In: Accounting
Given the following information:
Budget Actual
Units produced 10,000 10,010
Materials (kg) 400 405
Direct Labour (Hours) 35,000 37,010
Material Costs $8,000 ?
Direct Labour Costs $385,000 $408,960
Variable Overhead Costs $350,000 $370,000
Fixed Overhead Costs $160,000 $136,358
Other Information
Overhead is Allocated on Direct Labour Hours
During the year, 500 kg of materials were purchased for $9,000
Beginning Inventory: none
Ending Inventory: 95kg
Required:
Calculate the following variances
A. | Material rate variance=Actual quantity consumed*(Standard rate of material-Actual rate of material) | ||||||
If the answer is positive, variance is favorable.Otherwise unfavorable. | |||||||
Actual quantity consumed=405 Kg. | |||||||
Standard rate of material=Budgeted material costs/Budgeted materials in Kg.=8000/400=$20 per Kg. | |||||||
Actual rate of material=Actual material purchase cost/Actual materials purchased in Kg.=9000/500=$ 18 per Kg. | |||||||
Material rate variance=405*(20-18)=$ 810 Favorable | |||||||
B. | Material efficiency variance=Standard rate of material*(Standard quantity -Actual quantity consumed) | ||||||
If the answer is positive, variance is favorable.Otherwise unfavorable. | |||||||
Standard rate of material=Budgeted material costs/Budgeted materials in Kg.=8000/400=$20 per Kg. | |||||||
Standard quantity=Actual units produced*material required per unit | |||||||
Material required per unit=Budgeted materials in Kg./Budgeted units produced=400/10000=0.04 Kg per unit | |||||||
Standard quantity=10010*0.04=400.4 Kg. | |||||||
Actual quantity consumed=405 Kg. | |||||||
Material efficiency variance=20*(400.4 -405)=-92=$ 92 Unfavorable | |||||||
Actual material cost=Actual materials in Kg*Actual rate of material=405*18=$ 7290 | |||||||
C. | Labor price variance=Actual hours worked*(Standard rate of labor-Actual rate of labor) | ||||||
If the answer is positive, variance is favorable.Otherwise unfavorable. | |||||||
Actual hours worked=37010 | |||||||
Standard rate of labor=Budgeted direct labor cost/Budgeted direct labor hours=385000/35000=$ 11 per hour | |||||||
Actual rate of labor=Actual direct labor cost/Actual direct labor hours=408960/37010=$ 11.05 per hour | |||||||
Direct labor rate variance=37010*(11-11.05)=-1850.5=$ 1850.5 Unfavorable | |||||||
D. | Labor efficiency variance=Standard rate of labor*(Standard hours-Actual hours worked) | ||||||
If the answer is positive, variance is favorable.Otherwise unfavorable. | |||||||
Standard rate of labor=Budgeted direct labor cost/Budgeted direct labor hours=385000/35000=$ 11 per hour | |||||||
Standard hours=Actual units produced*standard hours required per unit | |||||||
Hours required per unit=Budgeted direct labor hours/Budgeted units produced=35000/10000=3.5 hours | |||||||
Standard hours=10010*3.5=35035 hours | |||||||
Actual hours worked=37010 hours | |||||||
Labor efficiency variance=11*(35035-37010)=-21725=$ 21725 unfavorable | |||||||