In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600
Estimated costs to complete as of year-end 5,810,000 1,826,000 0
Billings during the year 2,030,000 4,444,000 3,526,000
Cash collections during the year 1,815,000 3,900,000 4,285,000


Westgate recognizes revenue over time according to percentage of completion.

3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.)

Solutions

Expert Solution


Related Solutions

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 3,150,000 $ 2,475,000 Estimated costs to complete as of year-end 5,400,000 2,250,000 0 Billings during the year 2,150,000 3,100,000 4,750,000 Cash collections during the year 1,875,000 3,100,000 5,025,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows. 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 5. Calculate the amount of revenue and...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows. 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 3. Complete the information required below to...
in 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
in 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to...