In: Finance
A car manufacturer has been experiencing financial difficulties over the past few years. Sales have reduced significantly as a result of a worldwide economic recession. Costs have increased due to quality issues that led to a recall of some models of its cars.
Production volume last year was 50,000 cars and it is expected that this will increase by 4% per annum each year for the next five years.
The company directors are concerned to improve profitability and are considering two potential investment projects.
Project 1 – implement a new quality control process
The company has paid a consultant process engineer $50,000 to review the company’s quality processes. The consultant recommended that the company implement a new quality control process. The new process will require a machine costing $20,000,000. The machine is expected to have a useful life of five years and no residual value.
It is estimated that raw material costs will be reduced by $62 per car and that both internal and external failure costs from quality failures will be reduced by 80%.
Estimated internal and external failure costs per year without the new process, based on last year’s production volume of 50,000 cars, and their associated probabilities are shown below:
Internal Failure Costs External Failure Costs
$ Probability $ Probability
300,000 50% 1,300,000 60%
500,000 30% 1,900,000 30%
700,000 20% 3,000,000 10%
Internal and external failure costs are expected to increase each year in line with the number of car produced.
The company’s accountant has calculated that this investment will result in a net present value (NPV) of $1,338,000 and an internal rate of return of 10.5%.
Project 2 – in-house component manufacturing
The company could invest in new machinery to enable in-house manufacturing of a component that is currently made by outside suppliers. The new machinery is expected to cost $15,000,000 and have a useful life of five years and no residual value. Additional working capital of $1,000,000 will be required as a result of producing the component in-house.
The price paid to the current supplier is $370 per component. It is estimated that the in-house variable cost of production will be $260 per component. Each car requires one component. Fixed production costs, including machinery depreciation, are estimated to increase by $5,000,000 per annum as a result of manufacturing the component in-house.
Depreciation is calculated on a straight line basis.
Additional information
The company is unable to raise enough capital to carry out both projects. The company will therefore have to choose between the two alternatives.
Taxation and inflation should be ignored.
The company uses a cost of capital of 8% per annum.
Requirements
Project A Project B
NPV 1st 2nd
IRR 2nd 1st
Discuss potential reasons why the conflict between the NPV and IRR ranking may have arisen.
Project 1 | ||
1.Relevant cash flows that the accountant should have used for year 1 when appraising the project. | ||
Savings in Raw material costs | 50000*1.04*62= | 3224000 |
Savings in internal failure costs (Sum of Probabilities/50000*(50000*1.04)*80% | (((300000*50%)+(500000*30%)+(700000*20%))/50000*(50000*1.04))*80%= | 366080 |
Savings in external failure costs(Sum of Probabilities/50000*(50000*1.04)*80% | (((1300000*60%)+(1900000*30%)+(3000000*10%))/50000*(50000*1.04))*80%= | 1372800 |
Total relevant cash inflow(Savings) | 4962880 |
Project 2 – in-house component manufacturing | ||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
1.Initial cost of machinery | -15000000 | |||||
2.Additional wkg. Capital(introduced & recovered) | -1000000 | 1000000 | ||||
a.No.of cars to be produced | 52000 | 54080 | 56243 | 58493 | 60833 | |
3.Total Savings in variable costs at the rate of (370-260)=110 /car-------(a*$ 110) | 5720000 | 5948800 | 6186752 | 6434222 | 6691591 | |
4. Increase in fixed production costs (leaving out depreciation( $ 15000000/5 yrs.) ,as tax is to be ignored)ie.(5000000-3000000)=2000000 | -2000000 | -2000000 | -2000000 | -2000000 | -2000000 | |
5.Net annual cash flows(1+2+3+4) | -16000000 | 3720000 | 3948800 | 4186752 | 4434222 | 5691591 |
6. PV F at 8% (1/(1.08)^n | 1 | 0.92593 | 0.85734 | 0.79383 | 0.73503 | 0.68058 |
7. PV at 8% (5*6) | -16000000 | 3444444 | 3385460 | 3323579 | 3259286 | 3873601 |
8.NPV (Sum of Row 7) | 1286369.48 | |||||
9. IRR (of row 5) | 10.81% | |||||
Summary | NPV | IRR |
Project 1 | 1338000 | 10.50% |
Project 2 | 1286369 | 10.81% |
c. The company should choose Project 1 as its NPV is greater than that for Project 2 |
d.Potential reasons why the conflict between the NPV and IRR ranking may have arisen: |
Both NPV & IRR depend on the cash flows & their occurrence over |
1.different time-periods & |
2.of different magnitudes |
The more the difference in timing (ie. Year of occurrence) & quantum of cash flow (both inflow & outflow), the more will be the conflict between the rankings as per NPV/IRR |
Project 1 – implement a new quality control process | ||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Production volume | 52000 | 54080 | 56243 | 58493 | 60833 | |
1.Cost of machine | -20000000 | |||||
2.Savings in raw material costs at $ 62/ car | 3224000 | 3352960 | 3487078 | 3626562 | 3771624 | |
3.Savings in Internal failure costs(440000/50000*no.of cars*80%) | 366080 | 380723 | 395952 | 411790 | 428262 | |
4.Savings in External failure costs(1650000/50000*no.of cars*80%) | 1372800 | 1427712 | 1484820 | 1544213 | 1605982 | |
5.Net annual cash flows (CF0….CF5)(1+2+3+4) | -20000000 | 4962880 | 5161395 | 5367851 | 5582565 | 5805868 |
6.IRR (of Row CFs (0-5) in 5) | 10.43% | |||||
NPV calculations | ||||||
7.PV at 8% COC(1/1.08^n) | 1 | 0.92593 | 0.85734 | 0.79383 | 0.73503 | 0.68058 |
8.PV at 8%(CF0…CF5)*PVF (5*7) | -20000000 | 4595259 | 4425064 | 4261173 | 4103352 | 3951376 |
NPV (Sum of PVs in Row 8) | 1336225 | |||||
Workings for probable internal & external failure costs for production volume of 50,000 cars | ||||||
Probable costs | ||||||
Internal failure costs | ||||||
(300000*50%)+(500000*30%)+(700000*20%)= | 440000 | |||||
External failure costs | ||||||
(1300000*60%)+(1900000*30%)+(3000000*10%)= | 1650000 | |||||
Project 1 | ||||||
As per the accountant | 1338000 | 10.50% | ||||
As per above calculations | 1336225 | 10.43% | ||||
Minor differences in results for Project 1 | ||||||
But , still Project 1 scores over project 2 as its NPV is higher. | ||||||