In: Accounting
Question 6
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $684,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:
Activity Cost Pool |
Activity Measure |
Estimated Overhead Cost |
Expected Activity |
||
Machining |
Machine-hours |
$ |
200,000 |
10,000 |
MHs |
Machine setups |
Number of setups |
$ |
100,000 |
200 |
setups |
Product design |
Number of products |
$ |
84,000 |
2 |
products |
General factory |
Direct labor-hours |
$ |
300,000 |
12,000 |
DLHs |
Activity Measure |
Product Y |
Product Z |
Machine-hours |
7,000 |
3,000 |
Number of setups |
50 |
150 |
Number of products |
1 |
1 |
Direct labor-hours |
8,000 |
4,000 |
What is the activity rate for the Machining activity cost pool?
Group of answer choices
$20 per machine hour
$16.66 per machine hour
$57 per machine hour
$68.4 per machine hour
Question 7
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $684,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:
Activity Cost Pool |
Activity Measure |
Estimated Overhead Cost |
Expected Activity |
||
Machining |
Machine-hours |
$ |
200,000 |
10,000 |
MHs |
Machine setups |
Number of setups |
$ |
100,000 |
200 |
setups |
Product design |
Number of products |
$ |
84,000 |
2 |
products |
General factory |
Direct labor-hours |
$ |
300,000 |
12,000 |
DLHs |
Activity Measure |
Product Y |
Product Z |
Machine-hours |
7,000 |
3,000 |
Number of setups |
50 |
150 |
Number of products |
1 |
1 |
Direct labor-hours |
8,000 |
4,000 |
What is the activity rate for the Product Design activity cost pool?
Group of answer choices
$25 per direct labor hour
$42,000 per product
$84,000
$1 per product
Question 8
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $684,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:
Activity Cost Pool |
Activity Measure |
Estimated Overhead Cost |
Expected Activity |
||
Machining |
Machine-hours |
$ |
200,000 |
10,000 |
MHs |
Machine setups |
Number of setups |
$ |
100,000 |
200 |
setups |
Product design |
Number of products |
$ |
84,000 |
2 |
products |
General factory |
Direct labor-hours |
$ |
300,000 |
12,000 |
DLHs |
Which of the following is a product-level activity?
Group of answer choices
General factory activity
Machine setups activity
machining activity
Product design activity
Question 9
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $684,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:
Activity Cost Pool |
Activity Measure |
Estimated Overhead Cost |
Expected Activity |
||
Machining |
Machine-hours |
$ |
200,000 |
10,000 |
MHs |
Machine setups |
Number of setups |
$ |
100,000 |
200 |
setups |
Product design |
Number of products |
$ |
84,000 |
2 |
products |
General factory |
Direct labor-hours |
$ |
300,000 |
12,000 |
DLHs |
Activity Measure |
Product Y |
Product Z |
Machine-hours |
7,000 |
3,000 |
Number of setups |
50 |
150 |
Number of products |
1 |
1 |
Direct labor-hours |
8,000 |
4,000 |
Using the ABC system, how much overhead cost would be assigned to Product Y?
Group of answer choices
$228,000
$277,000
$407,000
$456,000
Answer(6):-
Activity rate for the Machining activity cost pool is calculated on the basis of machine hours available.
Total Machine Hours = 7000 +3000 =10,000
MAchining overhead cost = 200,000
Activity rate for the Machining activity cost pool = 200,000/10,000 = $20 per machine hour.
Answer(7):-
Activity rate for the Product Design activity cost pool is calculated on the basis of Number of products.
Number of products = 1 + 1 = 2
Product design overhead cost = 84,000
Activity rate for the Product Design activity = 84,000 /2 = $42,000 per product.
Answer(8):-
The correct answer is Product design activity.
Becasue for product design overhead cost activity is calculated or apportioned on product on the basis of number of product.
Answer(9):- The correct answer is $407,000.
Activity Cost Pool | Overhead cost (u) | Activity Measure | (v) | Activity Rate (W) = (u/v) |
Machining | 200,000 | Machine Hour | 10,000 | 20 |
Machine Setup | 100,000 | Number of setup | 200 | 500 |
Product Design | 84,000 | Number of products | 2 | 42000 |
General factory | 300,000 | Direct labour hour | 12,000 | 25 |
684,000 | ||||
Product Y | ||||
Machining | 140,000 | (7000*20) | ||
Machine Set up | 25,000 | (50*500) | ||
Product Design | 42,000 | (42,000*1) | ||
General factory | 200,000 | (8000*25) | ||
Total cost | 407,000 |