Question

In: Accounting

Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit...

Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights. An engineering and cost analysis has been made, and it is expected that the following cash flows would be associated with opening and operating a mine in the area:

Cost of new equipment and timbers $ 410,000
Working capital required $ 135,000
Annual net cash receipts $ 150,000 *
Cost to construct new roads in year three $ 47,000
Salvage value of equipment in four years $ 72,000

*Receipts from sales of ore, less out-of-pocket costs for salaries, utilities, insurance, and so forth.

The mineral deposit would be exhausted after four years of mining. At that point, the working capital would be released for reinvestment elsewhere. The company’s required rate of return is 18%.

Click here to view Exhibit 12B-1 and Exhibit 12B-2, to determine the appropriate discount factor(s) using tables.

Required:

a. What is the net present value of the proposed mining project?

b. Should the project be accepted?

Solutions

Expert Solution

1 Calculation of Net Present value of the project
Years
Now 1 2 3 4
Purchase of Equipment $     (410,000)
Investment in working capital $     (135,000)
Net annual cashflow $            150,000 $          150,000 $          150,000 $          150,000
Cost to construct road $          (47,000)
Salvage value of the Equipment $            72,000
Working Capital released $          135,000
Total Cash flows (a) $     (545,000) $            150,000 $          150,000 $          103,000 $          357,000
Discounting factor(18%)(b)                 1.000                     0.847                   0.718                   0.609                   0.516
Present value of Cash flow(a)x(b) $     (545,000) $            127,119 $          107,728 $            62,689 $          184,137
Net Present Value $        (63,328)
As the investment generates a negative NPV of $63,328, the investment is not acceptable .
Please do upvote if you found the answer useful.
Feel free reach in the comment section in case of any clarification or queries.

Related Solutions

Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit...
Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights. An engineering and cost analysis has been made, and it is expected that the following cash flows would be associated with opening and operating a mine in the area: Cost of new equipment and timbers $ 430,000 Working capital required $ 215,000 Annual net cash receipts $ 150,000 * Cost to construct new roads in...
Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit...
Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights. An engineering and cost analysis has been made, and it is expected that the following cash flows would be associated with opening and operating a mine in the area: Cost of new equipment and timbers $ 370,000 Working capital required $ 115,000 Annual net cash receipts $ 130,000 * Cost to construct new roads in...
Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit...
Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights. An engineering and cost analysis has been made, and it is expected that the following cash flows would be associated with opening and operating a mine in the area:   Cost of new equipment required and timbers $ 360,000   Working capital required $ 100,000   Annual net cash inflows* $ 140,000   Cost to construct new roads in...
Problem 13-16 Net Present Value Analysis [LO13-2] Windhoek Mines, Ltd., of Namibia, is contemplating the purchase...
Problem 13-16 Net Present Value Analysis [LO13-2] Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights. An engineering and cost analysis has been made, and it is expected that the following cash flows would be associated with opening and operating a mine in the area: Cost of new equipment and timbers $ 430,000 Working capital required $ 215,000 Annual net cash receipts $ 150,000...
Problem 12-16 Net Present Value Analysis [LO12-2] Windhoek Mines, Ltd., of Namibia, is contemplating the purchase...
Problem 12-16 Net Present Value Analysis [LO12-2] Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights. An engineering and cost analysis has been made, and it is expected that the following cash flows would be associated with opening and operating a mine in the area: Cost of new equipment and timbers $ 400,000 Working capital required $ 220,000 Annual net cash receipts $ 155,000...
1. Problem 13-16 Net Present Value Analysis [LO13-2] Windhoek Mines, Ltd., of Namibia, is contemplating the...
1. Problem 13-16 Net Present Value Analysis [LO13-2] Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights. An engineering and cost analysis has been made, and it is expected that the following cash flows would be associated with opening and operating a mine in the area: Cost of new equipment and timbers $ 390,000 Working capital required $ 125,000 Annual net cash receipts $...
Part aSekwanele Ltd is a manufacturing company in Windhoek, Namibia,producing and selling steelbeams....
Part a Sekwanele Ltd is a manufacturing company in Windhoek, Namibia, producing and selling steel beams. On 1 January 2019 the company acquired a property with the following details: N$ Purchase price Land: stand number 234 Mandume Ndemufayo 900 000 Office building thereon 2 200 000 Repairs and maintenance incurred for the year 70 000 Approximately 5% of the floor space is used as the administrative head office of the entity while the remainder of the building is leased out...
Bearcreek Mines paid $433,000 for the right to extract ore from a 450,000-ton mineral deposit. In...
Bearcreek Mines paid $433,000 for the right to extract ore from a 450,000-ton mineral deposit. In addition to the purchase price, Bearcreek Mines paid a $155 filing fee to the county recorder, a $2,800 license fee to the state of Utah, and $95,045 for a geologic survey. Because the company purchased the rights to the minerals only, it expects this mineral rights asset to have a residual value of zero when it is fully depleted. During the first year of...
Quencher Limited is planning to produce mineral water. It is contemplating to purchase a plant with a capacity of 100,000 bottles a month.
Quencher Limited is planning to produce mineral water. It is contemplating to purchase a plant with a capacity of 100,000 bottles a month. For the first year of operation the company expects to sell between 60,000 to 80,000 bottles. The budgeted costs at each of the two levels are as follows: GHS Particular 60,000 bottles 80,000 bottles Material 360,000 480,000 Labour 200,000 260,000 Factory overheads 120,000 150,000 Administration expenses 100,000 110,000 The production would be sold through retailers who will...
Altima Ltd, a manufacturer of edible oils, is contemplating the purchase b. of a new oil...
Altima Ltd, a manufacturer of edible oils, is contemplating the purchase b. of a new oil processing machine to replace the existing one. The existing machine was acquired two years ago at a cost of Shs.4,000,000. The useful life of this machine was originally expected to be five years with no salvage value, but after a critical analysis, the financial analyst has now estimated that the machine will have an economic life of 10 years with a salvage value of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT