salary (RM) 3.20 3,500 3.40 2,950 2.90 3,000 3.60 3,640 2.80 3,150 2.50 2,900 3.00 3,320 3.60 3,760 2.90 3,200 3.50 3,600 Obtain the relationship between score...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT