Question

In: Accounting

California Circuits Company (3C) manufactures a variety of components. Its Valley plant specializes in two electronic...

California Circuits Company (3C) manufactures a variety of components. Its Valley plant specializes in two electronic components used in circuit boards. These components serve the same function and perform equally well. The difference in the two products is the raw material. The XL-D chip is the older of the two components and is made with a metal that requires a wash prior to assembly. Originally, the plant released the wastewater directly into a local river. Several years ago, the company was ordered to treat the wastewater before its release, and it installed relatively expensive equipment. While the equipment is fully depreciated, annual operating expenses of $248,000 are still incurred for wastewater treatment.

Two years ago, company scientists developed an alloy with all of the properties of the raw materials used in XL-D that generates no wastewater. Some prototype components using the new material were produced and tested and found to be indistinguishable from the old components in every way relating to their fitness for use. The only difference is that the new alloy is more expensive than the old raw material. The company has been test-marketing the newer version of the component, referred to as XL-C, and is currently trying to decide its fate.

Manufacturing of both components begins in the Production Department and is completed in the Assembly Department. No other products are produced in the plant. The following provides information for the two components:

XL-D XL-C
Units produced 100,000 25,000
Raw material costs per unit $11.80 $13.80
Direct labor-hours per unit—Production 0.1 0.1
Direct labor-hours per unit—Assembly 0.4 0.4
Direct labor rate per hour—all labor $19.00 $19.00
Machine-hours per unit—Production 1.6 1.6
Machine-hours per unit—Assembly 0.4 0.4
Testing hours per unit (all in production) 3.0 3.0
Shipping weight per unit (pounds) 1.0 1.6
Wastewater generated per unit (gallons) 10.0 0.0

Annual overhead costs for the two departments follow:

Production Department Assembly Department
Supervision $ 98,000 $ 238,000
Material handling 92,000 39,000
Testing 148,000 0
Wastewater treatment 248,000 0
Depreciation on equipment 398,000 98,000
Shipping 6,800 118,000
Total $ 990,800 $ 493,000

The company president believes that it’s foolish to continue producing two essentially equivalent products. At the same time, the corporate image is somewhat tarnished because of a toxic dump found at another site (not the Valley plant). The president would like to be able to point to the Valley plant as an example of company research and development (R&D) working to provide an environmentally friendly product. The controller points out to the president that the company’s financial position is shaky, and it cannot afford to make products in any way other than the most cost-efficient one.

Required:

a. 3C’s current cost accounting system charges overhead to products based on direct labor cost using a single plantwide rate. What product costs will it report for the two products if the current allocation system is used?

b. The controller recently completed an executive education course describing the two-stage allocation procedure. Assume that the first stage allocates costs to departments and the second stage allocates costs to products. The controller believes that the costs will be more accurate if machine-hours are used to allocate Production Department costs and labor-hours are used to allocate Assembly Department costs. What product costs will be reported for the two products if the two-stage allocation process is used?

d. The president argues that an activity-based costing system would provide even better costs. The company decides to compute product costs assuming an ABC system is implemented only in the Production Department. Overhead in Assembly will continue to be allocated based on direct labor cost. The cost drivers selected for the activity-based costing system are as follows.
  

Overhead Item Driver
Supervision Direct labor-hours
Material handling Material cost
Testing Testing hours
Wastewater treatment Wastewater generated
Depreciation on equipment Machine-hours
Shipping Weight


What product costs would be reported if this ABC system were implemented? Assume that the production mix and costs would remain as originally planned.

Solutions

Expert Solution

Answer:

Answer-a:
Overhead rate = (Production overhead + Assembly overhead) / Total direct labor cost
                           = ($990,800 + 493,000) / (100,000*$9.5 + 25,000*$9.5)
                           = 125%
XL-C XL-D
Raw material $          11.80 $        13.80
Direct labor-Production                1.90              1.90
Direct labor-Assembly                7.60              7.60
Overhead @125%              11.88            11.88
Total cost $          33.18 $        35.18
Answer-b:
Overhead rate (Production department) =Production overhead / Total machine hours
                                                                         = $990,800 / (100,000*1.6 + 25,000*1.6)
                                                                         = $4.95
Overhead rate (Assembly department) =Assembly overhead / Total machine hours
                                                                         = $493,000 / (100,000*0.4 + 25,000*0.4)
                                                                         = $9.83
XL-C XL-D
Raw material $          11.80 $        13.80
Direct labor-Production                1.90              1.90
Direct labor-Assembly                7.60              7.60
Overhead production @$4.95/mh                7.92              7.92
Overhead assembly @$9.83/mh                3.93              3.93
Total cost $          33.15 $        35.15
Answer-d:
Production overhead Calculation:
Activity Driver Volume Cost Rate
Supervision Direct lab hr (100,000*0.1 + 25,000*0.1) = 12,500 hours 98000 7.84
Material handling Mat. Cost (100,000*11.80 + 25,000*13.80) = $1,525,000 92000 6%
Testing Test hrs (100,000*3 + 25,000*3) = 375,000 hours 148000 0.39
Wastewater treatment Waste (100,000*10 + 25,000*0) = 1,000,000 gal 248000 0.25
Depreciation Machn hrs (100,000*1.6 + 25,000*1.6) = 200,000 hours 398000 1.99
Shipping Weight (100,000*1 + 25,000*1.6) = 140,000 lbs 6800 0.05
Assembly overhead rate = $493,000 / (100,000*0.4 + 25,000*0.4) = $9.86
XL-C XL-D
Raw material $          11.80 $        13.80
Direct labor-Production                1.90              1.90
Direct labor-Assembly                7.60              7.60
Overhead production:
Supervision                7.84              7.84
Material handling                0.71              0.83
Testing                0.39              0.39
Wastewater treatment                0.25              0.25
Depreciation                1.99              1.99
Shipping                0.05              0.05
Overhead assembly @$9.86/dlh                3.93              3.93
Total cost $          36.46 $        38.58

Related Solutions

Fanning Analytics manufactures a variety of electronic products. The company is considering introducing its most exciting...
Fanning Analytics manufactures a variety of electronic products. The company is considering introducing its most exciting product; a new digital instrument panel for customized classic cars. This panel allows the car owner to customize the complete set of instruments for the vehicle. Output display may be analog or digital, with many styles of display using apps that may be purchased, downloaded, and installed with a micro SD card. Market studies indicate that the “Fully Customizable Instrument Panel” (FCIP) may be...
Vancouver manufacturing Ltd. manufactures a variety of high quality electronic components. Data from the last three...
Vancouver manufacturing Ltd. manufactures a variety of high quality electronic components. Data from the last three months are presented below: July August September Direct materials partial productivity 0.76 0.77 0.78 Overtime hours worked 60 65 62 Defect rate 1.00% 0.95% 0.92% On time delivery 97.0% 97.3% 97.0% Set up time (average in hours) 5.90 5.85 5.80 Number of machine breakdowns 3 2 2 Downtime (hours) 15.0 11.5 11.0 Number of products returned 5 4 3 Throughput time (hours) 10.0 9.8...
A company manufactures electronic components. 2 in 10 are of such high quality that they can...
A company manufactures electronic components. 2 in 10 are of such high quality that they can be sold at a premium. We refer to those high quality components as HQ components. A component is sampled at random for QA, and it is put back to the others after inspection. This process is done a total of 5 times. What is the probability that: At least 2 components are NOT HQ
An assembly plant orders a large shipment of electronic circuits each month. The supplier claims that...
An assembly plant orders a large shipment of electronic circuits each month. The supplier claims that the population proportion of defective circuits is ρ=0.04. When a shipment​ arrives, the plant manager selects a random sample of 300 circuits that are tested and the sample proportion of defective circuits is computed. This result is used for a hypothesis test to determine if there is sufficient evidence to conclude that the population proportion of defectives circuits from this supplier is greater than...
An electronic firm manufactures circuits to produce 30 amps. The UCL and LCL on the mean...
An electronic firm manufactures circuits to produce 30 amps. The UCL and LCL on the mean of the circuits for samples of size 4 were computed to be LCL = 27.15 and UCL = 33.04. The UCL and LCL for the sample range were estimated to be LCL = 0 and UCL = 5.75. These control limits were used to monitor the circuits produced for 13 time periods, yielding the following data: Time Period Sample amp measurements 1 2 3...
Sweetwater Company manufactures two products, Mountain Mist and Valley Stream. The company prepares its master budget...
Sweetwater Company manufactures two products, Mountain Mist and Valley Stream. The company prepares its master budget on the basis of standard costs. The following data are for March: Standards Mountain Mist Valley Stream Direct materials 3 ounces at $14.50 per ounce 4 ounces at $17.30 per ounce Direct labor 5 hours at $60.50 per hour 6 hours at $81 per hour Variable overhead (per direct labor-hour) $48 $53.50 Fixed overhead (per month) $368,068 $399,360 Expected activity (direct labor-hours) 6,680 7,800...
Sweetwater Company manufactures two products, Mountain Mist and Valley Stream. The company prepares its master budget...
Sweetwater Company manufactures two products, Mountain Mist and Valley Stream. The company prepares its master budget on the basis of standard costs. The following data are for March: Standards Mountain Mist Valley Stream Direct materials 3 ounces at $14.80 per ounce 4 ounces at $17.20 per ounce Direct labor 5 hours at $60.20 per hour 6 hours at $78 per hour Variable overhead (per direct labor-hour) $48 $53.20 Fixed overhead (per month) $364,425 $399,360 Expected activity (direct labor-hours) 6,450 7,800...
Sweetwater Company manufactures two products, Mountain Mist and Valley Stream. The company prepares its master budget...
Sweetwater Company manufactures two products, Mountain Mist and Valley Stream. The company prepares its master budget on the basis of standard costs. The following data are for March: Standards Mountain Mist Valley Stream Direct materials 3 ounces at $14.90 per ounce 4 ounces at $16.60 per ounce Direct labor 5 hours at $60.10 per hour 6 hours at $76 per hour Variable overhead (per direct labor-hour) $48 $52.60 Fixed overhead (per month) $342,225 $398,580 Expected activity (direct labor-hours) 5,850 7,800...
Sweetwater Company manufactures two products, Mountain Mist and Valley Stream. The company prepares its master budget...
Sweetwater Company manufactures two products, Mountain Mist and Valley Stream. The company prepares its master budget on the basis of standard costs. The following data are for March: Standards Mountain Mist Valley Stream Direct materials 3 ounces at $14.90 per ounce 4 ounces at $16.60 per ounce Direct labor 5 hours at $60.10 per hour 6 hours at $76 per hour Variable overhead (per direct labor-hour) $48 $52.60 Fixed overhead (per month) $342,225 $398,580 Expected activity (direct labor-hours) 5,850 7,800...
Sweetwater Company manufactures two products, Mountain Mist and Valley Stream. The company prepares its master budget...
Sweetwater Company manufactures two products, Mountain Mist and Valley Stream. The company prepares its master budget on the basis of standard costs. The following data are for March: Standards Mountain Mist Valley Stream Direct materials 3 ounces at $14.80 per ounce 4 ounces at $17.20 per ounce Direct labor 5 hours at $60.20 per hour 6 hours at $78 per hour Variable overhead (per direct labor-hour) $48 $53.20 Fixed overhead (per month) $364,425 $399,360 Expected activity (direct labor-hours) 6,450 7,800...