Question

In: Finance

Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an...

Payback, NPV, and MIRR

Your division is considering two investment projects, each of which requires an up-front expenditure of $23 million. You estimate that the cost of capital is 9% and that the investments will produce the following after-tax cash flows (in millions of dollars):

Year Project A Project B
1 5 20
2 10 10
3 15 8
4 20 6

What is the regular payback period for each of the projects? Round your answers to two decimal places.

Project A years

Project B years

What is the discounted payback period for each of the projects? Round your answers to two decimal places.

Project A years

Project B years

If the two projects are independent and the cost of capital is 9%, which project or projects should the firm undertake?
-Select-Project AProject BBoth projectsItem 5

If the two projects are mutually exclusive and the cost of capital is 5%, which project should the firm undertake?
-Select-Project AProject BItem 6

If the two projects are mutually exclusive and the cost of capital is 15%, which project should the firm undertake?
-Select-Project AProject BItem 7

What is the crossover rate? Round your answer to two decimal places.
%

If the cost of capital is 9%, what is the modified IRR (MIRR) of each project? Round your answers to two decimal places.

Project A %

Project B %

Solutions

Expert Solution

1) PAYBACK PERIOD:
PROJECT A:
Year Cash flow Cumulative cash flow
0 -23 -23
1 5 -18
2 10 -8
3 15 7
4 20 27
Payback period = 2+8/15 = 2.53 years
PROJECT B:
Year Cash flow Cumulative cash flow
0 -23 -23
1 20 -3
2 10 7
3 8 15
4 6 21
Payback period = 1+3/10 = 1.30 years.
2) DISCOUNTED PAYBACK:
PROJECT A:
Year Cash flow PVIF at 9% PV at 9% Cumulative PV
0 -23 1.00000 -23.00 -23.00
1 5 0.91743 4.59 -18.41
2 10 0.84168 8.42 -10.00
3 15 0.77218 11.58 1.59
4 20 0.70843 14.17 15.76
Discounted Payback period = 2+10/11.58 = 2.86 years
PROJECT B:
Year Cash flow PVIF at 9% PV at 9% Cumulative PV
0 -23 1.00000 -23.00 -23.00
1 20 0.91743 18.35 -4.65
2 10 0.84168 8.42 3.77
3 8 0.77218 6.18 9.94
4 6 0.70843 4.25 14.19
Payback period = 1+4.65/8.42 = 1.55
3) NPV AT 9%.
PROJECT A:
Year Cash flow PVIF at 9% PV at 9%
0 -23 1.00000 -23.00
1 5 0.91743 4.59
2 10 0.84168 8.42
3 15 0.77218 11.58
4 20 0.70843 14.17
NPV= 15.76
PROJECT B:
Year Cash flow PVIF at 9% PV at 9%
0 -23 1.00000 -23.00
1 20 0.91743 18.35
2 10 0.84168 8.42
3 8 0.77218 6.18
4 6 0.70843 4.25
NPV 14.19
If the COC is 9% and the projects are independent, both the projects
are acceptable as the NPV is positive.
4) NPV AT 5%:
PROJECT A:
Year Cash flow PVIF at 5% PV at 5%
0 -23 1.00000 -23.00
1 5 0.95238 4.76
2 10 0.90703 9.07
3 15 0.86384 12.96
4 20 0.82270 16.45
NPV= 20.24
PROJECT B:
Year Cash flow PVIF at 5% PV at 5%
0 -23 1.00000 -23.00
1 20 0.95238 19.05
2 10 0.90703 9.07
3 8 0.86384 6.91
4 6 0.82270 4.94
NPV 16.96
If the projects are mutually exclusive, Project A with higher NPV is to be chosen.
5) NPV with cost of capital of 15%:
PROJECT A:
Year Cash flow PVIF at 15% PV at 15%
0 -23 1.00000 -23.00
1 5 0.86957 4.35
2 10 0.75614 7.56
3 15 0.65752 9.86
4 20 0.57175 11.44
NPV= 10.21
PROJECT B:
Year Cash flow PVIF at 15% PV at 15%
0 -23 1.00000 -23.00
1 20 0.86957 17.39
2 10 0.75614 7.56
3 8 0.65752 5.26
4 6 0.57175 3.43
NPV 10.64
If the projects are mutually exclusive, Project B with higher NPV is to be chosen.
6) Cross over rate is the IRR of the incremental cash flows:
Year Incremental cash flows   (A-B) PVIF at 15% PV at 15% PVIF at 14% PV at 14%
1 -15 0.86957 -13.04 0.87719 -11.44
2 0 0.75614 0.00 0.76947 0.00
3 7 0.65752 4.60 0.67497 3.11
4 14 0.57175 8.00 0.59208 4.74
-0.44 -3.60
The cross over rate can be taken as 15%.
7) MIRR:
PROJECT A:
Year Cash flow FVIF at 9% FV at 9%
1 5 1.29503 6.48
2 10 1.18810 11.88
3 15 1.09000 16.35
4 20 1.00000 20.00
54.71
MRR = (54.71/23)^(1/4)-1= 24.19%
PROJECT B:
Year Cash flow FVIF at 9% FV at 9%
1 20 1.29503 25.90
2 10 1.18810 11.88
3 8 1.09000 8.72
4 6 1.00000 6.00
52.50
MIRR = (52.50/23)^(1/4)-1= 22.92%

Related Solutions

Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an...
Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an up-front expenditure of $24 million. You estimate that the cost of capital is 9% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two decimal places....
Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an...
Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an up-front expenditure of $22 million. You estimate that the cost of capital is 10% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two decimal places....
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $15 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are the...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  4,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are the...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $23 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects' net present...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $23 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  6,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 8,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects' net present values,...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  6,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 7,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $   Project B $   What are the two projects' net present values,...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $23 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 8,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects' net present values,...
1.NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
1.NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 6,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 7,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are...
Problem 10-07 NPV Your division is considering two investment projects, each of which requires an up-front...
Problem 10-07 NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $19 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects' net...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT