This is a point when an activity is either started or completed. Often used in conjunction with AOA networks, events consume no resources and have no time to completion associated with them. Select one: a. Event b. Milestone c. Task point d. Path
This is a network analysis technique used to determine the amount of scheduling flexibility (the amount of float) on various logical network paths in the project schedule network, and to determine the minimum total project duration. It involves the calculation of early (forward scheduling) and late (backward scheduling) start and finish dates for each activity. Select one: a. Program evaluation and review technique (PERT) b. Critical path method c. Project schedule d. Milestone path review
1. A. Event. This is a point when an activity is either started or completed. Often used in conjunction with AOA networks, events consume no resources and have no time to completion associated with them IS CALLED EVENT.
2. B. Critical path method. This is a network analysis technique used to determine the amount of scheduling flexibility (the amount of float) on various logical network paths in the project schedule network, and to determine the minimum total project duration. It involves the calculation of early (forward scheduling) and late (backward scheduling) start and finish dates for each activity IS CALLED Critical path method.