Material Sampling – Analyzing Direct Material You are reviewing a cost proposal, which includes an $800,200...

Material Sampling – Analyzing Direct Material

You are reviewing a cost proposal, which includes an $800,200 direct material estimate. After initial examination of the proposal, you note that there are 500 material items, but you also note that 20 high-cost items account for $620,000 of the total. The remaining $180,200 is spread across 480 relatively small purchases.

Answer the following questions:

1. Examination of the 20 high-cost items (estimated at $620,000) shows that all are properly priced except one item. That item is overpriced by $20,000. What should be your objective for these 20 items?

2. After analyzing a sample of the remaining 480 items, you find that the sample is overpriced by six percent. Using this six percent decrement factor, what cost should you estimate for those items? Remember that the average sample item cost is 106 percent of what it ought to be.

3. Given your answers to Questions 1 and 2, what should you estimate for total material cost?

Solutions

Expert Solution

Answer:

1)

These are to be checked thoroughly for its quantity and price since these high cost items are contributing 78% of total costs for 4% of total number of items. The actual requirement of these items should be determined properly and the produduction process of the same should be properly scrutenized to ensure that no wastage or loss occurs in these items. Any item overpriced should be corrected as it will make a huge difference to the total costs.

2)

Remaining items are only 22% of total costs for 96% items. These are to be sample checked and the actual quantity and price should be ensured. The sample taken indicated that these are overpriced by 6%. This increase doesn’t justify full checking; however the proposal should be asked for correction for over-charged items, with a note that all remaining items should be rechecked for its quantity and price.    

Using this 6% decrement factor, the cost we estimate for those items will be $170,000.

3)

Total material cost would be $ 170000 + $ 600000 = $ 770000

NOTE:: I HOPE YOUR HAPPY WITH MY ANSWER......**PLEASE SUPPORT ME WITH YOUR RATING......

**PLEASE GIVE ME "LIKE".....ITS VERY IMPORTANT  FOR,ME......PLEASE SUPPORT ME .......THANK YOU


Related Solutions

You are reviewing a cost proposal, which includes an $800,200 direct material estimate. After initial examination...
You are reviewing a cost proposal, which includes an $800,200 direct material estimate. After initial examination of the proposal, you note that there are 500 material items, but you also note that 20 high-cost items account for $620,000 of the total. The remaining $180,200 is spread across 480 relatively small purchases. Answer the following questions: 1. Examination of the 20 high-cost items (estimated at $620,000) shows that all are properly priced except one item. That item is overpriced by $20,000....
Selling price is $10/tin. The cost is $8/tin This includes $6 of direct material and $1.50...
Selling price is $10/tin. The cost is $8/tin This includes $6 of direct material and $1.50 of direct labor. Direct labor is 1 hour per 100 tins. Annual manufacturing overhead is estimated at $100,000 for the expected sales of 200,000 tins. The breakdown for manufacturing overhead includes 85% of variable costs. d. The Controllable Variance is $3250 Unfavorable. What was the total dollar amount for actual manufacturing overhead? e. Explain the calculation of the total standard hours allowed for actual...
Selling price is $10/tin. The cost is $8/tin This includes $6 of direct material and $1.50...
Selling price is $10/tin. The cost is $8/tin This includes $6 of direct material and $1.50 of direct labor. Direct labor is 1 hour per 100 tins. Annual manufacturing overhead is estimated at $100,000 for the expected sales of 200,000 tins. The breakdown for manufacturing overhead includes 85% of variable costs. 1a. What is the standard fixed manufacturing overhead cost per tin? b. The Volume Variance is $750 Favorable. How many units were actually produced during the year? c. How...
You are analyzing a proposal to build a new plant. Use the following information, a cost...
You are analyzing a proposal to build a new plant. Use the following information, a cost of capital of 14%, a capital gains tax rate of 5%, and an income tax rate of 40%. Land for the plant will be purchased today for $500. At the beginning of the second year (one year from today), $1,000 will be spent for the construction of the building. The equipment will be purchased at the beginning of the third year at a cost...
Material and Labor Variances The following actual and standard cost data for direct material and direct...
Material and Labor Variances The following actual and standard cost data for direct material and direct labor relate to the production of 2,000 units of a product: Actual Costs Standard Costs Direct material 4,200 lbs. @ $4.90 4,000 lbs. @ $5.20 Direct labor 5,700 hrs. @ $9.30 6,000 hrs. @ $9.50 Determine the following variances: Do not use negative signs with any of your answers. Next to each variance answer, select either "F" for Favorable or "U" for Unfavorable. Materials...
Drake Corporation is reviewing an investment proposal. The initial cost and estimates of the book value...
Drake Corporation is reviewing an investment proposal. The initial cost and estimates of the book value of the investment at the end of each year, the net cash flows for each year, and the net income for each year are presented in the schedule below. All cash flows are assumed to take place at the end of the year. The salvage value of the investment at the end of each year is equal to its book value. There would be...
Drake Corporation is reviewing an investment proposal. The initial cost and estimates of the book value...
Drake Corporation is reviewing an investment proposal. The initial cost and estimates of the book value of the investment at the end of each year, the net cash flows for each year, and the net income for each year are presented in the schedule below. All cash flows are assumed to take place at the end of the year. The salvage value of the investment at the end of each year is equal to its book value. There would be...
Drake Corporation is reviewing an investment proposal. The initial cost is $107,100. Estimates of the book...
Drake Corporation is reviewing an investment proposal. The initial cost is $107,100. Estimates of the book value of the investment at the end of each year, the net cash flows for each year, and the net income for each year are presented in the schedule below. All cash flows are assumed to take place at the end of the year. The salvage value of the investment at the end of each year is assumed to equal its book value. There...
Drake Corporation is reviewing an investment proposal. The initial cost and estimates of the book value...
Drake Corporation is reviewing an investment proposal. The initial cost and estimates of the book value of the investment at the end of each year, the net cash flows for each year, and the net income for each year are presented in the schedule below. All cash flows are assumed to take place at the end of the year. The salvage value of the investment at the end of each year is equal to its book value. There would be...
Drake Corporation is reviewing an investment proposal. The initial cost is $105,700. Estimates of the book...
Drake Corporation is reviewing an investment proposal. The initial cost is $105,700. Estimates of the book value of the investment at the end of each year, the net cash flows for each year, and the net income for each year are presented in the schedule below. All cash flows are assumed to take place at the end of the year. The salvage value of the investment at the end of each year is assumed to equal its book value. There...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT