Question

In: Operations Management

A production  process at Kenneth day Manufacturing is show inthe figure below. The drilling operation...


A production  process at Kenneth day Manufacturing is show in the figure below. The drilling operation occurs separately  from , and simultaneously with the sawing and sanding ,which are independent sequential operations.  A product needs to go through only one of the three assembly operations ( the operations  are in parallel)

6 units/hrs

Sawing 


2.2 units/ hrs

Sanding

Drilling 

1.8 units/hr


Welding

5 units/hr



Assembly 

0.7 units/hr

Assembly 

0.7 units / hr

Assembly 

0.7 units/hr



A)..........Drilling  or Sanding or sawing or welding  or assembly?.  

B) The bottleneck time is .........minutes per unit (round your response to three decimal places)

C) the throughout time of the overall system is ...........minutes ( round your response to two decimal places)

D) If the firm operates 10 hours  per days ,20 days per month , the monthly   capacity   of the manufacturing process is ..........units (Enter your response as a whole number)



Solutions

Expert Solution

Effective capacity of assembly 0.7+0.7+0.7= 2.1 units per hour

Process

Capacity (units/hour)

Cycle Time in mins= 60 /capacity

Sawing

6

10.00

Sanding

2.2

27.27

Welding

5

12.00

Assembly

2.1

28.57

drilling

1.8

33.33

Answer a: Drilling is a bottleneck because it has a most cycle time

Answer b: bottleneck cycle time is 33.33 mins

Answer c: Throughput time is sum of all process times= sawing + sanding + welding + assembly =10+27.27+ 12+(60/0.7)= 134.98 mins

Answer d: total working hours= 20 days*10 hours per day= 200 hours per month

Production capacity= bottleneck capacity= 1.8 units per hour

Total production per month= total working hours* Production capacity= 200*1.8= 360 units per month


Related Solutions

Murray Manufacturing Corp. has the process displayed below. The drilling operation occurs separately from and simultaneously...
Murray Manufacturing Corp. has the process displayed below. The drilling operation occurs separately from and simultaneously with the sawing and sanding operations. The product only needs to go through one of the three assembly operations (the assembly operations are “parallel”). sawing 15 min/unit sanding 15 min/unit drilling 27 min/unit welding 25 min/unit assembly 78 min/unit a) Which operation is the bottleneck? (2.5 marks) b) What is the throughput time for the overall system? (2.5 marks) c) If the firm operates...
explain production process, manufacturing operation and service operation.
explain production process, manufacturing operation and service operation.
The figure above demonstrates a production process layout with eight machines. The table below shows their...
The figure above demonstrates a production process layout with eight machines. The table below shows their hourly productivity. A B C D E F G H 14 units/hr 14 units/hr 11 units/hr 13 units/hr 5 units/hr 12 units/hr 10 units/hr 10 units/hr How many units can this system produce in 874 hours if the productivity of machine B is increased to 19 units/hr? Please round your answer UP and do not use any units!
Consider the following sample of production volumes and total cost data for a manufacturing operation. Production...
Consider the following sample of production volumes and total cost data for a manufacturing operation. Production Volume (units) Total Cost ($) 400 4,000 450 4,900 550 5,400 600 6,000 700 6,300 750 6,900 This data was used to develop an estimated regression equation, ŷ = 1,305.33 + 7.44x, relating production volume and cost for a particular manufacturing operation. Use α = 0.05 to test whether the production volume is significantly related to the total cost. (Use the F test.) State...
Consider the following sample of production volumes and total cost data for a manufacturing operation. Production...
Consider the following sample of production volumes and total cost data for a manufacturing operation. Production Volume (units) Total Cost ($) 400 4,000 450 5,000 550 5,300 600 5,900 700 6,400 750 6,900 This data was used to develop an estimated regression equation, ŷ = 1,305.33 + 7.44x, relating production volume and cost for a particular manufacturing operation. Use α = 0.05 to test whether the production volume is significantly related to the total cost. (Use the F test.) (a)...
Consider the following sample of production volumes and total cost data for a manufacturing operation.
You may need to use the appropriate technology to answer this question. Consider the following sample of production volumes and total cost data for a manufacturing operation. Production Volume (units) Total Cost ($) 400 4,100 450 5,000 550 5,500 600 5,900 700 6,500 750 7,000 This data was used to develop an estimated regression equation, ŷ = 1,342.67 + 7.52x, relating production volume and cost for a particular manufacturing operation. Use α = 0.05 to test whether the production volume...
A food processing operation consists of mixing ingredients, forming and cooking. Figure below shows the cooking...
A food processing operation consists of mixing ingredients, forming and cooking. Figure below shows the cooking process where the formed material travels through a cooking oven on a conveyer belt. The raw material is subject to shrinkage due to the cooking process. The specification limits for shrinkage is between 5% and 9%. There are two machines operating two shifts daily. A technician selects samples before and after cooking process and calculates percent shrinkage. Table below shows the data set for...
A production process consists of a three-step operation. The scrap rate is 19 percent for the...
A production process consists of a three-step operation. The scrap rate is 19 percent for the first step and 7 percent for the other two steps. a.If the desired daily output is 455 units, how many units must be started to allow for loss due to scrap? (Do not round intermediate calculations. Round up your final answer to the next whole number.) Number of units             b.If the scrap rate for each step could be cut in half at...
A manufacturing process requires small amounts of glue. The glue used in the production process is...
A manufacturing process requires small amounts of glue. The glue used in the production process is classified as a(n) Select one: a. manufacturing overhead. b. administrative expense. c. supplies expense. d. period cost. e. direct material
A bill of materials is used in manufacturing and production to show all of the parts...
A bill of materials is used in manufacturing and production to show all of the parts and materials required to manufacture a specific item or for the subassembly of a finished product, such as a motorcycle. The information in the bill of materials is useful for determining product costs, coordinating orders, and managing inventory. It can also show how product costs will be affected by price changes in components or raw materials. This project provides you with an opportunity to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT