Question

In: Accounting

A contractor has the opportunity to choose between building a house or doing two

A contractor has the opportunity to choose between building a house or doing two extension works in the next 6 months. If you build the house and sell it, you can make $25,000. However, if the housing market is affected by the increase in mortgage interest rates and would lose $5,000. On the other hand, you can earn $17,000 by performing both expansion jobs, regardless of market behavior. Based on excel QM which matrix would you deal with? 

a) Develop a payment matrix for this problem 

b) What alternative should be chosen if the contractor is an optimist? 

c) What alternative should be chosen if the contractor is a pessimist?

Solutions

Expert Solution

Based on excel QM which matrix would you deal with?

ANSWER

The expected value of the house is $25,000, while the expected value of the two extension works is $17,000. 

Therefore, the contractor should choose to build the house.

 

 

a) Develop a payment matrix for this problem  

ANSWER

The payment matrix for this problem is as follows: 

House: $25,000 

Extension work 1: $17,000 

Extension work 2: $17,000 

Total: $59,000 

 

 

b) What alternative should be chosen if the contractor is an optimist?  

ANSWER 

The contractor should choose to build the house if they are an optimist, as they believe that they will make a profit from the sale. 

 

 

c) What alternative should be chosen if the contractor is a pessimist? 

ANSWER 

The contractor should choose to perform both extension works if they are a pessimist, as they believe that they will not make a profit from the sale of the house.


Related Solutions

A construction contractor needs to choose between two suppliers of dump trucks. Supplier 1 has an...
A construction contractor needs to choose between two suppliers of dump trucks. Supplier 1 has an initial cost of $125,000 and annual operating cost of $25, 000 per year. Supplier 2 has initial cost $160,000 and has annual operating cost of 20,000 per year. The truck fleet has the same 10-year life forecast Based on incremental rate of return (IROR) and a MARR of 8%, and which supplier of trucks should the contractor choose? Please do not use excel.
A contractor must choose between buying or renting a crane for the duration of a 5...
A contractor must choose between buying or renting a crane for the duration of a 5 year construction project. The contractor uses an MARR of 8%. At the end of the project, the crane can be sold for 26% of its initial cost. The cost to operate and maintain the crane is $210,000 per year. Renting the crane costs $330,000 per year including all operating and maintenance costs. Determine the maximum amount the contractor should pay to purchase the crane...
A small building contractor has recently experienced two successive years in which work opportunities exceeded the...
A small building contractor has recently experienced two successive years in which work opportunities exceeded the firm’s capacity. The contractor must now make a decision on capacity for next year. Estimated profits under each of the two possible states of nature are as shown in the table below. Suppose after a certain amount of discussion, the contractor is able to subjectively assess the probabilities of low and high demand: P (low) = .3 and P (high) = .7. NEXT YEAR'S...
Golden Gate Construction Associates, a real estate developer and building contractor in San Francisco, has two...
Golden Gate Construction Associates, a real estate developer and building contractor in San Francisco, has two sources of long-term capital: debt and equity. The cost to Golden Gate of issuing debt is the after-tax cost of the interest payments on the debt, taking into account the fact that the interest payments are tax deductible. The cost of Golden Gate’s equity capital is the investment opportunity rate of Golden Gate’s investors, that is, the rate they could earn on investments of...
Golden Gate Construction Associates, a real estate developer and building contractor in San Francisco, has two...
Golden Gate Construction Associates, a real estate developer and building contractor in San Francisco, has two sources of long-term capital: debt and equity. The cost to Golden Gate of issuing debt is the after-tax cost of the interest payments on the debt, taking into account the fact that the interest payments are tax deductible. The cost of Golden Gate’s equity capital is the investment opportunity rate of Golden Gate’s investors, that is, the rate they could earn on investments of...
Golden Gate Construction Associates, a real estate developer and building contractor in San Francisco, has two...
Golden Gate Construction Associates, a real estate developer and building contractor in San Francisco, has two sources of long-term capital: debt and equity. The cost to Golden Gate of issuing debt is the after-tax cost of the interest payments on the debt, taking into account the fact that the interest payments are tax deductible. The cost of Golden Gate’s equity capital is the investment opportunity rate of Golden Gate’s investors, that is, the rate they could earn on investments of...
A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $500,000 and $700,000 B Normal probability distribution with a mean bid of $600,000 and a standard deviation of $40,000 If required, round your answers to three decimal places. If...
Continent Construction Company is a building contractor specializing in small commercial buildings. The company has the...
Continent Construction Company is a building contractor specializing in small commercial buildings. The company has the opportunity to accept one of two jobs; it cannot accept both because they must be performed at the same time and Continent does not have the necessary labor force for both jobs. Indeed, it will be necessary to hire a new supervisor if either job is accepted. Furthermore, additional insurance will be required if either job is accepted. The revenue and costs associated with...
Rooney Construction Company is a building contractor specializing in small commercial buildings. The company has the...
Rooney Construction Company is a building contractor specializing in small commercial buildings. The company has the opportunity to accept one of two jobs; it cannot accept both because they must be performed at the same time and Rooney does not have the necessary labor force for both jobs. Indeed, it will be necessary to hire a new supervisor if either job is accepted. Furthermore, additional insurance will be required if either job is accepted. The revenue and costs associated with...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $530,000 and $730,000 B Normal probability distribution with a mean bid of $630,000 and a standard deviation of $43,000 If required, round your answers to three...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT