Question

In: Accounting

Consider a project to supply 105 million postage stamps per year to the U.S. Postal Service...

Consider a project to supply 105 million postage stamps per year to the U.S. Postal Service for the next five years. You have an idle parcel of land available that cost $1,730,000 five years ago; if the land were sold today, it would net you $1,805,000 aftertax. The land can be sold for $1,753,000 after taxes in five years. You will need to install $5.6 million in new manufacturing plant and equipment to actually produce the stamps; this plant and equipment will be depreciated straight-line to zero over the project’s five-year life. The equipment can be sold for $700,000 at the end of the project. You will also need $600,000 in initial net working capital for the project, and an additional investment of $55,000 in every year thereafter. Your production costs are .53 cents per stamp, and you have fixed costs of $1,100,000 per year. If your tax rate is 21 percent and your required return on this project is 11 percent, what bid price should you submit on the contract?

Solutions

Expert Solution

Formula sheet

A1 B C D E F G H I J
2
3 Bid Price will be the price at which NPV of cash flows of the project is zero.
4 To calculated NPV, Free cash flow can be calculated as follows:
5 Free Cash Flow = Operating Cash Flow - Capital Expenditures - Change in working capital
6 Operating Cash Flow = EBIT*(1-Tax Rate)+Depreciation
7 Tax Rate 0.21
8 MARR 0.11
9 Bid Price 0.550545335444076
10 Immediate investment in plant and Equipment 5600000
11 Opportunity cost for land 1805000
12 Initial investment in working capital 600000
13 Annual Investment in working capital 55000
14 Production cost per stamp 0.53
15 Number of stamps sold per year 105000000
16 b)
17 Depreciation each year can be calculated as follows:
18 Machine Cost =D10
19 Life of Machine 5 years
20 Salvage value 0
21 Depreciation per year =(Investment - Salvage Value)/Expected life of equipment
22 =(D18-D20)/D19 =(D18-D20)/D19
23
24 Free cash flow can be calculated as followed:
25 Year 0 1 2 3 4 5
26 Revenue =$D$15*$D$9 =$D$15*$D$9 =$D$15*$D$9 =$D$15*$D$9 =$D$15*$D$9
27 Production cost =-$D$15*$D$14 =-$D$15*$D$14 =-$D$15*$D$14 =-$D$15*$D$14 =-$D$15*$D$14
28 Depreciation =-$D$22 =-$D$22 =-$D$22 =-$D$22 =-$D$22
29 Operating Income Before Tax (EBIT) =SUM(E26:E28) =SUM(F26:F28) =SUM(G26:G28) =SUM(H26:H28) =SUM(I26:I28)
30 Tax (@21%) =-E29*$D$7 =-F29*$D$7 =-G29*$D$7 =-H29*$D$7 =-I29*$D$7
31 After Tax operating income (EBIT*(1-T)) =E29+E30 =F29+F30 =G29+G30 =H29+H30 =I29+I30
32 Add Depreciation =-E28 =-F28 =-G28 =-H28 =-I28
33 Operating Cash Flow =E31+E32 =F31+F32 =G31+G32 =H31+H32 =I31+I32
34 Initial investment in plant and equipment =-D10
35 Opportunity cost for land =-D11
36 Net Proceed from sales of land 1753000
37 Investment in working capital =-D12 =-$D$13 =-$D$13 =-$D$13 =-$D$13 =-$D$13
38 Free Cash Flow =SUM(D33:D37) =SUM(E33:E37) =SUM(F33:F37) =SUM(G33:G37) =SUM(H33:H37) =SUM(I33:I37)
39
40 c)
41 NPV of the project is present value of future cash flows discounted at required rate of return less the initial investment.
42 Given the following cash flow and WACC, NPV for the project can be calculated as follows:
43 Year 0 1 2 3 4 5
44 Free Cash Flow (FCF) =D38 =E38 =F38 =G38 =H38 =I38
45 MARR (i) =D8
46 (P/F,i,n) for each year =1/((1+$D45)^E43) =1/((1+$D45)^F43) =1/((1+$D45)^G43) =1/((1+$D45)^H43) =1/((1+$D45)^I43)
47 Present Value of cash flows = FCF*(P/F,i,n) =E44*E46 =F44*F46 =G44*G46 =H44*H46 =I44*I46
48 Present value if future cash flows =SUM(E47:I47) =SUM(E47:I47)
49
50 NPV for Project =Present value fo future cash flows - Initial investment
51 =D48+D44 =D48+D44
52
53 Hence NPV of the project is =D51
54 Using goal seek function in excel, the bid price can be found at which NPV will be zero.
55 Thus Bid Price should be =D9
56

Goal Seek setting


Related Solutions

Consider a project to supply 105 million postage stamps per year to the U.S. Postal Service...
Consider a project to supply 105 million postage stamps per year to the U.S. Postal Service for the next five years. You have an idle parcel of land available that cost $1,730,000 five years ago; if the land were sold today, it would net you $1,805,000 aftertax. The land can be sold for $1,753,000 after taxes in five years. You will need to install $5.6 million in new manufacturing plant and equipment to actually produce the stamps; this plant and...
Consider a project to supply 105 million postage stamps per year to the U.S. Postal Service...
Consider a project to supply 105 million postage stamps per year to the U.S. Postal Service for the next five years. You have an idle parcel of land available that cost $1,950,000 five years ago; if the land were sold today, it would net you $2,150,000 aftertax. The land can be sold for $2,350,000 after taxes in five years. You will need to install $5.45 million in new manufacturing plant and equipment to actually produce the stamps; this plant and...
Consider a project to supply 98 million postage stamps per year to the U.S. Postal Service...
Consider a project to supply 98 million postage stamps per year to the U.S. Postal Service for the next five years. You have an idle parcel of land available that cost $1,695,000 five years ago; if the land were sold today, it would net you $1,770,000 aftertax. The land can be sold for $1,746,000 after taxes in five years. You will need to install $5.25 million in new manufacturing plant and equipment to actually produce the stamps; this plant and...
Consider a project to supply 98 million postage stamps per year to the U.S. Postal Service...
Consider a project to supply 98 million postage stamps per year to the U.S. Postal Service for the next five years. You have an idle parcel of land available that cost $1,695,000 five years ago; if the land were sold today, it would net you $1,770,000 aftertax. The land can be sold for $1,746,000 after taxes in five years. You will need to install $5.25 million in new manufacturing plant and equipment to actually produce the stamps; this plant and...
Consider a project to supply 90 million postage stamps per year to the U.S. Postal Service...
Consider a project to supply 90 million postage stamps per year to the U.S. Postal Service for the next five years. You have an idle parcel of land available that cost $1,655,000 five years ago; if the land were sold today, it would net you $1,730,000 aftertax. The land can be sold for $1,738,000 after taxes in five years. You will need to install $4.85 million in new manufacturing plant and equipment to actually produce the stamps; this plant and...
Consider a project to supply 92 million postage stamps per year to the U.S. Postal Service...
Consider a project to supply 92 million postage stamps per year to the U.S. Postal Service for the next five years. You have an idle parcel of land available that cost $1,665,000 five years ago; if the land were sold today, it would net you $1,740,000 aftertax. The land can be sold for $1,740,000 after taxes in five years. You will need to install $4.95 million in new manufacturing plant and equipment to actually produce the stamps; this plant and...
Consider a project to supply 102 million postage stamps per year to the U.S. Postal Service...
Consider a project to supply 102 million postage stamps per year to the U.S. Postal Service for the next five years. You have an idle parcel of land available that cost $1,715,000 five years ago; if the land were sold today, it would net you $1,790,000 aftertax. The land can be sold for $1,750,000 after taxes in five years. You will need to install $5.45 million in new manufacturing plant and equipment to actually produce the stamps; this plant and...
Consider a project to supply 60 million postage stamps per year to the U.S. Postal Service...
Consider a project to supply 60 million postage stamps per year to the U.S. Postal Service for the next five years. You have an idle parcel of land available that cost $760,000 five years ago; if the land were sold today, it would give you $912,000 after taxes. Three years ago, you purchased some equipment for $60,000. This equipment has a current book value of $40,000 and a current market value of $30,000. The land and equipment can be used...
Consider a project to supply 104 million postage stamps per year to the U.S. Postal Service...
Consider a project to supply 104 million postage stamps per year to the U.S. Postal Service for the next five years. You have an idle parcel of land available that cost $1,725,000 five years ago; if the land were sold today, it would net you $1,800,000 aftertax. The land can be sold for $1,752,000 after taxes in five years. You will need to install $5.55 million in new manufacturing plant and equipment to actually produce the stamps; this plant and...
Consider a project to supply 97 million postage stamps per year to the U.S. Postal Service...
Consider a project to supply 97 million postage stamps per year to the U.S. Postal Service for the next five years. You have an idle parcel of land available that cost $1,690,000 five years ago; if the land were sold today, it would net you $1,765,000 aftertax. The land can be sold for $1,745,000 after taxes in five years. You will need to install $5.2 million in new manufacturing plant and equipment to actually produce the stamps; this plant and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT