Question

In: Computer Science

The project manager is often faced with the need to reduce the time taken to complete...

The project manager is often faced with the need to reduce the time taken to complete a project. However, the cost usually increased due to the additional resources required. The table below presents normal and crash times and costs for each activity in a project. Immediate predecessor Normal time Normal cost Crash time Crash cost A - 4 50 2 90 B A 6 80 4 160 C A 10 60 8 120 D A 11 50 7 150 E B 8 100 6 160 F C,D 5 40 4 70 G E,F 6 70 4 150 Given the information in the above network and the table, answer the following questions: a) The project manager would like to reduce the duration of the project to 23 days. Identify the activities that you would crash and the resulting total cost for the project. Show workings. (3.5 marks) b) The table below shows the indirect project cost for different durations. What would be the optimal number of days for the project duration? Explain your answer and show workings. Days Indirect Costs 26 500 25 460 24 420 23 400 22 380 21 360 20 320 19 300 18 260 c) Use this data to graphically present the total costs of the project

Solutions

Expert Solution

Task data is captured below

Task Name

Predecessor

Normal Time

Normal Cost

Crash Time

Crash Cost

Cost Slope
(CC-NC) / (NT-CT)
Cost Slope Ranking

A

-

4

50

2

90

20 1

B

A

6

80

4

160

40 4

C

A

10

60

8

120

30 3

D

A

11

50

7

150

25 2

E

B

8

100

6

160

30 3

F

C, D

5

40

4

70

30 3

G

E, F

6

70

4

150

40 4
Total 450

Network Diagram

There are three paths in the project

ABEG - 24 days

ACFG - 25 days

ADFG - 26 days

Critical path or project duration is 26 days, due to ADFG.

Total normal cost of project is 450.

a) In order to reduce the project time to 23 days. The reduction is required in all the three paths, as all three of them are more than 23 days.

Minimum cost slope for crashing is avialable in case of A having cost slope ranking 1 i.e. of cost 20 for every day.

Another benefit of chosing A is that it is part of all the three paths, so reduction in the duration of this task due to crashing will have bearing on all the three paths. The critical path won't change as we go on crashing the task A to reducte the duration of critical path.

As can be seen by crashing A by 3 days to 1 day by providing crash cost of 3 * 20 = 60 units of cost.

All the three path duration reduce by 3 days i.e.

ABEG - 24 days to 21 days

ACFG - 25 days to 22 days

ADFG - 26 days to 23 days

Now the project duration is as desired (i.e. of 23 days) so we donot need to put any additional effot to crash any task anymore.

So now the total cost of project to complete it in 23 days is Normal cost + crashing cost of task A by 3 days
= 450 + 60 = 510

b) Total cost of project would add up the indirect cost.

Since indirect cost is dependent on number of days the project requires, reducing the time to complete the project would reduce the indirect cost, however in order to reduce the time we need to invest additional cost to crash some task.
If the cost to crash the task that lowers the duration of project by 1 day is less than the savings in indirect cost that it is worth doing.

Optimal Number of Days
Days-> 26 25 24 23 22 21 20 19 18
Indirect Cost 500 460 420 400 380 360 320 300 260
Normal Cost 450
Crashing Cost 20 20 20 20 25 40 40 40
Crashing Task A A A A D G G G
Normal+Crash
Cost
470 490 510 530 555 595 635 675
Total Cost
(Normal + crash
+ indirect)
950 930 910 910 910 915 915 935 935

To reduce 20,19, 18 we chose G even though it has the cost of 40, as trying to reduce D would require us to reduce C also. Adding crashing cost for both of this it would take (25 + 30) = 55 units of cost which is more than crashing cost of G (40).

For every saving of 1 day we save on indirect cost but spend on crashing cost. Since task A has the top ranking for crashing we crash it till we get the overall benefit.

As can be seen for all 22, 23 and 24 days we spend total cost of 910. So 22 days is the optimal duration as it is less duration with same cost.

However there is point to consider here. 22 days is possible if we crash the Task A by 4 days, means by putting extra effort we reduce the time of task A to 0 that is theretical and is not practical.

Only way it can happen is by doing something like requirement rescoping and alternate arrangement by which A is no more required and also does not create dependency for other task, which is not practical, and depends on the task.

Graph and data is provided on theretical basis but realistic optimal duration would be 23 days.

C)


Related Solutions

There are decisions that need to be taken by a financial manager. If you are a...
There are decisions that need to be taken by a financial manager. If you are a financial manager in a manufacturing firm that sells biscuits, please elaborate on what kind of decisions you will have to take in the company and give specific examples of the decisions
The time taken to complete an assignment in a class follows a normal distribution with a...
The time taken to complete an assignment in a class follows a normal distribution with a mean of105 minutes and a standard deviation of 10 minutes. A. What is the probability that a randomly selected student takes between 100and 112 minutes to complete the exam? B. What is the probability that a randomly selected student takes less than 115minutes to complete the exam? C. What is the time that corresponds to the 38th percentile? D. Between which two values does...
When it comes to a project, if a project manager were to pad their time when...
When it comes to a project, if a project manager were to pad their time when creating our schedule are we being unethical? Where do we draw the line?
A bank manager has developed a new system to reduce the time customers spend waiting for...
A bank manager has developed a new system to reduce the time customers spend waiting for teller service during peak hours. The manager hopes the new system will reduce the waiting time that currently is 10 minutes. Formulate the hypotheses and rejection rule for this problem. A random sample of 70 waiting times was obtained after the system was implemented. The sample showed a sample mean of 9.5 minutes and a standard deviation of 2.2 minutes. Obtain the p-value. At...
Recall that a bank manager has developed a new system to reduce the time customers spend...
Recall that a bank manager has developed a new system to reduce the time customers spend waiting to be served by tellers during peak business hours. The mean waiting time during peak business hours under the current system is roughly 9 to 10 minutes. The bank manager hopes that the new system will have a mean waiting time that is less than six minutes. The mean of the sample of 100 bank customer waiting times in Table 1.9 is 5.46....
A bank manager has developed a new system to reduce the time customers spend waiting to...
A bank manager has developed a new system to reduce the time customers spend waiting to be served by tellers during peak business hours. The bank manager hopes that the new system will lower the average waiting time to less than six minutes. A one-month trial of the system is conducted and 25 customers have been selected and the waiting times were recorded. The sample resulted in a mean of 5.2 minutes and a standard deviation of 2.4 minutes. a-...
Recall that a bank manager has developed a new system to reduce the time customers spend...
Recall that a bank manager has developed a new system to reduce the time customers spend waiting for teller service during peak hours. The manager hopes the new system will reduce waiting times from the current 9 to 10 minutes to less than 6 minutes. Suppose the manager wishes to use the random sample of 100 waiting times to support the claim that the mean waiting time under the new system is shorter than six minutes. Letting μ represent the...
Recall that a bank manager has developed a new system to reduce the time customers spend...
Recall that a bank manager has developed a new system to reduce the time customers spend waiting for teller service during peak hours. The manager hopes the new system will reduce waiting times from the current 9 to 10 minutes to less than 6 minutes. Suppose the manager wishes to use the random sample of 100 waiting times to support the claim that the mean waiting time under the new system is shorter than six minutes. Letting μ represent the...
Recall that a bank manager has developed a new system to reduce the time customers spend...
Recall that a bank manager has developed a new system to reduce the time customers spend waiting to be served by tellers during peak business hours. The mean waiting time during peak business hours under the current system is roughly 9 to 10 minutes. The bank manager hopes that the new system will have a mean waiting time that is less than six minutes. The mean of the sample of 90 bank customer waiting times is x⎯⎯ x ¯ =...
Recall that a bank manager has developed a new system to reduce the time customers spend...
Recall that a bank manager has developed a new system to reduce the time customers spend waiting to be served by tellers during peak business hours. The mean waiting time during peak business hours under the current system is roughly 9 to 10 minutes. The bank manager hopes that the new system will have a mean waiting time that is less than six minutes. The mean of the sample of 99 bank customer waiting times is x¯ = 5.44. If...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT