Answers in BOLD:
LCL=32, UCL= 47
Process is capable is Cp is more than 1
mean |
Standard deviation-sd |
Cp= (UCL-LCL)/6sd |
Cpk= Min [(mean-LCL)/3sd; (UCL-mean)/3sd] |
Capability |
|
Armand |
37 |
3 |
0.8333 |
0.5556 |
Not capable |
Jerry |
37 |
2 |
1.2500 |
0.8333 |
Capable |
Melissa |
39.5 |
1.8 |
1.3889 |
1.3889 |
Capable |