Question

In: Accounting

A new chemical plant will be constructed. The following data is used for this construction. Using...

A new chemical plant will be constructed. The following data is used for this construction. Using this data;

  1. Draw the Cumulative Cash Flow Diagram for Nondiscounted and Discounted after-tax cash flows.
  2. Define the profitability criteria for each Cash Flows (Nondiscounted and Discounted)
  3. Calculate and show, PBP, CCP, CCR, ROROI, DPBP, NPV, DCFROR on the Cash Flow Diagram.

DATA:

Cost of Land, L           : 5x106 TL

FCI, during year 1       : 7x106 TL

FCI, during year 2       : 30x106 TL

FCI, during year 3       : 50x106 TL

Plant start-up at the end of year 3

Working Capital          : 20x106 TL at the end of year 3

Yearly sales revenue (after start-up) : R = 80 x106 TL per year

Cost of Manufacturing excluding depreciation allowance(after start-up):

COM =40 x106TL per year

Taxation rate, t = 30%

Salvage value of the plant, S = 5x106 TL

Total Project life : 8 years

Depreciation: Use 3 years after start-up

Depreciation = d = (FCI-Salvage value)/n

Discount rate = 20%

CCR= 1 + (CCP/(Land+WC+FCIL) or

CCR = (sum of all positive cash flows/ sum of all negative cash flows)

ROROI = Average annual net profit/ FCIL

PVR = (present value of all positive cash flows/ present value of all negative cash flows)

Net Profit = (R-COM-d)(1-t)+d

Solutions

Expert Solution


Related Solutions

Using arduino 1 In a certain chemical processing plant, a liquid chemical element is used in a manufacturing process.
 Using arduino 1  In a certain chemical processing plant, a liquid chemical element is used in a manufacturing process. This chemical element is stored in three different tanks. A level sensor in each tank according to the figure generates a HIGH level voltage when the liquid level in the tank falls below 25%. Design a circuit with Arduino to monitor the level of the chemical element that will trigger an alarm when the level of AT LEAST 2 tanks drops...
            The Fukushima Power plant is planning construction of a new plant to generate electricity four...
            The Fukushima Power plant is planning construction of a new plant to generate electricity four years hence and must decide now between a small, medium, or large-sized plant. The exact size needed is uncertain because future demands can only be estimated. Forecasters have estimated future demands and their likelihoods as follows: Level of Demand Probability High 0.30 Medium 0.55 Low 0.15 In the following, all the future costs and earnings have been adjusted to their present worth: If a...
Microwave Oven​ Programming, Inc. is considering the construction of a new plant. The plant will have...
Microwave Oven​ Programming, Inc. is considering the construction of a new plant. The plant will have an initial cash outlay of ​$12 ​million, and will produce cash flows of ​$4 million at the end of year​ 1, $ 5 million at the end of year​ 2, and ​$3 million at the end of years 3 through 5. What is the internal rate of return on this new​ plant?
(10 pts) Brower, Inc. just constructed a manufacturing plant in Europe. The construction cost 10 million...
(10 pts) Brower, Inc. just constructed a manufacturing plant in Europe. The construction cost 10 million Euros. Brower intends to leave the plant open for three years. During the three years of operation, Euro cash flows are expected to be 1 million euros, 2 million euros, and 3 million euros, respectively. Operating cash flows will begin one year from today and are remitted back to the parent at the end of each year. At the end of the third year,...
Brower, Inc. just constructed a manufacturing plant in Europe. The construction cost 10 million Euros. Brower...
Brower, Inc. just constructed a manufacturing plant in Europe. The construction cost 10 million Euros. Brower intends to leave the plant open for three years. During the three years of operation, Euro cash flows are expected to be 1 million euros, 2 million euros, and 3 million euros, respectively. Operating cash flows will begin one year from today and are remitted back to the parent at the end of each year. At the end of the third year, Brower expects...
Zolar, Inc, just constructed a manufacturing plant in Canada. The construction cost 9 billion Canadian dollar....
Zolar, Inc, just constructed a manufacturing plant in Canada. The construction cost 9 billion Canadian dollar. Zolar intends to leave the plant open for 3 years. During the 3 years of operation, dollar cash flows are expected to be 3 billion dollar, 3 billion dollar and 2 billion dollar respectively. Operating cash flows will begin one year from today and are remitted back to the parent at the end of each year. At the end of the third year, Zolar...
Your company is using a plant of size 10,000 sq. ft. that was constructed in 2006...
Your company is using a plant of size 10,000 sq. ft. that was constructed in 2006 for $300,000. The cost indices that correspond to this size of a plant for 2006 and 2014 are 145 and 186 respectively. If the power-sizing exponent is 0.55, how much would it cost to build a 40,000 sq. ft. warehouse in 2014? Note: Answer would be $816,026. Please include complete explanation and step-by-step solution.
On January 1, 2015, the Crocus Company began construction of a new manufacturing plant. The plant...
On January 1, 2015, the Crocus Company began construction of a new manufacturing plant. The plant was completed on December 31, 2016. Expenditures on the project were as follows (in $ millions): January 1, 2015 $1 July 1, 2015 54 October 1, 2015 22 February 1, 2016 30 April 1, 2016 21 September 1, 2016 20 December 31, 2016 6 On January 1, 2015, Crocus obtained a $60 million construction loan with a 6% interest rate. The loan was outstanding...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021. Expenditures on the project were as follows ($ in millions): July 1, 2020 54 October 1, 2020 22 February 1, 2021 30 April 1, 2021 21 September 1, 2021 20 October 1, 2021 6 On July 1, 2020, Crocus obtained a $70 million construction loan with a 6% interest rate. The loan was outstanding through the end of...
A power plant is planning construction of a new plant to generate electricity four years hence...
A power plant is planning construction of a new plant to generate electricity four years hence and must decide now between a small, medium, or large-sized plant. The exact size needed is uncertain because future demands can only be estimated. Forecasters have estimated future demands and their likelihoods as follows: Level of Demand Probability High 0.30 Medium 0.55 Low 0.15             In the following, all the future costs and earnings have been adjusted to their present worth: The capacity of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT