Question

In: Operations Management

The Trump Tower is a 72-story luxury condominium building constructed at Springfield Plaza in Manhattan, New...

The Trump Tower is a 72-story luxury condominium building constructed at Springfield Plaza in Manhattan, New York. Before the building was constructed, Smithers Limited Partnership (Smithers LP) began selling condominiums at the building. The condominium offering plan required a nonrefundable down payment of 25 percent of the purchase price. The purchase contract provided that if a purchaser defaulted and did not complete the purchase, Smithers LP could keep the 25 percent down payment as liquidated damages. Homer and Marge Simpson each contracted to purchase two condominium units on the top floors of the building. Both Marge and Homer were represented by attorneys. Over the course of two years, while the building was being constructed, the Simpsons paid the 25 percent nonrefundable down payment of $8 million.

On September 11, 2001, before the building was complete, terrorists attacked Manhattan by flying two planes into nearby landmarks, murdering thousands of people. Marge and Homer sent letters to Smithers LP, rescinding their purchase agreements because of the terrorist attack that occurred on September 11. Thus, Smithers LP terminated the four purchase agreements and kept the 25 percent down payments on the four condominiums as liquidated damages. Marge and Homer sued Smithers LP, alleging that the money should be returned to them. However, Smithers LP defended, arguing that the 25 percent nonrefundable down payment was an enforceable liquidated damages clause. Is the liquidated damage clause enforceable? Explain.

Solutions

Expert Solution

To be the liquidated damage clause enforceable, it should meet the criteria given below.

(a) Damages caused by the breach of contract are difficult to estimate.

(b) The amount is reasonable and is not intended to punish the buyer.

In the case, none of the criteria is met, because no financial damage was caused by the refusal of the parties to buy the condos. The amount of $8 Million is by no means reasonable and is intended to punish the buyer and an attempt to swindle his / her money. Considering above facts, the case is not liquidated damage clause enforceable.


Related Solutions

Design a staircase for a two story building with the given loads: DL = 72 psf...
Design a staircase for a two story building with the given loads: DL = 72 psf LL = 60 psf The building floor height = 8ft for a total height of 16 ft. The staircase design must comply with the A.D.A. requirement for a hospital building. Design calculations must be in english units (ft, inches, pnds etc).
Design a staircase for a two story building with the given loads DL = 72 psf...
Design a staircase for a two story building with the given loads DL = 72 psf and LL= 60 psf. The staircase design must comply with A.D.A. requirements for hospital buildings.
A new office building has been constructed at a cost of $3,000,000. It is estimated to...
A new office building has been constructed at a cost of $3,000,000. It is estimated to have a life of 50 years with a value at that time of $200,000. It will have maintenance costs of $10,000 per year. It will also have major repairs costing $80,000 that occur at years 10, 20, 30 and 40. It will have additional repairs at the end of year 25 costing $250,000. Determine the equivalent uniform annual cost if the rate of interest...
A new office building has been constructed at a cost of $3,000,000. It is estimated to...
A new office building has been constructed at a cost of $3,000,000. It is estimated to have a life of 50 years with a value at that time of $200,000. It will have maintenance costs of $10,000 per year. It will also have major repairs costing $80,000 that occur at years 10, 20, 30 and 40. It will have additional repairs at the end of year 25 costing $250,000. Determine the equivalent uniform annual cost if the rate of interest...
You are the new CM for a 2 story OFFICE building that is lagging behind by...
You are the new CM for a 2 story OFFICE building that is lagging behind by the following: Wall framing in upper floor is incomplete and needs 2 more days to complete. Doors for installation first floor have not been delivered. Painting contractor crew cannot start painting since floor is not clear of debris ect. Foreman has left due to family emergency. Electrical contractor is 3 days behind. Give your interpretation of how you will approach this situation and provide...
3.8 Bright Horizons Skilled Nursing Facility, an investor-owned company, constructed a new building to replace its...
3.8 Bright Horizons Skilled Nursing Facility, an investor-owned company, constructed a new building to replace its outdated facility. The new building was completed on January 1, 2015, and Bright Horizons began recording depreciation immediately. The total cost of the new facility was $18,000,000, comprising (a) $10 million in construction costs and (b) $8 million for the land. Bright Horizons estimated that the new facility would have a useful life of 20 years. The salvage value of the building at the...
3.8 Bright Horizons Skilled Nursing Facility, an investor-owned company, constructed a new building to replace its...
3.8 Bright Horizons Skilled Nursing Facility, an investor-owned company, constructed a new building to replace its outdated facility. The new building was completed on January 1, 2015, and Bright Horizons began recording depreciation immediately. The total cost of the new facility was $18,000,000, comprising (a) $10 million in construction costs and (b) $8 million for the land. Bright Horizons estimated that the new facility would have a useful life of 20 years. The salvage value of the building at the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT