Question

In: Civil Engineering

A project has 300,000 BCY (wet excavated earth). We need to complete excavation in 12 weeks...

A project has 300,000 BCY (wet excavated earth). We need to complete excavation in 12 weeks – Figure to work 6 days per week, 10 hours per day.

1. Backhoe Problem:

1. Find required production per hour in BCY/hr and LCY/hr.
2. Determine bucket Fill Factor
3. Calculate bucket cycles per hour
4. Calculate required bucket capacity assuming the following:
a. Work efficiency = 50 min/60 min hr
5. Select required excavator (Caterpillar)
6. Suggest suitable off-road haul truck for project. Assume 4 buckets to load a truck load.

Solutions

Expert Solution

solution:

given that, earth to be excavated = 300000 BCY

time available = 12 weeks (6 days working)

working time / day = 10 hours

1) production required / hour = excavating volume of earth / time available

= 300000 / (12 * 6 * 10)

= 416.67 BCY / hour

Assuming 25% swell, LCY = 1.25 BCY = 416.67 * 1.25 = 520.84 LYC

2) Assuming the bucket size of 1.75 cubic yards and it is filling only 1.70 cubic yards in each cycle.

therefore, bucket fill factor = (average fill in each cycle / full capacity of the bucket) 100

= (1.70 / 1.75) 100 = 97.14%

3) volume to be excavated per hour = 416.67 BCY

if only one backhoe is working then, the cycle length = volume to be excavated per hour/capacity of the bucket

= 416.67 / 1.70 = 245.1 = 245 (approx.) cycles per hour

4) If work efficiency is 50 min. per hour, the capacity of bucket required = [(total earth to be excavated / (week * working days in a week * working hours in the day)) / no. of cycles per hour]

according to 50 min. per hour, work per day will be only 8 hours and 20 minutes.

therefore, the new capacity of bucket = [(300000 / (12 * 6 * 8.33)) / 245]

= 2.0416 cubic yards


Related Solutions

The time required to complete a project is normally distributed with a mean of 78 weeks...
The time required to complete a project is normally distributed with a mean of 78 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?
The mean time required to complete a certain type of construction project is 52 weeks with...
The mean time required to complete a certain type of construction project is 52 weeks with a standard deviation of 3 weeks. Answer questions 4–7 using the preceding information and modeling this situation as a normal distribution. 4. What is the probability of the completing the project in no more than 52 weeks? a) 0.25 b) 0.50 c) 0.75 d) 0.05 5. What is the probability of the completing the project in more than 55 weeks? a) 0.1587 b) 0.5091...
The mean time required to complete a certain type of construction project is 52 weeks with...
The mean time required to complete a certain type of construction project is 52 weeks with a standard deviation of 3 weeks. Answer questions 4–7 using the preceding information and modeling this situation as a normal distribution. What is the probability of the completing the project in no more than 52 weeks? 0.25 0.50 0.75 0.05 What is the probability of the completing the project in more than 55 weeks? 0.1587 0.5091 0.7511 0.0546 What is the probability of completing...
The Wet Corp. has an investment project that will reduce expenses by $20,000 per year for...
The Wet Corp. has an investment project that will reduce expenses by $20,000 per year for 3 years. The project's cost is $20,000. If the asset is part of the 3-year MACRS category (33.33% first year depreciation) and the company's tax rate is 36%, what is the cash flow from the project in year 1?
The Wet Corp. has an investment project that will reduce expenses by $30,000 per year for...
The Wet Corp. has an investment project that will reduce expenses by $30,000 per year for 3 years. The project's cost is $35,000. If the asset is part of the 3-year MACRS category (33.33% first year depreciation) and the company's tax rate is 33%, what is the cash flow from the project in year 1? (Do not round intermediate calculations. Round your answer to the nearest dollar amount.) $23,950 $23,400 $24,730 $25,410
Planning a festival. The Earth Day Committee has begun planning for an Earth Day festival. We...
Planning a festival. The Earth Day Committee has begun planning for an Earth Day festival. We list the subtasks for this project and the dependencies among them in the following table. Draw a PERT diagram for this project and construct a schedule for the tasks. Task Preceding Tasks Time Required (weeks) Get funding None 2 Get permits None 1 Decide on program 1 2 Rent tents 1,2,3 2 Arrange for speakers, entertainers, etc. 1,2,3,4 4 Advertise 1,3,5 2 Set up...
responed to the writting below any comment ? Since these microorganisms contaminate the earth, we need...
responed to the writting below any comment ? Since these microorganisms contaminate the earth, we need a protocol to disinfect the spaceship. The microbes that are found on space ships are the organisms that survived the trip from spaces and can survive in both space and earth environments. In a biofilm on a deep-sea hydrothermal vent, microorganisms survive at temperatures above 100C. If a sample were to be taken from the biofilm, many of the microbes would die on their...
The project manager is often faced with the need to reduce the time taken to complete...
The project manager is often faced with the need to reduce the time taken to complete a project. However, the cost usually increased due to the additional resources required. The table below presents normal and crash times and costs for each activity in a project. Immediate predecessor Normal time Normal cost Crash time Crash cost A - 4 50 2 90 B A 6 80 4 160 C A 10 60 8 120 D A 11 50 7 150 E...
In this project we are asked to complete a 2017 joint tax return for Gary and...
In this project we are asked to complete a 2017 joint tax return for Gary and Jennifer Smith whose information is provided below. Most people today use tax return software to prepare their tax returns. The three most commonly used software packages are available from Tax Cut, H&R Block and Intuit’s Turbo tax. A registration code is provided in our textbook for the Tax Cut software on the page opposite the inside cover of everyone’s textbook. It does not matter...
We have a project where we need to incorporate smart technology in a product made by...
We have a project where we need to incorporate smart technology in a product made by a certain brand that we were assigned. We were assigned Stihl, here is a link to their website: https://m.stihlusa.com/. One idea we had was to incorporate an app that would link all the Stihl tools you had and then show you oil life and certain things like that. Any ideas you can come up with would be great. The smart technology needs to be...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT