In: Accounting
What are the payback and NPV (net present value) methods of evaluating capital projects? Which is considered the best evaluation method, and why is one better than the other?
Payback and NPV methods are the measure for evaluating an capital project. | ||||||||||||
Payback deals with the time taken by project to pay back cost of initial investment.On the other hand NPV (Net Present Value) is the | ||||||||||||
present value of all cash flows associated with the project. | ||||||||||||
Let us consider an example for this purpose that is discounted at 10%: | ||||||||||||
Year | Cash flows | Cumulative cash flows | Discount factor | Present Value | ||||||||
a | b | c | d=1.10^-a | e=b*d | ||||||||
0 | $ -1,00,000 | $ -1,00,000 | 1.0000 | $ -1,00,000 | ||||||||
1 | 50,000 | $ -50,000 | 0.9091 | 45,455 | ||||||||
2 | 30,000 | $ -20,000 | 0.8264 | 24,793 | ||||||||
3 | 22,000 | $ 2,000 | 0.7513 | 16,529 | ||||||||
4 | 15,000 | $ 17,000 | 0.6830 | 10,245 | ||||||||
Net Present Value | -2,978 | |||||||||||
Payback Period | = | 2+(20000/22000) | = | 2.91 Years | ||||||||
From the above example, It is observed that project is paying back initial investment in 2.91 years of 4 years project. | ||||||||||||
So, on the basis of Payback ,project is acceptable. | ||||||||||||
But, when calculating Net Present Value from the project, it is found that project is giving a negative Net Present Value. | ||||||||||||
It means as of today we are losing $ 2978 from the project.So, Project will be rejected. | ||||||||||||
In such case , NPV method is acceptable because the objective of capital project is to create money from project | ||||||||||||
and project is not creating any money and hence it will be rejected by considering NPV method | ||||||||||||