MS Project 2016
These Questions are about MS Project 2016.
Answer the questions:
1. How to update tasks in MS Project 2016?
2. How to use tasks and subtasks?
3. How to link and unlink tasks in MS Project?
4. How to set constraints and deadlines?
5. How to set project milestones?
6. How to complete the resource sheet?
Answer)
1. How to update tasks in MS Project 2016?
If there are several tasks in the project, then -
In View group, in the Task tab clock Gnatt Chart.
Hold CTRL and select each of the tasks.
In Schedule group click 0-25-50-75-100 (Choose the percentage complete) Complete
2. How to use tasks and subtasks?
A task can have many subtasks. In MS Project 2016, the indented task becomes a subtask of the task above it. The task is the summary task and the summary task is made up of subtasks.
Create a subtask -
In the Gantt Chart view
select the task.
click Task > Indent to turn the task into a subtask
3. How to link and unlink tasks in MS Project?
Creation of task dependencies is about linking tasks in MS Project.
Select one task, Hold the Ctrl key down, select the second task.
On the Task tab, in the Schedule group, click the chain link button, to link the tasks.
For unlinking the tasks,
select the tasks
click the icon that shows a broken chain.
The tasks will be unlinked.
4. How to set constraints and deadlines?
To add a constraint -
Double-click the task
Go to Advanced tab
Click on the Constraint type list arrow
Select a constraint type
Click on the Constraint date list arrow
Select a constraint date
And click ok.
To add a deadline -
Select the cell where you want the new column
Click Format tab
Click Insert Column button
Select Deadline
Click list arrow in the Deadline column
Select a deadline
5. How to set project milestones?
Set project milestones -
Click View
In the Task Views group, click the Gantt Chart
Type milestone name or select a task to turn into a milestone
Type 0 in the duration
Milestone added
6. How to complete the resource sheet?
Setting up the resources -
Click the View tab
Select Resource Views group and Click Resource Sheet
Click cell below the Resource Name heading
Enter the Resources as an individual person, job function or group.