The cumulative timing approach was used to time a job and its elements. Use the following stop-watch readings to determine the duration of each element (5) • Stop-watch reading after element 1 is 0.03 minutes • Stop-watch reading after element 2 is 0.07 minutes • Stop-watch reading after element 3 is 0.13 minutes • Stop-watch reading after element 4 is 0.18 minutes • Stop-watch reading after element 5 is 0.24 minutes

Solutions

Expert Solution

Stop-watch reading after element 1 = 0.03 minutes

Hence, duration of element 1 = 0.03 minutes

Stop-watch reading after element 2 = 0.07 minutes

Hence, duration of element 2 = (Stop-watch reading after element 2) - (Stop-watch reading after element 1) = 0.07 - 0.03 = 0.04 minutes

Stop-watch reading after element 3 = 0.13 minutes

Hence, duration of element 3 = (Stop-watch reading after element 3) - (Stop-watch reading after element 2) = 0.13 - 0.07 = 0.06 minutes

Stop-watch reading after element 4 = 0.18 minutes

Hence, duration of element 4 = (Stop-watch reading after element 4) - (Stop-watch reading after element 3) = 0.18 - 0.13 = 0.05 minutes

Stop-watch reading after element 5 = 0.24 minutes

Hence, duration of element 5 = (Stop-watch reading after element 5) - (Stop-watch reading after element 4) = 0.24 - 0.18 = 0.06 minutes

Hence, we get answers as:

Duration of element 1 = 0.03 minutes

Duration of element 2 = 0.04 minutes

Duration of element 3 = 0.06 minutes

Duration of element 4 = 0.05 minutes

Duration of element 5 = 0.06 minutes

-----------------------------------------------------------------------------------------------------------------------

In case of any doubt, please ask through the comment section before Upvote/downvote.


Related Solutions

The following reaction is the Haber process used to make ammonia from its elements. Use this...
The following reaction is the Haber process used to make ammonia from its elements. Use this information for questions 1 & 2               N2(g) + 3H2(g) <--> 2NH3(g)              DHo = +92 kJ ___1. Suppose the reaction flask is already at equilibrium, but then the volume of the reaction flask is then reduced. What will happen? a) [NH3] will lower.                                              c) The reaction will proceed right. b) [Reactants] will increase                          d) Nothing will occur. It will stay at equilibrium. ___2. Suppose...
Was the Elements an exposition of the most advanced mathematics of its time? (Elements by Euclid)
Was the Elements an exposition of the most advanced mathematics of its time? (Elements by Euclid)
A time study was conducted on a job that contains four elements. The observed times and...
A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table. OBSERVATIONS (minutes per cycle) Element Performance Rating 1 2 3 4 5 6 1 90 % 0.44 0.50 0.43 0.45 0.44 0.46 2 85 1.50 1.56 1.47 1.51 1.49 1.52 3 110 0.84 0.89 0.77 0.83 0.86 0.80 4 100 1.10 1.14 1.08 1.16 1.16 1.26 a. Determine the average cycle time for...
The use of the allowance for doubtful accounts approach: a. should not be used if the...
The use of the allowance for doubtful accounts approach: a. should not be used if the customers are highly concentrated. b. increases the allowance for doubtful accounts when an account is written off. c. results in a matching of uncollectible accounts expense with the related sales that led to the expense. d. does not recognize an expense when the allowance is set up
Consider the following information on job times and due dates (in hours). Job Job Time Due...
Consider the following information on job times and due dates (in hours). Job Job Time Due Date A 4.00 8.00 B 1.50 5.00 C 4.50 9.00 D 4.25 17.00 E 2.25 6.00 You are asked to determine the processing sequence using Shortest Processing Time (SPT) and Earliest Due Date (EDD) rule; and to decide which sequence is better for average job flow time and the average job tardiness performance measures. FORMAT FOR ENTRIES: • Sequence should be entered in the...
1.Which of the following is a commonly used cost approach in business valuation? Multiples analysis approach...
1.Which of the following is a commonly used cost approach in business valuation? Multiples analysis approach Capital cost approach Transaction cost analysis approach 2. The two market approaches commonly used in the business valuation are multiple analysis and: project analysis. transactions analysis. market analysis. NPV analysis. 3. The transaction approach is difficult to use because: transactions data are typically as reliable as the data available for multiples analysis, especially when they are associated with a private firm. transactions involving the...
Use the CLV concept to explain the typical pricing approach used by major carriers.
Use the CLV concept to explain the typical pricing approach used by major carriers.
Given the following mix of job, job lengths, and arrival times, assume a time slice of...
Given the following mix of job, job lengths, and arrival times, assume a time slice of 10 and compute the completion for each job and average response time for the FCFS, SJN, SRT, and Round Robin Scheduling Algorithm. jobs arrival time CPU cycle(ms) A 0 16 B 3 2 C 5 11 D 9 6 E 10 1 F 12 9 G 14 4 H 16 14 I 17 1 J 19 8
Bloom's taxonomy is not only an approach that is advocated for use at GCU, its quite...
Bloom's taxonomy is not only an approach that is advocated for use at GCU, its quite popular in general because it provides educators some concrete ways to generalize and assess learning. Have you used it in your own teaching? If so, please feel free to share your experience with it!
1) Find out the standard time using the following data: Average time for machine elements =...
1) Find out the standard time using the following data: Average time for machine elements = 6 min. Average time for manual elements = 4 min. Performance rating = 110% Allowances = 10% of normal time 2) The actual observed time for an operation was 1 minute per piece. If the performance rating of the operator was 120 and a 5 per cent personal time is to be provided, the standard time in minute per piece is: