Schematic drawings and cost estimates are characteristics of which phase found in the facility construction process?
Group of answer choices
Programming Phase
Construction Phase
Occupancy Phase
Design Phase
Schematic drawings and cost estimates are characteristics of which phase found in the facility construction process?
Answer : Design Phase
Explanation to the answer :
What does design phase include : read below -
Normally, the conception of the project starts with the client. This is where the dream begins as well as the research for the right location and the specifications/standards that should be followed.Depending on the project, the conception stage might vary. It can take anywhere from a few days to a few months or more, depending on how imminent is the need for the completion of the project.It goes without saying that construction workers usually don’t have much input during this stage, as the ball is still in the hands of the project owner.
Once the project is closer to fruition, it is time to sit down and talk design. This is still a preliminary stage, which means that nothing is guaranteed at this point. Nevertheless, design is the stage where usually the bidding process begins.The team that is in charge of the design, led by an architect or an engineer, will need to make sure that each of the state regulations and codes is met while respecting the vision of the project owner as well as ensuring that the newly built structure will be usable.
There are normally four different steps within the design stage and they include programming and feasibility, schematic design, design development, and contract documents.During the programming and feasibility step, each of the objectives and goals of the project has to be outlined. Numerous decisions are made at this stage, including how large the building will be, how space will be used, and how many rooms will be needed.
The schematic design is a sketch that will show the space as well as materials, colors, and even textures. That sketch will be used during the design development to research the equipment needed, along with the cost for them and the materials being used.Once the contract documents are drawn up, everything is close to being finalized, because they contain the final drawings and specifications. These documents are used in the construction field by those placing bids to work on the project.