Question

In: Accounting

Stoney Run Construction Company (U.S. GAAP) enters into a 3-year contract to build a new warehouse...

Stoney Run Construction Company (U.S. GAAP) enters into a 3-year contract to build a new warehouse facility. Information for Years 1, 2, and 3 is shown below:

Year 1 Year 2 Year 3
Sale price $2,800,000 $2,800,000 $2,800,000
Estimated costs 1,600,000 2,000,000 2,000,000
Costs incurred to date (paid in cash) 400,000 900,000 2,000,000
Billed to date 250,000 1,150,000 2,800,000
Received in cash to date 190,000 950,000 2,800,000

COST RECOVERY METHOD (IFRS)

Question 1: Calculate the Gross Profit booked in Year 1:

Question 2: Book the following Journal Entries for Year 1:

1-Record Sale

2-Record payments received

Question 3: Book the following journal entries for Year 3:

1-Record payments received

2-Record gross profit

Solutions

Expert Solution

  • All working forms part of the answer
  • Working sheet

Working

Year 1

Year 2

Year 3

A

Contract Price

$       2,800,000.00

$ 2,800,000.00

$ 2,800,000.00

B

Cost Incurred to Date

$           400,000.00

$      900,000.00

$ 2,000,000.00

C

Estimated cost yet to be incurred to complete the contract

$       1,200,000.00

$ 1,100,000.00

$                        -  

D = B+C

Total Cost

$       1,600,000.00

$ 2,000,000.00

$ 2,000,000.00

E = (D/B) x 100

% of Completion

25%

45%

100%

F = A x E

Revenue to date

$           700,000.00

$ 1,260,000.00

$ 2,800,000.00

G

Revenue of Previous year

$                            -  

$      700,000.00

$ 1,260,000.00

H = F - G

Net Revenue this year

$           700,000.00

$      560,000.00

$ 1,540,000.00

I (=B)

Cost to date

$           400,000.00

$      900,000.00

$ 2,000,000.00

J

Cost to date of previous year

$                            -  

$      400,000.00

$      900,000.00

K = I - J

Net Cost for the year

$           400,000.00

$      500,000.00

$ 1,100,000.00

L = H - K

Gross Profits

$           300,000.00

$        60,000.00

$      440,000.00

  • Answers
  • Question 1

Answer: Gross Profit Year 1 = $ 300,000 [calculated above]

  • Question 2

Date

Accounts title

Debit

Credit

  1. RECORD SALE

Accounts receivables

$ 250,000.00

Billing on Construction contracts

$ 250,000.00

(amount billed during the year)

Date

Accounts title

Debit

Credit

  1. RECORD PAYMENT RECEIVED

Cash

$ 190,000.00

Accounts receivables

$ 190,000.00

(cash received)

  • Question 3

Date

Accounts title

Debit

Credit

  1. Payment received

Cash

$      1,850,000.00

Accounts receivables

$ 1,850,000.00

(cash received)

Date

Accounts title

Debit

Credit

  1. Record Gross Profits

Construction in Progress

$          440,000.00

Construction expenses

$      1,100,000.00

Construction Revenue

$ 1,540,000.00

(revenue recognised)


Related Solutions

Stoney Run Construction Company (U.S. GAAP) enters into a 3-year contract to build a new warehouse...
Stoney Run Construction Company (U.S. GAAP) enters into a 3-year contract to build a new warehouse facility. Information for Years 1, 2, and 3 is shown below: Year 1 Year 2 Year 3 Sale price $2,800,000 $2,800,000 $2,800,000 Estimated costs 1,600,000 2,000,000 2,000,000 Costs incurred to date (paid in cash) 400,000 900,000 2,000,000 Billed to date 250,000 1,150,000 2,800,000 Received in cash to date 190,000 950,000 2,800,000 Question 4: Calculate the gross profit booked in Year 2: Question 5: Book...
Cullumber Construction enters into a contract with a customer to build a warehouse for $1070000 on...
Cullumber Construction enters into a contract with a customer to build a warehouse for $1070000 on March 30, 2021 with a performance bonus of $40000 if the building is completed by July 31, 2021. The bonus is reduced by $8000 each week that completion is delayed. Cullumber commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2021 70% August 7, 2021 20% August 14, 2021 5%...
Cullumber Construction enters into a contract with a customer to build a warehouse for $1070000 on...
Cullumber Construction enters into a contract with a customer to build a warehouse for $1070000 on March 30, 2021 with a performance bonus of $40000 if the building is completed by July 31, 2021. The bonus is reduced by $8000 each week that completion is delayed. Cullumber commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2021 70% August 7, 2021 20% August 14, 2021 5%...
Big Construction Company signs a contract on 1 July 2019, agreeing to build a warehouse for...
Big Construction Company signs a contract on 1 July 2019, agreeing to build a warehouse for Buyer Corporation Ltd at a fixed contract price of $10 million. Buyer Ltd will be in control of the asset throughout the construction process. Big Construction Company estimates that construction costs will be as follows: 2019 2.5 million 2020 $4 million 2021 $1.5 million The contract provides that Buyer Corporation Ltd will make payments on 31 December each year as follows: 2019 $2 million...
The Young Company enters into a long-term project to build a new office building. The Contract...
The Young Company enters into a long-term project to build a new office building. The Contract price is $9,000,000 and Young expects to complete the project in three years. Young gives you the following information for the first two years regarding the project: 2017 2018 Actual costs incurred during year 2,400,000 3,800,000 Estimated costs to complete at as of December 31: 5,100,000 3,000,000 Amounts billed to customer 2,800,000 4,100,000 Collections from customer 2,600,000 3,400,000 Required: 1.    Prepare the journal entries...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2018, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2019, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2019 billings were $2,990,000, and $2,675,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2018, costs of $2,050,000 were incurred with estimated costs of $4,050,000 yet to be incurred. Billings of $2,550,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,550,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,800,000 and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT