Question B.1
A company has the following master schedule (Table B.1) and master file (Table B.2) for its most popular Lapdesk.
Table B.1 Master Production Schedule
Week |
1 |
2 |
3 |
4 |
5 |
6 |
Lapdesk |
400 |
300 |
450 |
330 |
450 |
400 |
Table B.2 Master file
Lapdesk |
Pressboard |
|
On hand |
200 |
300 |
On order |
100(week 2) |
0 |
LLC |
0 |
1 |
Lot Size |
L4L |
Mult 100 |
Lead Time |
1 |
1 |
Each lapdesk has two pressboards. Use MRP to schedule planned order releases for Lapdesk and pressboard.
This question is 25 marks out of 150 in total in a level 6 exam, please consider this when compiling an answer, any additional workings out or extra comments/explanations will receive positive feedback, thank you in advance, the more clear and more descriptive the better. (please note positive review will follow if answer is of high standards)
Below is the MRP plan based on the details given:
Item: Lapdesk | ||||||
LT= 1 week | Lot size: L4L | |||||
Week | 1 | 2 | 3 | 4 | 5 | 6 |
Gross requirements | 400 | 300 | 450 | 330 | 450 | 400 |
Scheduled orders | 100 | |||||
On hand inventory: 200 | 300+200-400-100=0 | 0 | 0 | 0 | 0 | |
Net requirement | 300+200-100=400 | 450 | 330 | 450 | 400 | |
Planned Order Receipt | 400 | 450 | 330 | 450 | 400 | |
Planned Order Release | 400 | 450 | 330 | 450 | 400 | |
Backorders | 400-200=200 | |||||
Item: Pressboard | ||||||
2 units of Pressboard needed for 1 unit of Lapdesk | LT= 1 week | Lot size: Mult 100 | ||||
Week | 1 | 2 | 3 | 4 | 5 | 6 |
Gross requirements | 400*2=800 | 450*2=900 | 330*2=660 | 450*2=900 | 400*2=800 | |
Scheduled orders | ||||||
On hand inventory: 300 | 0 | 700-660=40 | 900+40-900=40 | 800+40-800=40 | 40 | |
Net requirement | 500+900=1400 | 660 | 900-40=860 | 800-40=760 | ||
Planned Order Receipt | 1400 | 700 | 900 | 800 | ||
Planned Order Release | 1400 | 700 | 900 | 800 | ||
Backorders | 800-300=500 |