In: Operations Management
Which of the following is NOT a term used to describe the seller in a contract?
a. Vendor
b. Dealer
c. Service provider
d. Contractor
A project manager wants to know every detail form her team members. She reviews every document. She also manages details such as when a project team member is taking a break from the work day. Which of the following theories fits her management style?
a. Theory Z
b. Theory Y
c. Theory X
d. Maslow's Theory
Which of the following documents is the most useful in expediting the development of project schedule?
a. Risk Register
b. Stakeholder Register
c. Project Charter
d. Template
Effective information distribution includes all of the following techniques EXCEPT
a. Writing style
b. Presentation techniques
c. Issue log
d. Choice of media
1) d) contractor
Because vendor, dealers, and service providers are people who give service to other people. Which are reared to sellers in a contract. But contractor is nothing but owning something for some duration of time for construction or for maintainance purpose.
2) a) Theory Z
Because as per theory Z, management emphasis on employee disciplines, responsibility towards work. Develop skills etc. In present question manager wants to know about all details of employee breaks in work days in order to create the sense of responsibility. Therefore theory Z fits to the management.
3) d) Template
Template gives a replica of previous projects while making new project schedule. Thereby helps the organization to make project schedule quickly.
4) c) issue log
Writing styles, presentation skill, choice of media are useful in effective information system, where as issue log registers all the issue activities in an organization.