Question

In: Accounting

X Corporation, which uses a normal job costing system and dispose the over/under applied manufacturing overhead...

X Corporation, which uses a normal job costing system and dispose the over/under applied manufacturing overhead using write-off method, had two jobs in process at the start of 20x2: Job No. 59, WIP Balance$66,500Job No. 60, WIP Balance$139,500X applies manufacturing overhead on the basis of machine hours.At the beginning of the 20x2, X corporation estimated its manufacturing overhead during the first quarter would total $231,250and its budgeted machine hours would total 6250Manufacturing overhead incurred during the first quarter of 20x2 included following charges:Depreciation $20,000Indirect labor 50000Indirect materials used 4000Other factory costs128700The company worked on three jobs during the first quarter. Costs added during the first quarter were as follows:Job No.Direct MaterialDirect LaborMachine Hours59$18,000$45,000150060025,00010006137,00035,000?The manufacturing overhead account showed that overhead was overapplied by $34,100Job no. 59 and 60 were completed during the quarter, and X sold job no. 59 for $218,000.00Round your answers to the nearest dollar. Fill in the blank without $ or comma or period, e.g., 12345

How many machine hours were used by Job no. 61?

What was the gross margin of Job no. 59 after the adjustment of overapplied manufacturing overhead?

Solutions

Expert Solution

1. Predetermined overhead rate = Estimated manufacturing overhead / Budgeted machine hours

= 231,250 / 6,250 = $37 / hour

Actual overhead :

Depreciation...........................20,000

Indirect labor..........................50,000

Indirect materials used..........4,000

Other factory cost.................128,700

Total.......................................$202,700

As given in question overhead was overapplied by $34,100

So total applied overhead( 34,100 + 202,700) = 236,800

Need to find out machine houur of job no. 61

Assume machine hours taken by job 61 is X

236,800 = ( 1,500 + 1,000 + X ) * 37

6,400 = 2,500 + X

X = 6,400 - 2,500 = 3,900

So total hours taken by job 61 is 3,900 macine hours

Actual overhead rate ( 202,700 / ( 1,500 + 1,000 + 3,900) = $31.67 / hour

2. Cost of goods sold ( job. 59)

WIP opening balance.................................................66,500

Direct materials..........................................................18,000

Direct labor................................................................45,000

Applied overhead...............( 1500 * 37).....................55,500

( Machine hours * PDOH rate)

Overapplied overhead.......( 1500 * 31.67 - 37)........(7,995)

= Total.....................................................................$177,005

Gross margin of job no 59 = Sales revenue - Cost of goods sold = 218,000 - 177,005 = $40,995


Related Solutions

Lin Corporation uses a job order costing system and normal costing, with overhead being applied on...
Lin Corporation uses a job order costing system and normal costing, with overhead being applied on the basis of direct labor cost. There were no jobs in process at the start of the period. During the month, the company worked on 3 jobs, with the following information: Alpha Beta Gamma Direct Labor ($8/hour) $24,000 $8,800 Direct Materials $42,000 $61,000 Overhead Applied $23,940 $6,160 During the month, only job Alpha was completed and transferred to finished goods inventroy. The ending balance...
Curtis Inc. uses a job order costing system. Manufacturing overhead is applied on the basis of...
Curtis Inc. uses a job order costing system. Manufacturing overhead is applied on the basis of direct labor cost. Total manufacturing overhead was estimated to be $60,680 for the year; direct labor was estimated to total $151,700. Raw Materials Inventory (1/1) $ 10,700 (12/31) $ 13,700 Work in Process Inventory (1/1) $ 23,900 (12/31) $ 18,500 Finished Goods Inventory (1/1) $ 34,100 (12/31) $ 40,000 The following transactions have occurred during the year. Raw materials purchases $ 107,000 Direct materials...
Cadburn Corp. uses a job order costing system with manufacturing overhead applied to products on the...
Cadburn Corp. uses a job order costing system with manufacturing overhead applied to products on the basis of direct labor hours. For the upcoming year, Cadburn Corp. estimated total manufacturing overhead cost at $250,000 and total direct labor hours of 50,000. During the year actual manufacturing overhead incurred was $262,500 and 51,000 direct labor hours were used. a. Calculate the predetermined overhead rate. b. Calculate how much manufacturing overhead will be applied to production. c. Is overhead over- or underapplied?...
Tucson Co. uses a normal costing system. Factory (or Manufacturing) overhead is applied at a budgeted...
Tucson Co. uses a normal costing system. Factory (or Manufacturing) overhead is applied at a budgeted rate based on direct labor cost. At the end of the period, there are two unfinished jobs. Additional information is available as follows:                   Direct materials used                             $ 50,000                   Direct labor costs                                   $100,000                   Beginning Work-in-process inventory $100,000                   Cost of goods manufactured                  $150,000                   Beginning Finished goods inventory     $140,000                     Ending Finished goods inventory          $110,000                   Actual factory overhead incurred...
The company uses a job-order costing system in which overhead is applied to jobs on the...
The company uses a job-order costing system in which overhead is applied to jobs on the basis of direct labor cost. Its predetermined overhead rate is based on a cost formula that estimated $94,500 of manufacturing overhead for an estimated activity level of $45,000 direct labor dollars. At the beginning of the year, the inventory balances were as follows: Raw materials $ 10,800 Work in process $ 4,400 Finished goods $ 8,900 During the year, the following transactions were completed:...
Deer Lake Inc. uses a job order costing system with manufacturing overhead applied to products at...
Deer Lake Inc. uses a job order costing system with manufacturing overhead applied to products at a rate of 150% of direct labor cost. Treating each case independently, find the missing amounts (Input all amounts as positive values.): Case 1 Case 2 Case 3 Direct materials used $20,600 $10,000 Direct labor $26,800 Manufacturing overhead applied $44,100 Total manufacturing costs $97,000 $30,000 Beginning Work in Process $10,300 $7,200 Ending Work in process $7,600 $9,500 Cost of goods manufactured $94,400 $34,100 Beginning...
Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently,...
Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine hours is used. Xania’s plant manager has heard that departmental overhead rates can offer significantly better cost assignments than a plantwide rate can offer. Xania has the following data for its two departments for the coming year: Department A Department B Overhead costs (expected) $80,000 $78,000 Normal activity (machine hours) 14,500 10,800 Required: 1. Compute a predetermined...
Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently,...
Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine hours is used. Xania’s plant manager has heard that departmental overhead rates can offer significantly better cost assignments than a plantwide rate can offer. Xania has the following data for its two departments for the coming year: Department A Department B Overhead costs (expected) $80,000 $83,000 Normal activity (machine hours) 16,000 2,800 Required: 1. Compute a predetermined...
Job Order Costing: Wadadli Products uses a job-order costing system Overhead costs are applied to jobs...
Job Order Costing: Wadadli Products uses a job-order costing system Overhead costs are applied to jobs on the basis of machine-hours. At the beginning of the year, management estimated that 170,000 machine-hours would be required for the periods estimated level of production. The company also estimated $212,500 of fixed manufacturing overhead expenses for the coming period and variable manufacturing overhead of $1.50 per machine hour. Required: 1. Compute the company’s predetermined overhead rate. 2. Assume that during the year of...
Erkens Company uses a job costing system with normal costing and applies factory overhead on the...
Erkens Company uses a job costing system with normal costing and applies factory overhead on the basis of machine hours. At the beginning of the year, management estimated that the company would incur $1,980,000 of factory overhead costs and use 66,000 machine hours. Erkens Company recorded the following events during the month of April: Purchased 180,000 pounds of materials on account; the cost was $5.00 per pound. Issued 120,000 pounds of materials to production, of which 15,000 pounds were used...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT