Planning a festival. The Earth Day Committee has begun planning for an Earth Day festival. We list the subtasks for this project and the dependencies among them in the following table. Draw a PERT diagram for this project and construct a schedule for the tasks.
Task |
Preceding Tasks |
Time Required (weeks) |
|
None |
2 |
|
None |
1 |
|
1 |
2 |
|
1,2,3 |
2 |
|
1,2,3,4 |
4 |
|
1,3,5 |
2 |
|
1,2,3,4 |
1 |
|
1,2,3,4,5,6,7 |
1 |