Question

In: Finance

Consider equity holders’ choice between two mutually exclusive projects: Project A and Project B. Both have...

Consider equity holders’ choice between two mutually exclusive projects: Project A and Project
B. Both have upfront cost at Year 0 of $50 million and equity plans to finance entirely with debt.
Cash flows in the year following the investment are partially state-contingent. Project A has a
certain cash flow of $60 million regardless of the state of the world in Year 1, but Project B has a

cash flow of $90 in the Good state, and a cash flow of $20 million in the Bad state. The risk-
neutral probability of the Good state is 1/2.

Assume that the risk-free rate is 0% and that equity holders are considering the choice of two
mutually exclusive debt markets to tap: Naïve and Sophisticated. In the Naïve market, potential
lenders are not aware of agency costs of debt and always believe that equity holders will take
actions that maximize firm value regardless of capital structure. In the Sophisticated market,

potential lenders are aware of agency costs of debt and the incentives of equity to engage in ex-
post appropriation of wealth from bondholders. In particular, Sophisticated market lenders

understand the risk-shifting incentive of equity that arises from the convexity of their claim in
the firm’s asset volatility.


Answer the following questions:
1. Which project maximizes firm value?
2. Assume equity taps the Naïve market
a. What promised face value of debt must equity issue to raise the $50 million
upfront cost?
b. Based on the face value you calculated in (a), calculate the payoff to equity in
each project and find which project they will take.
c. What is the expected payoff to the Naïve investors given the promised face value
from (a) and project choice from (b)?
3. Assume equity taps the Sophisticated market
a. What promised face value of debt must equity issue to raise the $50 million
upfront cost?
b. Assume that equity cannot commit to taking a certain project ex-ante. Which
project do they select in this case?

Solutions

Expert Solution

1. Risk free rate, r = 0%

NPV (project A) = -50 + 60/(1+r) = +10

NPV (project B) = -50 + 0.5*[90/(1+r) + 20/(1+r)] = +5

NPV (project A) > NPV (project B)

Project A maximizes the firm value.

2. (a) NAIVE MARKET - The equity will raise the $50 million by issuing a bond with face value $50 to naive lenders.

(b) In project A, the equity holders will have to pay back $50 million to the bondholders from the payoff of the project. Hence, Payoff to equity holders = $10 million.

In project B, there are two scenarios with equal likelihood (probability = 0.5):

1. If the payoff from project B is $90 million, the debt holders will get back their $50 million, and equity holders' payoff is $40 million from the project.

2. If the payoff from project B is only $20 million, debt holders will receive only $20 million and lose $30 million. Equity holders will not receive anything and their payoff will be $0 million.

Average payoff for equity holders from project B = 0.5*$40 million + 0.5*$0 million = $20 million.

Payoff to equity holders (t=1)
Project Poor Good
A 10 10
B 0 40
Difference (B-A) -10 30
Probability 0.5 0.5
Average payoff 10

Therefore, equity holders are better off with project B than project A.

(c) Payoff to debt holders:

Project B :  -$50 million + 0.5*($50 million + $20 million) = -$15 million

Payoff to bondholders (t=1)
Project Poor Good
A 50 50
B 20 50
Difference (B-A) -30 0
Probability 0.5 0.5
Average payoff -15

3. (a) As long as the sophisticated market lenders have lent only up to $30 million, the equity holders would have no incentive to go for project B (riskier project). In this case, the interests of the debt holders and equity holders would be aligned.

Therefore, the sophisticated market lenders would lend only $30 million.

Payoff to bondholders (t=1)
Project Poor Good
A 30 30
B 20 30
Difference (B-A) -10 0
Probability 0.5 0.5
Average payoff -5
Payoff to equity holders (t=1)
Project Poor Good
A 30 30
B 0 60
Difference (B-A) -30 30
Probability 0.5 0.5
Average payoff 0

(b) In case they can not select a project ex ante, even equity holders would then prefer project A.


Related Solutions

An entrepreneur has a choice of two mutually exclusive investment projects, Project A and Project B....
An entrepreneur has a choice of two mutually exclusive investment projects, Project A and Project B. Each lasts for one time period and the firm has no other projects. Project A will result in a cash flow of £27 million in the good state and £10 million in the bad state. Each outcome is equally likely. Project B will result in a cash flow of £34 million in the good state and zero in the bad state. Each outcome is...
a firm must choose between two mutually exclusive projects, a & b. project a has an...
a firm must choose between two mutually exclusive projects, a & b. project a has an initial cost of $10000. its projected net cash flows are $800, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. project b has an initial cost of $14000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. the firm’s cost of capital is 6.00%. choose the...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. At what cost of capital would the firm be...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0   –$ 68,000   –$ 83,000 1 48,000 47,000 2 43,000 56,000 3 38,000 59,000 The cash flows of Project A are expressed in real terms, whereas those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 5 percent. Calculate the NPV for each project. (Do not round intermediate calculations and round your answers...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial investment of $1500, and will yield $800 of cash inflows for the next three years. Project B requires an initial investment of $5000, and will yield $1,500 of cash inflows for the next five years. The required return on each project is 10%. a. What are the net present values of Project A and Project B? b. What is the problem with using the...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial investment of $1000, and will yield $500 of cash inflows for the next three years. Project B requires an initial investment of $3,500, and will yield $1,000 of cash inflows for the next five years. The required return on both projects is 10%.                                                                                                      (13 marks total) a. What are the net present values of Project A and Project B? b. What is...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial investment of $1500, and will yield $800 of cash inflows for the next three years. Project B requires an initial investment of $5000, and will yield $1,500 of cash inflows for the next five years. The required return on each project is 10%.                                                                                                                                        (13 marks total) a.   What are the net present values of Project A and Project B?                 b.  ...
Consider the following two mutually exclusive project. Relevant discount rate for both projects are 12 percent....
Consider the following two mutually exclusive project. Relevant discount rate for both projects are 12 percent. Year CF Project A (Rp) CF Project B (Rp) 0 (2,000,000) (2,300,000) 1 900,000 550,000 2 800,000 650,000 3 950,000 708,000 4 978,000 1,155,000 5 300,000 2,000,000 a. If you apply the discounted payback criterion, which project will you choose? Why? b. If you apply the IRR criterion, which project will you choose? Why? Hint: Range A: 29-31% ; Range B: 24-26% c. If...
ABC Inc. has a choice between two mutually exclusive projects, Project I has cash flows of...
ABC Inc. has a choice between two mutually exclusive projects, Project I has cash flows of −$48,000, $20,200, $20,500, and $19,000 for Years 0 to 3, respectively. Project II has a cost of $45,000 and annual cash inflows of $18,500 for 3 years. At what rate would you be indifferent between these two projects? Which project will you take if the required return is 10%. (1+1 points) Answer ABC Inc. needs 150,000 boxes of parts per year over the next...
Suppose that you have two mutually exclusive projects. A and B. Project A has cash flows...
Suppose that you have two mutually exclusive projects. A and B. Project A has cash flows of CF0, CF1, CF2, CF3, CF4, CF5. (Years 0-5). Project B has cash flow of CF0, CF1, CF2, CF3. The discount rate for the projects is 10.5%. a) Analyze these two projects and recommend a project to accept. b) Carefully outline all your analysis and reasoning and discuss your methodologies for arriving at your solution in detail. Project A Project B CF0 (4,650.00) (8,300.00)...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT