In: Accounting
Consider a project to supply 105 million postage stamps per year to the U.S. Postal Service for the next five years. You have an idle parcel of land available that cost $1,730,000 five years ago; if the land were sold today, it would net you $1,805,000 aftertax. The land can be sold for $1,753,000 after taxes in five years. You will need to install $5.6 million in new manufacturing plant and equipment to actually produce the stamps; this plant and equipment will be depreciated straight-line to zero over the project’s five-year life. The equipment can be sold for $700,000 at the end of the project. You will also need $600,000 in initial net working capital for the project, and an additional investment of $55,000 in every year thereafter. Your production costs are .53 cents per stamp, and you have fixed costs of $1,100,000 per year. If your tax rate is 21 percent and your required return on this project is 11 percent, what bid price should you submit on the contract?
Formula sheet
A1 | B | C | D | E | F | G | H | I | J |
2 | |||||||||
3 | Bid Price will be the price at which NPV of cash flows of the project is zero. | ||||||||
4 | To calculated NPV, Free cash flow can be calculated as follows: | ||||||||
5 | Free Cash Flow = Operating Cash Flow - Capital Expenditures - Change in working capital | ||||||||
6 | Operating Cash Flow = EBIT*(1-Tax Rate)+Depreciation | ||||||||
7 | Tax Rate | 0.21 | |||||||
8 | MARR | 0.11 | |||||||
9 | Bid Price | 0.550545335444076 | |||||||
10 | Immediate investment in plant and Equipment | 5600000 | |||||||
11 | Opportunity cost for land | 1805000 | |||||||
12 | Initial investment in working capital | 600000 | |||||||
13 | Annual Investment in working capital | 55000 | |||||||
14 | Production cost per stamp | 0.53 | |||||||
15 | Number of stamps sold per year | 105000000 | |||||||
16 | b) | ||||||||
17 | Depreciation each year can be calculated as follows: | ||||||||
18 | Machine Cost | =D10 | |||||||
19 | Life of Machine | 5 | years | ||||||
20 | Salvage value | 0 | |||||||
21 | Depreciation per year | =(Investment - Salvage Value)/Expected life of equipment | |||||||
22 | =(D18-D20)/D19 | =(D18-D20)/D19 | |||||||
23 | |||||||||
24 | Free cash flow can be calculated as followed: | ||||||||
25 | Year | 0 | 1 | 2 | 3 | 4 | 5 | ||
26 | Revenue | =$D$15*$D$9 | =$D$15*$D$9 | =$D$15*$D$9 | =$D$15*$D$9 | =$D$15*$D$9 | |||
27 | Production cost | =-$D$15*$D$14 | =-$D$15*$D$14 | =-$D$15*$D$14 | =-$D$15*$D$14 | =-$D$15*$D$14 | |||
28 | Depreciation | =-$D$22 | =-$D$22 | =-$D$22 | =-$D$22 | =-$D$22 | |||
29 | Operating Income Before Tax (EBIT) | =SUM(E26:E28) | =SUM(F26:F28) | =SUM(G26:G28) | =SUM(H26:H28) | =SUM(I26:I28) | |||
30 | Tax (@21%) | =-E29*$D$7 | =-F29*$D$7 | =-G29*$D$7 | =-H29*$D$7 | =-I29*$D$7 | |||
31 | After Tax operating income (EBIT*(1-T)) | =E29+E30 | =F29+F30 | =G29+G30 | =H29+H30 | =I29+I30 | |||
32 | Add Depreciation | =-E28 | =-F28 | =-G28 | =-H28 | =-I28 | |||
33 | Operating Cash Flow | =E31+E32 | =F31+F32 | =G31+G32 | =H31+H32 | =I31+I32 | |||
34 | Initial investment in plant and equipment | =-D10 | |||||||
35 | Opportunity cost for land | =-D11 | |||||||
36 | Net Proceed from sales of land | 1753000 | |||||||
37 | Investment in working capital | =-D12 | =-$D$13 | =-$D$13 | =-$D$13 | =-$D$13 | =-$D$13 | ||
38 | Free Cash Flow | =SUM(D33:D37) | =SUM(E33:E37) | =SUM(F33:F37) | =SUM(G33:G37) | =SUM(H33:H37) | =SUM(I33:I37) | ||
39 | |||||||||
40 | c) | ||||||||
41 | NPV of the project is present value of future cash flows discounted at required rate of return less the initial investment. | ||||||||
42 | Given the following cash flow and WACC, NPV for the project can be calculated as follows: | ||||||||
43 | Year | 0 | 1 | 2 | 3 | 4 | 5 | ||
44 | Free Cash Flow (FCF) | =D38 | =E38 | =F38 | =G38 | =H38 | =I38 | ||
45 | MARR (i) | =D8 | |||||||
46 | (P/F,i,n) for each year | =1/((1+$D45)^E43) | =1/((1+$D45)^F43) | =1/((1+$D45)^G43) | =1/((1+$D45)^H43) | =1/((1+$D45)^I43) | |||
47 | Present Value of cash flows = FCF*(P/F,i,n) | =E44*E46 | =F44*F46 | =G44*G46 | =H44*H46 | =I44*I46 | |||
48 | Present value if future cash flows | =SUM(E47:I47) | =SUM(E47:I47) | ||||||
49 | |||||||||
50 | NPV for Project | =Present value fo future cash flows - Initial investment | |||||||
51 | =D48+D44 | =D48+D44 | |||||||
52 | |||||||||
53 | Hence NPV of the project is | =D51 | |||||||
54 | Using goal seek function in excel, the bid price can be found at which NPV will be zero. | ||||||||
55 | Thus Bid Price should be | =D9 | |||||||
56 |
Goal Seek setting