Question

In: Statistics and Probability

Ina works in a juice firm and has to develop the production plan for the lemon...

Ina works in a juice firm and has to develop the production plan for the lemon and the orange juice concentrates. The fruits (lemon and orange) that she needs to make the juice are not the bottleneck but Ina is concerned about the other main ingredients that go into making the juice: a water-based solution, sugar, and a vitamin mix. Checking with the ERP system tells her that she has 10.3 metric tons of the water solution, 2.92 metric tons of sugar, and 2030 kg of vitamin mix. The recipe tells her to use 47 kg of water solution to make a metric ton of lemon drink and 72 kg of water solution to make a metric ton of orange drink. For the lemon drink she also needs 24 kg of sugar and 24 kg of vitamin mix. The orange drink needs 16 kg of sugar and 10 kg of vitamin mix.

From the sales department, Ina knows that the lemon soft drink sells at 60 SEK/metric ton and the orange drink sells at 75 SEK/metric ton. (SEK = Swedish krona).

How much lemon drink should Ina produce to maximize revenue?

Give your answer in metric tons and round to one decimal place.

How much orange drink should Ina produce to maximize revenue?

Give your answer in metric tons and round to one decimal.

How much revenue can Ina generate with the optimal production plan?

Round your answer to the nearest integer

Solutions

Expert Solution

This is a linear programming problem.

Given Information:

Water Solution (kg) Sugar (Kg) Vitamin Mix (Kg) Profit per kg
Constraints
Orange Mix 72 16 10 0.06 SEK
Lemon Mix 47 24 24 0.075 SEK
Availability 10300 kg 2920 kg 2030 kg

The linear programming can be formulated as follows:

Let the quantity of orange mix be x and lemon mix be y

Maximize Z = 0.06x + 0.075y

Subject to constraints:

72x + 47y < = 10300

16x + 24y <= 2920

10x + 24y <= 2030

x,y >= 0

The linear programming can be solved using excel:

Step 1: Put the data onto the spreadsheet

Step 2: The maximize function can be defined as follows:

Step 3: The water solution constraint can be defined as follows:

Step 4: The sugar constraint can be defined as follows:

Step 5: The vitamin mix constraint can be defined as follows:

Step 6: Go to data --> solver

Step 7: Now select the data and click solve

Production of lemon drink to maximize revenues: 0.0343 metric tonnes or 34.3 kg

Production of Orange drink to maximize revenues: 0.1206 metric tonnes or 120.6 kgs

Maximum Revenue = 9812.7 SEK per metric ton


Related Solutions

Develop a production plan and calculate the annual cost for a firm whose demand forecast is...
Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,300; winter, 8,200; spring, 6,800; summer, 12,300. Inventory at the beginning of fall is 515 units. At the beginning of fall you currently have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on...
An orange juice processing plant has three production lines. The production lines fill juice into 400...
An orange juice processing plant has three production lines. The production lines fill juice into 400 ml packages. The production manager of the plant would like to know if the production lines are all filling the packages the same amount. A sample of 25 packages from each production line are taken and the data is saved in juice.csv. The production manager would like to know: “are the three production lines filling packages with the same amount of juice, on average?”....
My daily water/fliud intake is usually 6 cups of water, a cup of lemon juice and...
My daily water/fliud intake is usually 6 cups of water, a cup of lemon juice and a small can of soft drink (cola). How does this compare with recommended values? What factors need to be considered in deciding how much water must be consumed?
Guardian Inc. is trying to develop an asset-financing plan. The firm has $510,000 in temporary current...
Guardian Inc. is trying to develop an asset-financing plan. The firm has $510,000 in temporary current assets and $410,000 in permanent current assets. Guardian also has $610,000 in fixed assets. Assume a tax rate of 40 percent. a. Construct two alternative financing plans for Guardian. One of the plans should be conservative, with 90 percent of assets financed by long-term sources, and the other should be aggressive, with only 56.25 percent of assets financed by long-term sources. The current interest...
Guardian Inc. is trying to develop an asset-financing plan. The firm has $410,000 in temporary current...
Guardian Inc. is trying to develop an asset-financing plan. The firm has $410,000 in temporary current assets and $310,000 in permanent current assets. Guardian also has $510,000 in fixed assets. Assume a tax rate of 30 percent. a. Construct two alternative financing plans for Guardian. One of the plans should be conservative, with 70 percent of assets financed by long-term sources, and the other should be aggressive, with only 56.25 percent of assets financed by long-term sources. The current interest...
Guardian Inc. is trying to develop an asset-financing plan. The firm has $470,000 in temporary current...
Guardian Inc. is trying to develop an asset-financing plan. The firm has $470,000 in temporary current assets and $370,000 in permanent current assets. Guardian also has $570,000 in fixed assets. Assume a tax rate of 30 percent. a. Construct two alternative financing plans for Guardian. One of the plans should be conservative, with 90 percent of assets financed by long-term sources, and the other should be aggressive, with only 56.25 percent of assets financed by long-term sources. The current interest...
Guardian Inc. is trying to develop an asset-financing plan. The firm has $530,000 in temporary current...
Guardian Inc. is trying to develop an asset-financing plan. The firm has $530,000 in temporary current assets and $430,000 in permanent current assets. Guardian also has $630,000 in fixed assets. Assume a tax rate of 30 percent. a. Construct two alternative financing plans for Guardian. One of the plans should be conservative, with 70 percent of assets financed by long-term sources, and the other should be aggressive, with only 56.25 percent of assets financed by long-term sources. The current interest...
Guardian Inc. is trying to develop an asset-financing plan. The firm has $380,000 in temporary current...
Guardian Inc. is trying to develop an asset-financing plan. The firm has $380,000 in temporary current assets and $280,000 in permanent current assets. Guardian also has $480,000 in fixed assets. Assume a tax rate of 30 percent. a. Construct two alternative financing plans for Guardian. One of the plans should be conservative, with 80 percent of assets financed by long-term sources, and the other should be aggressive, with only 56.25 percent of assets financed by long-term sources. The current interest...
Guardian Inc. is trying to develop an asset-financing plan. The firm has $340,000 in temporary current...
Guardian Inc. is trying to develop an asset-financing plan. The firm has $340,000 in temporary current assets and $240,000 in permanent current assets. Guardian also has $440,000 in fixed assets. Assume a tax rate of 25 percent. a. Construct two alternative financing plans for Guardian. One of the plans should be conservative, with 90 percent of assets financed by long-term sources, and the other should be aggressive, with only 56.25 percent of assets financed by long-term sources. The current interest...
James is anylyzing the production process of the firm. By Assuming a separate person works at...
James is anylyzing the production process of the firm. By Assuming a separate person works at each step in the process, please answer the following questions. STEP #1 -> STEP #2--> Step #3--> Step #4--> 15 min/unit 40 min/unit 30 min/unit 20 min/unit =======(A)======== What is the maximum output of the current system in 8 hours? =========(B)============ How would the maximum output of the system be increased in 8 hours if he hired a new worker for the bottleneck of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT