In: Operations Management
Which of the following is NOT a project constraint?(2 Points)
the budget
the customer requirements
the schedule
the technical specifications
all of the above are project constraints
All of the above are project constraints.
Project constraint means limitations of a project.
Budget is a project constraint. A limited budget for the completion
of a project is a big constraint.
Customer Requirement: If you successfully fulfill the customer
requirement then they will be happy. But if you are unable to meet
customer requirement within a due period of time and within a
limited price already decided by the customer, then it will affect
the project's success. So, customer requirement is a project
constraint.
the schedule: The schedule specifies the timelimit within which the
project will be delivered. So it's a constraint.
Technical specification is a project constraint because these
specifications follow from client requirement specification.
Quality, safety and performance are considered while analyzing
technical specification and a project should meet these factors to
satisfy customers.