LaRosa Machine Shop (LMS) is studying where to locate its tool bin facility on the shop...

LaRosa Machine Shop (LMS) is studying where to locate its tool bin facility on the shop floor. The locations of the five production stations appear in figure shown below.

Location
Station X Y Demand
Fabrication 1.0    4.0    12     
Paint 1.0    2.0    24     
Subassembly 1 2.5    2.0    13     
Subassembly 2 3.0    5.0    7     
Assembly 4.0    4.0    22     

In an attempt to be fair to the workers in each of the production stations, management has decided to try to find the position of the tool bin that would minimize the sum of the distances from the tool bin to the five production stations. We define the following decision variables:

X = horizontal location of the tool bin

Y = vertical location of the tool bin

We may measure the straight line distance from a station to the tool bin located at (X,Y) by using Euclidean (straight-line) distance. For example, the distance from fabrication located at the coordinates (1,4) to the tool bin located at the coordinates (X,Y) is given by .

(a) Suppose we know the average number of daily trips made to the tool bin from each production station. The average number of trips per day are 12 for fabrication, 24 for Paint, 13 for Subassembly 1, 7 for Subassembly 2 and 22 for Assembly. It seems like we would want the tool bin closer to those stations with high average numbers of trips. Develop a new unconstrained model that minimizes the sum of the demand-weighted distance defined as the product of the demand (measured in number of trips) and the distance to the station.
Min:               
(b) Solve the model you developed in part (a).
If required, round your answer to six decimal places. Do not round intermediate calculation.
X =  
Y =  
(c) The solution to the un-weighted model is X = 2.230 and Y = 3.349. Comment on the differences between the unweighted distance solution given and the demand-weighted solution found in part (b).

Solutions

Expert Solution

Pls,comment if any issue.

a)

b)

X=2.09191706177165

Y=2.85182622020003

Using Excel Solver,

c)

Comparing the unweighted distance solution given and the demand-weighted solution we obtained we get, the horizontal location of the tool bin and vertical location of the tool bin for demand weight is less than the unweighted distance.


Related Solutions

LaRosa Machine Shop (LMS) is studying where to locate its tool bin facility on the shop...
LaRosa Machine Shop (LMS) is studying where to locate its tool bin facility on the shop floor. The locations of the five production stations appear in figure shown below. Location Station X Y Demand Fabrication 1.0    4.0    12      Paint 1.0    2.0    19      Subassembly 1 2.5    2.0    13      Subassembly 2 3.0    5.0    7      Assembly 4.0    4.0    12      In an attempt to be fair to the workers in each of the production stations, management has decided to try to find the position...
Which government policies are especially important in the decision about where to locate an international facility?...
Which government policies are especially important in the decision about where to locate an international facility? Why do free trade zones often influence the location decisions of international businesses?
Brothers Cliff and Stanley began operations of their machine shop (H & H Tool, Inc.) on...
Brothers Cliff and Stanley began operations of their machine shop (H & H Tool, Inc.) on January 1, 2016. The annual reporting period ends December 31. The trial balance on January 1, 2018, follows (the amounts are rounded to thousands of dollars to simplify): Account Titles Debit Credit Cash $ 2 Accounts Receivable 6 Supplies 13 Land 0 Equipment 64 Accumulated Depreciation $ 5 Software 18 Accumulated Amortization 4 Accounts Payable 4 Notes Payable (short-term) 0 Salaries and Wages Payable...
Brothers Harry and Herman Hausyerday began operations of their machine shop (H & H Tool, Inc.)...
Brothers Harry and Herman Hausyerday began operations of their machine shop (H & H Tool, Inc.) on January 1, 2016. The annual reporting period ends December 31. The trial balance on January 1, 2018, follows (the amounts are rounded to thousands of dollars to simplify): Account Titles Debit Credit Cash $ 2 Accounts Receivable 6 Supplies 13 Land 0 Equipment 61 Accumulated Depreciation $ 5 Software 15 Accumulated Amortization 6 Accounts Payable 4 Notes Payable (short-term) 0 Salaries and Wages...
Brothers Harry and Herman Hausyerday began operations of their machine shop (H & H Tool, Inc.)...
Brothers Harry and Herman Hausyerday began operations of their machine shop (H & H Tool, Inc.) on January 1, 2016. The annual reporting period ends December 31. The trial balance on January 1, 2018, follows (the amounts are rounded to thousands of dollars to simplify): Account Titles Debit Credit Cash $ 3 Accounts Receivable 5 Supplies 12 Land 0 Equipment 69 Accumulated Depreciation $ 6 Software 24 Accumulated Amortization 4 Accounts Payable 5 Notes Payable (short-term) 0 Salaries and Wages...
Brothers Harry and Herman Hausyerday began operations of their machine shop (H & H Tool, Inc.)...
Brothers Harry and Herman Hausyerday began operations of their machine shop (H & H Tool, Inc.) on January 1, 2016. The annual reporting period ends December 31. The trial balance on January 1, 2018, follows (the amounts are rounded to thousands of dollars to simplify): Account Titles Debit Credit Cash $ 3 Accounts Receivable 5 Supplies 12 Land 0 Equipment 69 Accumulated Depreciation $ 6 Software 24 Accumulated Amortization 4 Accounts Payable 5 Notes Payable (short-term) 0 Salaries and Wages...
Brothers Harry and Herman Hausyerday began operations of their machine shop (H & H Tool, Inc.)...
Brothers Harry and Herman Hausyerday began operations of their machine shop (H & H Tool, Inc.) on January 1, 2016. The annual reporting period ends December 31. The trial balance on January 1, 2018, follows (the amounts are rounded to thousands of dollars to simplify): Account Titles Debit Credit Cash $ 4 Accounts Receivable 4 Supplies 11 Land 0 Equipment 53 Accumulated Depreciation $ 7 Software 20 Accumulated Amortization 7 Accounts Payable 6 Notes Payable (short-term) 0 Salaries and Wages...
Brothers Harry and Herman Hausyerday began operations of their machine shop (H & H Tool, Inc.)...
Brothers Harry and Herman Hausyerday began operations of their machine shop (H & H Tool, Inc.) on January 1, 2016. The annual reporting period ends December 31. The trial balance on January 1, 2018, follows (the amounts are rounded to thousands of dollars to simplify): Account Titles Debit Credit Cash $ 3 Accounts Receivable 5 Supplies 12 Land 0 Equipment 58 Accumulated Depreciation $ 6 Software 16 Accumulated Amortization 7 Accounts Payable 5 Notes Payable (short-term) 0 Salaries and Wages...
Brothers Harry and Herman Hausyerday began operations of their machine shop (H & H Tool, Inc.)...
Brothers Harry and Herman Hausyerday began operations of their machine shop (H & H Tool, Inc.) on January 1, 2016. The annual reporting period ends December 31. The trial balance on January 1, 2018, follows (the amounts are rounded to thousands of dollars to simplify): Account Titles Debit Credit Cash $ 3 Accounts Receivable 5 Supplies 12 Land 0 Equipment 58 Accumulated Depreciation $ 6 Software 16 Accumulated Amortization 7 Accounts Payable 5 Notes Payable (short-term) 0 Salaries and Wages...
Brothers Harry and Herman Hausyerday began operations of their machine shop (H & H Tool, Inc.)...
Brothers Harry and Herman Hausyerday began operations of their machine shop (H & H Tool, Inc.) onJanuary 1, 2013. The annual reporting period ends December 31. The trial balance on January 1, 2015, follows(the amounts are rounded to thousands of dollars to simplify): Account Titles Debit Credit cash 2 accounts recievable 6 supplies 13 land 0 equipment 64 accumulated depreciation 5 software 18 accumulated amortization 4 accounts payable 4 notes payable (short-term) 0 salaries and wages payable 0 interest payable...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT