Question

In: Accounting

q1: On the basis of the budget reports, management analyzes differences between actual and planned results....

q1: On the basis of the budget reports,

management analyzes differences between actual and planned results.
management may take corrective action.
management may modify the future plans.
All of these answers are correct.

q2: Which one of the statements is correct about controllable costs?

More costs are controllable as one moves downward in management levels.
Variable costs are controllable and fixed costs are not.
A cost is controllable if it is incurred directly in a manager’s division or segment.

Allocated costs are controllable.

q3: In developing a flexible budget within a relevant range of activity,

it is necessary to prepare a budget at 1,000 unit increments.
only fixed costs are included.
it is necessary to relate variable cost data to the activity index chosen.
variable and fixed costs are combined and are reported as a total cost.

q4: The formula for the materials quantity variance is

(AQ × AP) – (AQ × SP).
(AQ × AP) – (SQ × SP).
(AQ × SP) – (SQ × SP).
(SQ × AP) – (SQ × SP).

q5: Using standard costs

makes management by exception more difficult.
increases clerical costs.
makes employees less “cost-conscious.”
provides a basis for evaluating cost control

q6: An unfavorable labor quantity variance may be caused by

worker fatigue or carelessness.
higher pay rates mandated by union contracts.
misallocation of workers.
paying workers higher wages than expected.

q7:Unfavorable materials price and quantity variances are generally the responsibility of the

Price       Quantity
Production department Production Department
Production Department Purchasing Department
Purchasing department Purchasing Department
Purchasing department Production Department

q8: The standard rate of pay is $20 per direct labor hour. If the actual direct labor payroll was $137200 for 7000 direct labor hours worked, the direct labor price (rate) variance is

$3500 favorable.
$3500 unfavorable.
$2800 unfavorable.
$2800 favorable.

q9: The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 2500 units, the actual direct labor cost was $73600 for 4600 direct labor hours worked, the total direct labor variance is

$2500 unfavorable.
$1400 favorable.
$1400 unfavorable.
$875 unfavorable.

q10: Sheridan Companyplanned to use 1 yard of plastic per unit budgeted at $96 a yard. However, the plastic actually cost $95 per yard. The company actually made 4600 units, although it had planned to make only 3800 units. Total yards used for production were 4660. How much is the total materials variance?

$76800 U
$4660 F
$1100 U
$7680 U

Solutions

Expert Solution

QUESTION 1 .
All of these answers are correct.
QUESTION 2 .
Variable costs are controllable and fixed costs are not.
QUESTION 3
It is necessary to relate variable cost data to the activity index chosen.
QUESTION 4
(AQ × SP) – (SQ × SP)
QUESTION 5
Provides a basis for evaluating cost control
QUESTION 6
Paying workers higher wages than expected.
QUESTION 7
Purchasing department & Production Department
QUESTION 8
ACTUAL RATE = WAGES/TOTAL HOURS = 137200/7000 = 19.6
LABOR RATE VARIANCE = (STANDARD RATE – ACTUAL RATE ) * ACTUAL HOURS
= (20- 19.6) 7000
= 0.4 * 7000 = 2800 FAVORABLE
QUESTION 9
TOTAL LABOR VARIANCE = STANDARD COST – ACTUAL COST
= 2 direct labor hours * 2500 units * 15 per hour – 73600
=75000-73600
=1400 FAVORABLE
QUESTION 10
TOTAL MATERIAL VARIANCE = STANDARD COST FOR ACTUAL QUANTITY – ACTUAL COST
STANDARD COST FOR ACTUAL QUANTITY = 4660*96 = 447360
ACTUAL COST = 4660 * 9 = 442700
TOTAL MATERIAL VARIANCE = 447360-442700 = 4660 F


Related Solutions

What term describes: 'the forecasting of differences between actual and planned outcomes, and the implementation of...
What term describes: 'the forecasting of differences between actual and planned outcomes, and the implementation of action, before the event, to avoid such differences'? Direct control Variance analysis Budgeting d)Feedback control
Which of the following is being fulfilled when management compares the budget to actual? results? A....
Which of the following is being fulfilled when management compares the budget to actual? results? A. Planning B. Directing C. Controlling D. Adjusting
1. Reports that only compare actual results to static budget estimates. Group of answer choices Balanced...
1. Reports that only compare actual results to static budget estimates. Group of answer choices Balanced Scorecard Production budgets Performance reports Flexible budgets 2. A report displaying the measurement of KPI's. Group of answer choices Balanced Scorecard Flexible Budget Performnce Report Key Performance Indicator Report 3. A part of an organization whose management is responsible for planning and controlling certain specific activities. Group of answer choices Responsibility center A segment A division A transfer center 4. Operating income divided by...
Management accounting measures, analyzes, and reports financial and nonfinancial information to internal managers. The goal is...
Management accounting measures, analyzes, and reports financial and nonfinancial information to internal managers. The goal is to use past performance to predict the future. The internal reports should plainly inform managers of the financial results of actual operations. The reports should also show how activities can be changed to affect and improve what will happen in the future. Business operations are complex sets of activities, and to maximize profit considerable information, analysis, and decision making is required in advance of...
The budgeted and actual results for June 2020 are as follows: Budget Actual Production (units) 150,000...
The budgeted and actual results for June 2020 are as follows: Budget Actual Production (units) 150,000 150,500 Direct material A 300,000m2 £675,000 316,050m2 £695,310 Direct material B 900,000 £18,000 1,053,500 £21,070 Direct labour 37,500 hours £318,750 37,625 hours £323,575 Fixed overheads £287,500 £300,623.75 You are required to: Calculate all possible variances from the information provided above for June and use the variances to reconcile the actual cost of production with the standard cost of production. Evaluate the variances calculated in...
A variance is the difference between a budgeted, planned, or standard cost and the actual amount...
A variance is the difference between a budgeted, planned, or standard cost and the actual amount incurred/sold. Variances can be computed for both costs and revenues. Identify and explain the types of variance analysis tools, which can be used in a production department of a manufacturing company, which specialises in spare parts for cars
While many organizational costs can be planned for, the actual results may vary from the initial...
While many organizational costs can be planned for, the actual results may vary from the initial projections. Assessing how these variances impact the bottom line is an essential task of many managers. For this Assignment, review the information in the scenario posted in the entry titled Week 5 Assignment located in the Doc Sharing link. You will utilize the information in this week’s Resources and your course text to consider how variance analysis and the results obtained from conducting such...
Individual case study Management accounting measures analyzes and reports financial and nonfinancial information to internal managers....
Individual case study Management accounting measures analyzes and reports financial and nonfinancial information to internal managers. The goal is to use past performance to predict the future. The internal reports should plainly inform managers of the financial results of actual operations. The reports should also show how activities can be changed to affect and improve what will happen in the future. Business operations are complex sets of activities, and to maximize profit considerable information, analysis, and decision making is required...
Individual Case Analysis(35%) Management accounting measures analyzes and reports financial and nonfinancial information to internal managers....
Individual Case Analysis(35%) Management accounting measures analyzes and reports financial and nonfinancial information to internal managers. The goal is to use past performance to predict the future. The internal reports should plainly inform managers of the financial results of actual operations. The reports should also show how activities can be changed to affect and improve what will happen in the future. Business operations are complex sets of activities, and to maximize profit considerable information, analysis, and decision making is required...
Discuss the differences between the accrual basis and the cash basis of accounting ( we did...
Discuss the differences between the accrual basis and the cash basis of accounting ( we did mention it in previous discussion forum) What's the differences between cash flows and cash forecast? You might want to interview a banker or small business owner, asking them how they use the particular statement in decision making
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT