In: Finance
Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $490,847 is estimated to result in some amount of annual pretax cost savings. The press will have an aftertax salvage value at the end of the project of $86,695. The OCFs of the project during the 4 years are $175,493, $191,453, $170,805 and $167,265, respectively. The press also requires an initial investment in spare parts inventory of $25,940, along with an additional $3,284 in inventory for each succeeding year of the project. The shop's discount rate is 6 percent. What is the NPV for this project?
Solution
Year 0 | Year 1 | Year 2 | Year 3 | Year 4 | |
Machine cost | (490,847) | ||||
Investment is sapres | (25,940) | ||||
Aftertax salvage value | 86,695 | ||||
Opearting cash flow | 175,493 | 191,453 | 170,805 | 167,265 | |
Inventory Investment | (3,284) | (3,284) | (3,284) | (3,284) | |
Total cash flow | 172,209 | 188,169 | 167,521 | 250,676 | |
Discounting factor@6% | 1 | 0.943 | 0.890 | 0.840 | 0.792 |
PV Of Cash Flows | (516,787) | 162,461 | 167,470 | 140,654 | 198,559 |
NPV | 152,357 | ||||
So NPV of the project is | $ 152,357 |