In: Accounting
In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,072,000 | $ | 2,738,000 | $ | 2,849,000 | |||
Estimated costs to complete as of year-end | 5,328,000 | 2,590,000 | 0 | ||||||
Billings during the year | 2,160,000 | 2,650,000 | 5,190,000 | ||||||
Cash collections during the year | 1,880,000 | 2,700,000 | 5,420,000 | ||||||
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,072,000 | $ | 3,880,000 | $ | 3,280,000 | |||
Estimated costs to complete as of year-end | 5,328,000 | 3,180,000 | 0 | ||||||
|
Percentage completion method |
2018 |
2019 |
2020 |
|
Cost incurred in till previous year |
0 |
2072000 |
4810000 |
|
ADD |
Cost incurred during the year |
2072000 |
2738000 |
2849000 |
Total cost incurred till date |
2072000 |
4810000 |
7659000 |
|
ADD |
Estimated cost to be incurred |
5328000 |
2590000 |
0 |
Total estimated cost to be incurred |
7400000 |
7400000 |
7659000 |
|
Percentage of completion (A) |
28% |
65% |
100% |
|
(cost incurred till date /total estimated cost ) |
||||
Total revenue (B) |
10000000 |
10000000 |
10000000 |
|
Total revenue recognized (A *B) |
2800000 |
6500000 |
10000000 |
|
Less |
Revenue recognized in previous year |
0 |
2800000 |
6500000 |
revenue recognized in current year |
2800000 |
3700000 |
3500000 |
|
2018 |
2019 |
2020 |
||
Revenue |
2800000 |
3700000 |
3500000 |
|
Less |
Cost incurred |
2072000 |
2738000 |
2849000 |
Gross profit |
728000 |
962000 |
651000 |
B |
Percentage completion method |
2018 |
2019 |
2020 |
Cost incurred in till previous year |
0 |
2072000 |
5952000 |
|
ADD |
Cost incurred during the year |
2072000 |
3880000 |
3280000 |
Total cost incurred till date |
2072000 |
5952000 |
9232000 |
|
ADD |
Estimated cost to be incurred |
5328000 |
318000 |
0 |
Total estimated cost to be incurred |
7400000 |
6270000 |
9232000 |
|
Percentage of completion (A) |
28% |
94.92% |
100% |
|
(cost incurred till date /total estimated cost ) |
||||
Total revenue (B) |
10000000 |
10000000 |
10000000 |
|
Total revenue recognized (A *B) |
2800000 |
9492822.96 |
10000000 |
|
Less |
Revenue recognized in previous year |
0 |
2800000 |
9492822.96 |
revenue recognized in current year |
2800000 |
6692822.96 |
507177.04 |
|
2018 |
2019 |
2020 |
||
Revenue |
2800000 |
6692822.96 |
507177.04 |
|
Less |
Cost incurred |
2072000 |
3880000 |
3280000 |
Gross profit |
728000 |
2812822.96 |
-2772822.96 |