In: Accounting
What are the payback and NPV (net present value) methods of evaluating capital projects? Which is considered the best evaluation method, and why is one better than the other?
| Payback and NPV methods are the measure for evaluating an capital project. | ||||||||||||
| Payback deals with the time taken by project to pay back cost of initial investment.On the other hand NPV (Net Present Value) is the | ||||||||||||
| present value of all cash flows associated with the project. | ||||||||||||
| Let us consider an example for this purpose that is discounted at 10%: | ||||||||||||
| Year | Cash flows | Cumulative cash flows | Discount factor | Present Value | ||||||||
| a | b | c | d=1.10^-a | e=b*d | ||||||||
| 0 | $ -1,00,000 | $ -1,00,000 | 1.0000 | $ -1,00,000 | ||||||||
| 1 | 50,000 | $ -50,000 | 0.9091 | 45,455 | ||||||||
| 2 | 30,000 | $ -20,000 | 0.8264 | 24,793 | ||||||||
| 3 | 22,000 | $ 2,000 | 0.7513 | 16,529 | ||||||||
| 4 | 15,000 | $ 17,000 | 0.6830 | 10,245 | ||||||||
| Net Present Value | -2,978 | |||||||||||
| Payback Period | = | 2+(20000/22000) | = | 2.91 Years | ||||||||
| From the above example, It is observed that project is paying back initial investment in 2.91 years of 4 years project. | ||||||||||||
| So, on the basis of Payback ,project is acceptable. | ||||||||||||
| But, when calculating Net Present Value from the project, it is found that project is giving a negative Net Present Value. | ||||||||||||
| It means as of today we are losing $ 2978 from the project.So, Project will be rejected. | ||||||||||||
| In such case , NPV method is acceptable because the objective of capital project is to create money from project | ||||||||||||
| and project is not creating any money and hence it will be rejected by considering NPV method | ||||||||||||