In: Accounting
Fellar Corp. has identified the following
information:
Activity cost pools | |
Materials handling | $39,200 |
Machine maintenance | 32,560 |
Cost drivers | |
Number of material moves | 700 |
Number of machine hours | 74,000 |
Required:
1. Calculate the activity rate for each cost pool.
(Round your answers to 2 decimal places.)
2. Determine the amount of overhead assigned to
Fellar’s products if they have the following activity demands:
(Round your intermediate calculations to 2 decimal places
and final answers to the nearest whole dollar
amount.)
Product A | Product B | ||
Number of material moves | 560 | 140 | |
Number of machine hours | 42,900 | 31,100 | |
Statement showing computations | ||||||||
Particulars | Amount a | Activity Driver | No of Activity b | Cost per activity c= a/b | No of Activity of Product A d | Cost Allocated to Product A c*d | No of Activity of Product B e | Cost Allocated to Product B c*e |
Material Handling | 39,200.00 | No of material Moves | 700.00 | 56.00 | 560.00 | 31,360.00 | 140.00 | 7,840.00 |
Machine Maintenance | 32,560.00 | No of Machine hours | 74,000.00 | 0.44 | 42,900.00 | 18,876.00 | 31,100.00 | 13,684.00 |
Total Overhead | 71,760.00 | 50,236.00 | 21,524.00 | |||||
a) | ||||||||
Activity | Activity Rate | |||||||
Material Handling | 56.00 | |||||||
Machine Maintenance | 0.44 | |||||||
b) | ||||||||
Overhead assigned to product A | 50,236.00 | |||||||
Overhead assigned to product B | 21,524.00 | |||||||
71,760.00 | ||||||||