Question

In: Accounting

C. Gugusan Bintang Sdn Bhd (GBSB) produces customized products and assigns manufacturing costs using normal costing...

C. Gugusan Bintang Sdn Bhd (GBSB) produces customized products and assigns manufacturing costs using normal costing system. From its inception, GBSB has been using plantwide overhead rate based on direct labour hours (DLH) to assign manufacturing overhead costs to customer orders. Recently, as the amount of its indirect costs getting larger, the accounting department of GBSB was considering two options – (1) to change the allocation base to machine hours; (2) to use departmental rate. If the latter is chosen, machining and assembly departments would use machine hours and direct labour hours respectively. The following details are collected from GBSB’s 2019 production budget: Machining Department Assembly Department Manufacturing overhead RM3,400,000 RM1,820,000 Direct labour costs RM1,800,000 RM1,500,000 Direct labour hours 120,000 240,000 Machine hours 200,000 61,000 At the end of 2019, the actual manufacturing overhead costs were RM3,510,000 in Machining Department and RM2,125,000 in Assembly Department. Machine hours used by Machining Department is 215,000 whereas Assembly Department used 63,500 machine hours. REQUIRED: (a) Calculate the plantwide pre-determined overhead rate using the following bases: (i) Direct labour hours (1 Mark) (ii) Machine hours (1 Mark) (b) Discuss which of the two bases calculated at (a) would be a better basis for plantwide overhead rate. (c) Determine the departmental overhead rate for each department. (d) Explain why departmental overhead rate would be a better option. (e) Explain TWO (2) ways how overapplied or underapplied overhead being disposed. BKAM2013 MANAGEMENT ACCOUNTING 1

Solutions

Expert Solution

All amounts are in RM

(a)

Plant wide predetermined overhead rate

i. On direct labour hours

Overhead rate = Totall manufacturing overhead/Total labour hours

= (3,400,000 + 1,820,000)/(120,000+240,000)

= 14.5 per labour hour

ii. On machine hours

Overhead rate = Total manufacturing overhead/Total machine hours

= (3,400,000 + 1,820,000)/(200,000+61,000)

= 20 per machine hour

b)

Of the two basis calculated in (a), the manufacturing overhead costs in Assembly department is less compared to Machining department. The direct labour hours of assembly department are higher in Assembly department compared to manufacturing department. The machining hours of assembly department are less compared to Machining department. There is direct relationship between the machine hours and manufacturing overhead cost betwen departments. So it is better to allocate based on the Machine hours rate. (In machining department, overhead costs are higher than assembly department but labour hours are less in machine department compared bro assembly department. So labour hours is not a correct basis)

c)

Departmental overhead rate

For Machining department = Total manufacturing overhead costs/Total machine hours

= 3,400,000/200,000

= 17 per machine hour

For assembly department = Total manufacturing costs/labour hours

= 1,820,000/240,000

= 7.583

d)

Departmental overhead is a better option because it gives the correct basis of overhead rates. The machining department mainly uses machine hours for its work and the assembly department is more a labour oriented so uses labour hours. This gives a better overhead rates for absorption and thus helps in correct allocation of overhead costs to products.

e)

Overapplied or underapplied overheads are treated in of the two ways

1. They take the entire overapplied or underapplied overheads to Cost of goods sold. Treating them as period costs

2. They allocate the overapplied or underapplied overheads to Work in progess, Finished goods, Cost of goods sold based on on units in WIP, Units in Finished goods inventory, Units sold. Here we are treating it as product cost.


Related Solutions

Famay Sdn Bhd (FSB) is a manufacturing company that produces high-technology electrical products. One of the...
Famay Sdn Bhd (FSB) is a manufacturing company that produces high-technology electrical products. One of the items used in the product is component M-2712. Each month, 10 units of M-2712 is required in production. Currently, component M-2712 is produces internally with the following costs incurred: Direct material RM500 Direct labor RM4,000 Manufacturing overhead 150% of direct labor Material handling 20% from direct material Additional information related to production of M-2712 are as below: i. Material handling is a separate charge...
PlayTime Co produces Swingsets and assigns its costs using the process costing system. For the month...
PlayTime Co produces Swingsets and assigns its costs using the process costing system. For the month of January, the following information was provided regarding units processed: Units Completed and Transferred Out 15,000 units Units in Ending Inventory 2,000 units The units in ending work in process inventory were 30% complete with respect to direct materials and 55% complete with respect to conversion costs. In addition, PlayTime Co had the following costs associated with their product in the month of January:...
Rose Sdn. Bhd. (RSB) produces two products, which are Standard and Advanced. The followings are the...
Rose Sdn. Bhd. (RSB) produces two products, which are Standard and Advanced. The followings are the budgeted units to be produced by RSB for 2019: Standard (units) Advanced (units) Total Units July April 7,000 12,000 19,000 August May 8,000 13,000 21,000 September June 9,000 14,000 23,000 October July 10,000 15,000 25,000 It takes 3 pounds of direct materials to produce the Standard product and 4 pounds of direct materials to produce the Advanced product. It is the company's policy to...
Air and Breeze Co produces Ceiling Fans and assigns its costs using the process costing system....
Air and Breeze Co produces Ceiling Fans and assigns its costs using the process costing system. For the month of January, the following information was provided regarding units processed: Units Completed and Transferred Out 12,000 units Units in Ending Inventory 3,000 units The units in ending work in process inventory were 30% complete with respect to direct materials and 55% complete with respect to conversion costs. In addition, Air and Breeze Co had the following costs associated with their product...
Air and Breeze Co produces Ceiling Fans and assigns its costs using the process costing system....
Air and Breeze Co produces Ceiling Fans and assigns its costs using the process costing system. For the month of January, the following information was provided regarding units processed: Units Completed and Transferred Out 12,000 units Units in Ending Inventory 3,000 units The units in ending work in process inventory were 30% complete with respect to direct materials and 55% complete with respect to conversion costs. In addition, Air and Breeze Co had the following costs associated with their product...
Sinary Maju Sdn. Bhd. is a manufacturing company that produces plastic ware product. This company operates...
Sinary Maju Sdn. Bhd. is a manufacturing company that produces plastic ware product. This company operates a variances accounting system. Each unit of the product has the following standard requirements: Description Quantity Price per unit RM Direct material 20 kgs RM2 per kg 40 Direct labour 10 hours RM5 per hour 50 Variable overhead 10 hours RM3 per hour 30 Annual budgeted fixed overhead are RM864,000. Budgeted production of plastic ware product is 1,800 units. The following actual data was...
Kawan Sdn Bhd (KSB) produces three products (X1, X2 and X3) from the same resources (but...
Kawan Sdn Bhd (KSB) produces three products (X1, X2 and X3) from the same resources (but in different quantities). Extract from the original budget for Month of December are shown below: Products X1   X2   X3 Selling price (RM per unit) 24   41   42 Total cost (RM per unit) 20   20   35 Labour hours per unit 0.5   2   1.5 Machine hours per unit 0.5   2   0.75 Production and sales (unit)   5,000   6,000   11,000 Variable costs are 40% of the total cost...
IT Excel Sdn. Bhd., a manufacturing company that produces a computer component leases a building for RM250,000 per year for its manufacturing facilities.
IT Excel Sdn. Bhd., a manufacturing company that produces a computer component leases a building for RM250,000 per year for its manufacturing facilities. In addition, the machinery in this building is being paid for in installments of RM50,000 per year. Each unit of the product produced costs RM40 in labor and RM20 in materials. The variable costs are estimated at 60 percent of total revenue.(a) Determine the price per unit of the product(b) Calculate the quantity at which the manufacturer...
Abam Sdn Bhd (ASB) produces Cewee Hand Sanitizer and uses process costing system. Cewee Hand Sanitizer...
Abam Sdn Bhd (ASB) produces Cewee Hand Sanitizer and uses process costing system. Cewee Hand Sanitizer passes through two processing departments: Mixing and Bottling. Liquid materials are blended in the Mixing Department and the resulting product is sent to Bottling Department, where its filled into 100 gram-plastic bottle. ASB uses the FirstIn, First-Out (FIFO) method in its process costing system. The information relates to the Mixing Department for the month of February 2020 is as follows: Beginning inventory of Work...
Describe the flow of manufacturing costs in a normal job costing system.
Describe the flow of manufacturing costs in a normal job costing system.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT