Internal rate of return and modified internal rate of
return.
Quark Industries has three potential projects, all with an
initial cost of $1,600,000.
Given the discount rate and the future cash flow of each project
in the following table,
Cash Flow Project M Project N Project O
Year 1 $400,000 $500,000 $900,000
Year 2 $400,000 $500,000
$700,000
Year 3 $400,000 $500,000 $500,000
Year 4 $400,000 $500,000 $300,000
Year 5 $400,000 $500,000 $100,000
Discount rate 9% 14% 17%