Question

In: Finance

A). You are evaluating a project with the following cash flows: initial investment is $-12, and...

A).

You are evaluating a project with the following cash flows: initial investment is $-12, and the expected cash flows for years 1 - 3 are $10, $11 and $17 (all cash flows are in millions of dollars). What is this projects NPV? The company's WACC is 10%.

B).

You are evaluating a project with an initial investment of $16.9 million dollars, and expected cash flows of $7 million dollars each for years 1-3. What is the project's simple payback? The corporate WACC is 10%

Solutions

Expert Solution

The NPV is computed as shown below:

= Initial investment + Present value of future cash flows

Present value is computed as follows:

= Future value / (1 + r)n

So, the NPV is computed as follows:

= - $ 12 million + $ 10 million / 1.10 + $ 11 million / 1.102 + $ 17 million / 1.103

= $ 18.95 million Approximately

Payback period represents the time period in which the initial investment in a project is recovered.

Payback period is computed as follows:

The cumulative cash inflow of year 1 and 2 is computed as follows:

= $ 7 million + $ 7 million

= $ 14 million

The cumulative cash inflow of year 1, 2 and 3 is computed as follows:

= $ 7 million + $ 7 million + $ 7 million

= $ 21 million

It means that the initial investment of $ 16.9 million is recovered between year 2 and year 3 and hence the payback period lies between year 2 and year 3 and is computed as follows:

= 2 years + Remaining investment to be recovered / Year 3 cash inflow

= 2 years + ( $ 16.9 million - $ 14 million) / $ 7 million

= 2.41 years Approximately

Feel free to ask in case of any query relating to this question      


Related Solutions

You are evaluating a project with the following cash flows: initial investment is $-23, and the  expected...
You are evaluating a project with the following cash flows: initial investment is $-23, and the  expected cash flows for years 1 - 3 are $12, $9 and $8 (all cash flows are in millions of dollars). What is this projects NPV? The company's WACC is 9%. Express your answer in millions of dollars, rounded to 2 decimals and without the dollar sign. So, if your answer is 23.5678, just enter 23.57.
You are evaluating a project (initial investment is $41,000) that is expected to produce cash flows...
You are evaluating a project (initial investment is $41,000) that is expected to produce cash flows of $5,000 each year for the next ten years and $7,000 each year for the following ten years. The IRR of this project is 12%. The firm’s WACC is 8%. What is the project’s NPV?
You are evaluating a project based on the following: Initial Investment: $1,250,000 Cash Flows: $275,000 per...
You are evaluating a project based on the following: Initial Investment: $1,250,000 Cash Flows: $275,000 per year for 5 years (end of year) Required Return: 10% Required Payback: 5 Years 1. Would you accept or reject the project based on the Net Present Value (NPV)? 2. Would you accept or reject the project based on the Payback Period? 3. Would you accept or reject the project based on the Discounted Payback Period? 4. Based on your answers to Questions 1-3,...
If you are evaluating a project with the following cash flows, for what range of costs...
If you are evaluating a project with the following cash flows, for what range of costs of capital would you accept the project? Year 0 Year 1 Year 2 Year 3 Project CF $1,000 -$700 -$600 -$500 2. You are considering two mutually exclusive projects with the following cash flows. The appropriate cost of capital for Project A is 10%. The appropriate cost of capital for Project B is 14%. Year 0 Year 1 Year 2 Year 3 Project A...
Given the following, calculate the cash flows for the project. Initial investment $365,000 Expected life is...
Given the following, calculate the cash flows for the project. Initial investment $365,000 Expected life is 5 years First Year Revenues: 245,000 First Year Expenses: $70,000 Growth for revenue and expenses: 3 percent per year Straight Line Depreciation over 5 years Salvage Value: $45,000 One-time net working capital investment of $10,000 required at the start of the project This investment is recovered at the end of the project The tax rate is 34 percent Answer the following: What are the...
Solo Corp. is evaluating a project with the following cash flows:
Solo Corp. is evaluating a project with the following cash flows: Year Cash Flow 0 –$ 28,500 1 10,700 2 13,400 3 15,300 4 12,400 5 – 8,900 The company uses a discount rate of 11 percent and a reinvestment rate of 8 percent on all of its projects. Calculate the MIRR of the project using the discounting approach. (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Calculate the MIRR...
Solo Corp. is evaluating a project with the following cash flows:
Solo Corp. is evaluating a project with the following cash flows: Year Cash Flow 0 –$ 28,500 1 10,700 2 13,400 3 15,300 4 12,400 5 – 8,900 The company uses a discount rate of 11 percent and a reinvestment rate of 8 percent on all of its projects. Calculate the MIRR of the project using the discounting approach. (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Calculate the MIRR...
Waste Industries is evaluating a $55,500 project with the following cash flows. Years Cash Flows 1...
Waste Industries is evaluating a $55,500 project with the following cash flows. Years Cash Flows 1 $ 9,120 2 20,200 3 26,600 4 16,300 5 26,300 The coefficient of variation for the project is 0.475. Coefficient of Variation Discount Rate 0 − 0.25 7 % 0.26 − 0.50 9 % 0.51 − 0.75 13 % 0.76 − 1.00 16 % 1.01 − 1.25 19 % Use Appendix B for an approximate answer but calculate your final answer using the formula...
Waste Industries is evaluating a $56,900 project with the following cash flows. Years Cash Flows 1...
Waste Industries is evaluating a $56,900 project with the following cash flows. Years Cash Flows 1 $ 9,710 2 19,200 3 26,500 4 19,800 5 27,300 The coefficient of variation for the project is 0.443. Coefficient of Variation Discount Rate 0 − 0.25 7 % 0.26 − 0.50 9 % 0.51 − 0.75 13 % 0.76 − 1.00 16 % 1.01 − 1.25 19 % Use Appendix B for an approximate answer but calculate your final answer using the formula...
Apple Inc. is evaluating Project Vanguard with the following cash flows:
Apple Inc. is evaluating Project Vanguard with the following cash flows: Year 0 1 2 3 4 Cash Flow ($m) -80 10 20 35 40 (i)  Use the payback rule to determine whether the company should accept the project or not if its payback period cutoff is 4 years. (ii) Use the IRR rule to determine whether the company should accept the project or not if its cost of capital is 10%. (iii) Use the NPV rule to determine whether...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT