In: Civil Engineering
Provide definitions for each of the folowing dont copy paste from google
concurrency group
movement
NEMA phase numbering
overlap
phase
ring
ring barrier diagram
The ring barrier diagram-
The ring barrier diagram specifies the safe sequencing of phases (and thus the movements that they control) at a signalized intersection.
Movement and Phase-
The movement and the phase are often used interchangeably,but
are distinct and mean different things.Firstly the term movement
can be defined as the response of the user to a "go" indication.
This response has two attributes: The courier direction from which
the user originates and the turn which the user makes. The
compass direction normally includes one of the following
designations: eastbound, westbound, northbound,
or southbound. The turn designation includes left turn, through, or
right turn.
We can also say whether a movement is opposed or not by another
movement by using the terms protected,
permitted, or not opposed. A protected movement has the unambiguous
right-of-way, while a permitted
movement may continue through the intersection only when there is a
large enough (and safe) gap in the
opposing traffi c movement.
Left turn movements are designated with odd
numbers (1, 3, 5, and 7) and through movements are designated as
even numbers (2, 4, 6, and 8). While right
turn movements are often given the same number as their compatible
through movements, they are sometimes
given the same right digit with a leading “1.”
A phase is a timing unit that controls one or more movements. The
timing unit includes three timing intervals,
one each for the indications of green, yellow, and red. Phases are
typically numbered in the same way as
movements, with the exception that the even numbered phases
normally control both the through and right-turn
movements. standard NEMA phasing convention (so-named since the
National Electrical
Manufacturers Association has established standards for the
operation of an actuated traffi c controller). For
consistency, phases 2 and 6 should correspond to the through
movements on the major street, while phases
4 and 8 should correspond to the through movements on the minor
street.