In: Finance
Consider a project to supply 98 million postage stamps per year to the U.S. Postal Service for the next five years. You have an idle parcel of land available that cost $1,695,000 five years ago; if the land were sold today, it would net you $1,770,000 aftertax. The land can be sold for $1,746,000 after taxes in five years. You will need to install $5.25 million in new manufacturing plant and equipment to actually produce the stamps; this plant and equipment will be depreciated straight-line to zero over the project’s five-year life. The equipment can be sold for $595,000 at the end of the project. You will also need $565,000 in initial net working capital for the project, and an additional investment of $48,000 in every year thereafter. Your production costs are .46 cents per stamp, and you have fixed costs of $1,030,000 per year. If your tax rate is 24 percent and your required return on this project is 8 percent, what bid price should you submit on the contract? (Do not round intermediate calculations and round your answer to 5 decimal places, e.g., 32.16161.)
Operating cash flow (OCF) each year = income after tax + depreciation - working capital investment
In year 5, the entire working capital investment is recovered, and hence the investment in working capital is negative
The cost of the land 5 years ago is a sunk cost and irrelevant. The $1.77 million after-tax sale price of the land today is an opportunity cost and is relevant. The $1.746 million after-tax sale price of the land in 5 years is a relevant cash flow as well.
after-tax salvage value = salvage value - tax on profit on sale of equipment
The entire salvage value is profit, and hence subject to tax. This is because the equipment is fully depreciated, and its book value is zero.
NPV is calculated using NPV function in Excel
First, we assume the bid price to be $0.40 per stamp.
NPV at $0.40 bid price per stamp is -$25,509,884
The project will only be accepted if the NPV is positive.
We use GoalSeek function in Excel to find the bid price per stamp at which NPV becomes zero. This is the minimum bid price for the contract, as the project will not be accepted below this price.
The bid price per stamp is $0.48578