Question

In: Finance

Massey Machine Shop is considering a four-year project to improve its production efficiency. Six months ago,...

Massey Machine Shop is considering a four-year project to improve its production efficiency. Six months ago, it contracted with Dr. Wright to provide a thorough study of whether there was a need for this four-year efficiency project. The report was delivered one month ago and it’s cost was $30,000. The report suggests that the company should go ahead with the project subject to Massey’s financial analysis. Buying a new machine press for $450,000 is estimated to result in $120,000 in annual pretax cost savings. The press falls in the MACRS five-year class and it will have a salvage value at the end of the project of $85,000. At time 0, the press will also require an additional investment in inventory of $9,000. Meanwhile, the accounts payable will increase by $3000. Every other current accounts remain the same. If the company’s tax rate is 20% and the discount rate is 12%, should the company accept the project? The MACRS schedule is as follows:

Year 5-year Class 1 at 20%, 2 at 32%, 3 at 19.2%, 4 at 11.52%, 5 at 11.52%, 6 at 5.76%

Solutions

Expert Solution


Related Solutions

Massey Machine Shop is considering a four-year project to improve its production efficiency. Six months ago,...
Massey Machine Shop is considering a four-year project to improve its production efficiency. Six months ago, it contracted with Dr. Wright to provide a thorough study of whether there was a need for this four-year efficiency project. The report was delivered one month ago and it’s cost was $30,000. The report suggests that the company should go ahead with the project subject to Massey’s financial analysis. Buying a new machine press for $450,000 is estimated to result in $120,000 in...
Massey Machine Shop is considering a four-year project to improve its production efficiency. Six months ago,...
Massey Machine Shop is considering a four-year project to improve its production efficiency. Six months ago, it contracted with Dr. Wright to provide a thorough study of whether there was a need for this four-year efficiency project. The report was delivered one month ago and it’s cost was $30,000. The report suggests that the company should go ahead with the project subject to Massey’s financial analysis. Buying a new machine press for $450,000 is estimated to result in $120,000 in...
Massey Machine Shop is considering a four year project to improve its production efficiency. Buying a...
Massey Machine Shop is considering a four year project to improve its production efficiency. Buying a new machine press for $730,000 is estimated to result in $220,000 in annual pretax cost savings. The press falls in the MACRS five year class, and it will have a salvage value at the end of the project of $89,000. The press also requires an initial investment in spare parts inventory of $26,000, along with an additional $3,000 in inventory for each succeeding year...
Massey Machine Shop is considering a four year project to improve its production efficiency. Buying a...
Massey Machine Shop is considering a four year project to improve its production efficiency. Buying a new machine press for $730,000 is estimated to result in $220,000 in annual pretax cost savings. The press falls in the MACRS five year class, and it will have a salvage value at the end of the project of $89,000. The press also requires an initial investment in spare parts inventory of $26,000, along with an additional $3,000 in inventory for each succeeding year...
Massey Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Massey Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $450,000 is estimated to result in $150,000 in annual pretax cost savings. The press falls in the MACRS five year class, and it will have a salvage value at the end of the project of $90,000. The press also requires an initial investment in spare parts inventory of $18,000, along with an additional $3,000 in inventory for each succeeding year of...
Massey Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Massey Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $570,000 is estimated to result in $240,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $96,000. The press also requires an initial investment in spare parts inventory of $30,000, along with an additional $3,500 in inventory for each succeeding year of the...
Massey Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Massey Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $450,000 is estimated to result in $150,000 in annual pretax cost savings. The press falls in the MACRS five year class, and it will have a salvage value at the end of the project of $90,000. The press also requires an initial investment in spare parts inventory of $18,000, along with an additional $3,000 in inventory for each succeeding year of...
CMS Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
CMS Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $545,000 is estimated to result in $97,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value of $70,000. The press also requires an initial working capital of $21,000, along with an additional $3,000 in working capital for each succeeding years of project. The tax rate is 34%, and the company's...
Geller Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geller Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $390,000 is estimated to result in $150,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $66,000. The press also requires an initial investment in spare parts inventory of $12,000, along with an additional $1,700 in inventory for each succeeding year of the...
Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a...
Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $490,847 is estimated to result in some amount of annual pretax cost savings. The press will have an aftertax salvage value at the end of the project of $86,695. The OCFs of the project during the 4 years are $175,493, $191,453, $170,805 and $167,265, respectively. The press also requires an initial investment in spare parts inventory of $25,940, along with...