In: Finance
You are considering a project which has a set up cost of $4,895, and which yields $1,500, $2,000, and $2,500 at the end of the first, second, and third years after set-up. What is the internal rate of return on this project (Hint: trial and error)
a. |
5% |
|
b. |
10% |
|
c. |
15% |
Calculation of IRR :
IRR is the rate at which the PV of Cash Inflows = PV of cash
outflows i.e NPV of the project is 0.
[CF1/(1+IRR)1] + [CF2/(1+IRR)2] + [CF3/(1+IRR)3] + - CF0 = 0
We have,
CF0 = -$4895
CF1 = $1,500
CF2 = $2,000
CF3 = $2,500
We have to find out the discounting rate at which NPV of the
project is 0.
ASSUMING IRR TO BE 5.00% AND COMPUTING
Since NPV is positive at discount rate of 5%, IRR should be more
than 5%.
ASSUMING IRR TO BE 10.00% AND COMPUTING
Since NPV is almost zero at discount rate of 10.00%, IRR is 10.00%.
Note : Present Value Factor have been calculated as = (1/1+r)n
Where
r= Required rate of Return (Discount rate)
n= No of Periods
Option b) is correct.