In: Accounting
EXERCISE 18.11 The following information pertains to May activity
in Accessory World’s Coating Department:
Cost data:
Total cost of beginning inventory on May 1 . . . . . . . . . . . .
. . . . . . . . . . . . . $45,300
Direct materials costs incurred in May. . . . . . . . . . . . . . .
. . . . . . . . . . . . . . 11,925
Conversion costs incurred in May . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . 84,525
Cut sets transferred in during May. . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . ?
Physical units data:
Units in process, May 1 . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . 6,000 sets
Units started in May . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . ? sets
Units in process, May 31 . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . 9,000 sets
Percentage of completion data:
Direct materials, May 1. . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . 60%
Conversion, May 1 . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . 80
Cut sets transferred in, May 1 . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . ?
Direct materials, May 31. . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . 70%
Conversion, May 31 . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . 90
Cut sets transferred in, May 31 . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . ?
Compute how many cut mat sets were started in the Coating
Department during May.
b. Prepare a schedule showing: (1) the number of mat sets
transferred out of the Coating Department
in May, and (2) the number of mat sets started and completed by the
Coating Department
in May.
c. Compute the equivalent units of input resources for the Coating
Department in May.
d. Compute the cost per equivalent unit of input resource for the
Coating Department in May.
e. Prepare the summary journal entry required to transfer the cost
of finished mat sets from the
Coating Department’s Work in Process Inventory to the company’s
Finished Goods Inventory in
May.
f. Compute the total cost assigned to the Coating Department’s
ending inventory in process on
May 31.
FIFO method | |||
Beggining units | 6000 | Transferred out | 45,000 |
Started into production | 48000 | Ending units | 9,000 |
54000 | 54000 | ||
Equivalent units | Material | Conversion | Transferred in |
Beginning units | 6000 | 6000 | 6000 |
Completion in current period | 40% | 20% | 0% |
A | 2400 | 1200 | 0 |
Units started and completed | 39000 | 39000 | 39,000 |
Completion | 100% | 100% | 100% |
B | 39000 | 39000 | 39000 |
Ending Units | 9,000 | 9,000 | 9,000 |
Completion | 70% | 90% | 100% |
C | 6300 | 8100 | 9000 |
Total units A+B+C | 47700 | 48300 | 48000 |
Per unit cost | Cost | Total units | Per unit cost |
Material cost | 11925 | 47700 | 0.25 |
Conversion cost | 84525 | 48300 | 1.75 |
transferred in | 288000 | 48000 | 6.00 |
384450 | 8.00 |
Cost of goods sold | Material | convertion cost | transferred in | |
Beginning inventory completed | ||||
Completion | 40% | 20% | 0% | |
Per unit cost | 0.25 | 1.75 | 6.00 | |
Units | 6000 | 6000 | 6000 | |
Total cost A | 600.00 | 2100 | 0 | 2700 |
Units started and completed | ||||
Completion | 100% | 100% | 100% | |
Per unit cost | 0.25 | 1.75 | 6.00 | |
Units | 39000 | 39000 | 39000 | |
Total cost B | 9750.00 | 68250 | 234000 | 312000 |
Beginning work in progress C | 0 | 0 | 0 | 45300 |
Total cost A+B+C | 10350 | 70350 | 234000 | 360000 |
Ending work in progress | ||||
Completion | 70% | 90% | 100% | |
Per unit cost | 0.25 | 1.75 | 6.00 | |
Units | 9,000 | 9,000 | 9,000 | |
Total cost | 1575 | 14175 | 54000 | 69750 |