In: Accounting
Budget for date X Professional labor compensation $990.000
Audit support department cost $774.000
Professional labor-hours billed to client 18.000 hours
Actual results for date X
Audit support department costs 735.000
Professional labor hours billed to clients 17.500
Actual professional labor cost rate $59 per hours
Audit of this firm was budgeted to take 150 hours of professional labor time. The actual professional labor time spent 160 hours.Compute the cost of audit using a)actual costing b)normal costing c)the variation from normal costing that uses budgeted rates for direct costs. Explain any differences in the job cost
The cost of audit will be the sum total of direct cost and indirect cost
The following information will be required to calculate the total cost
Actual indirect cost = actual Audit support department costs / Professional labor hours billed to clients
= $735000 /17500
=$42 /hour
budgeted direct cost per hour = budgeted Professional labor compensation/ budgeted Professional labor-hours billed to client
=$990000/18000
=$55/hour
Budgeted indirect cost = budgeted Audit support department costs / budgeted Professional labor hours billed to clients
=$774000/18000
=$43/hour
The cost of audit under three different methods are calculated below
Actual costing |
Normal costing |
Variation of normal costing |
||||||||
actual rate |
actual audit hours |
amount($) |
actual rate |
Budgeted rate |
actual audit hours |
amount($) |
Budgeted rate |
actual audit hours |
amount($) |
|
A |
B |
C= A x B |
D |
E |
F=D x E |
|||||
Direct costs |
59 |
160 |
9440 |
59 |
160 |
9440 |
55 |
160 |
8800 |
|
Indirect costs |
42 |
160 |
6720 |
43 |
160 |
6880 |
43 |
160 |
6880 |
|
Total costs |
16160 |
16320 |
15680 |
In calculation in all three methods for cost of audit the actual time spend in audit of 160 hours is taken . in actual costing the actual rate per hour for direct cost is higher than budgeted cost by $4 per hour and indirect cost is taken which is lower than budgeted cost by $1 per hour the total cost is $3 per hour higher than budgeted total cost hence the total cost of audit in actual costing is higher at $16,160 than variation from normal costing which is $15,680
The total cost is highest at normal costing because direct cost rate per hour is taken at actual which are $59/hour and budgeted cost of indirect cost rate at $43 and the total cost is $16,320
It shows that budgeted cost of direct cost per hour is assumed at lower rate per hour and has to looked into further